This is a Schedule of Items for a Request for Quote (RFQ) for the Gila National Forest Vault Toilet Decommission project (RFQ# 127EAX27Q0007). The solicitation requires contractors to furnish all equipment and labor to complete the project according to all specified terms, conditions, and specifications.

The schedule includes six base items and two optional items, all priced on a lump sum basis. Base items include: (1) demolition of Big Horn Campground toilet and decommissioning of San Fran Hot Springs toilet with concrete sidewalk removal and relocation to Bighorn CG; (2) demolition of Gomez Peak toilet with concrete sidewalk removal and decommissioning of Mogollon toilet with relocation to Gomez Peak; (3) demolition of Little Walnut Day Use toilet and decommissioning of Lower Gallinas CG toilet with relocation to Little Walnut Day Use Area; (5) demolition of Kingston Campground toilet; (6) demolition of Emory Pass Heliport fiberglass toilet structure and concrete foundation; and (8) installation of concrete slabs with "Van Horn Roll" at three CXT toilet units. Optional Item 4 involves demolition of Head of Ditch Campground North toilet and purchase/installation of a new CXT® Gunnison style precast concrete toilet building. Optional Item 7 requires purchase of a new CXT® Gunnison style toilet building and delivery to Fort Bayard Administrative Site. All pricing must include Federal, State, and Local taxes where applicable, with separate totals required for base items, optional items, and combined totals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gila National Forest Vault Toilet Decommission

SCHEDULE OF ITEMS

Solicitation RFQ# 127EAX27Q0007

Furnish all equipment and labor to complete the project according to all terms, conditions, and specifications.

CG = Campground LS = Lump Sum SY = Square Yard NA = Not Applicable

Base Item Item Description Type Unit Cost ($)

Demolish Big Horn CG toilet Romtec® LS Decommission San Fran Hot

Springs toilet, remove concrete sidewalk, and relocate toilet to

Bighorn CG

CXT® LS

Total $_______________

Item Description Type Unit Cost ($)

Demolish Gomez Peak toilet and remove 5- 5’x5’ sections of concrete sidewalk

Romtec® LS

Decommission Mogollon toilet & relocate to Gomez Peak

CXT® LS

Total $_______________

Item Description Type Unit Cost ($)

Demolish Little Walnut Day Use toilet

Romtec® LS

Decommission Lower Gallinas CG toilet & relocate to Little

Walnut Day Use Area

CXT® LS

Total $_______________

Base Item

Item Description Type Unit Cost ($)

Demolish Head of Ditch Campground North toilet

Romtec® LS

Purchase and install a new CXT® Gunnison style 6’6” x 14’8” (Brand Name or Equal)

Right Hand Screen, “Buckskin” color standard precast concrete toilet building for installation.

Installation location is at

Head of Ditch CG.

CXT® LS

Total $_______________

Item Description Type Unit Cost ($)

5 Demolish Kingston Campground toilet

Romtec® LS

Total $_______________

Item Description Type Unit Cost ($)

Demolish Emory Pass Heliport toilet

Fiberglass Structure, Concrete

Foundation

LS

Total $_______________

Item 4 is an OPTIONAL ITEM

Item Description Type Unit Cost ($)

Purchase a new CXT® Gunnison style 6’6” x 14’8”

(Brand Name or Equal) Right Hand Screen, “Buckskin” color standard precast concrete toilet building and deliver to Fort Bayard Administrative Site

(32.842075 ° X -109.140944 °)

CXT® LS

Item 7 Total $_______________

Item Description Type Unit Cost ($)

Install a 14’7-1/2” x 5’ x 4” thick concrete slab with “Van

Horn Roll” at each CXT toilet after installation, 3

CXT units in total.

NA SY

Item 8 Total $_______________

Item 7 is an OPTIONAL ITEM

Base Item

Base Items 1, 2, 3, 5, 6, 8 Total: $___________________

Optional Item 4, Total: $___________________

Optional Item 7, Total: $___________________

All Items Total (base + option): $___________________

Prices to include all taxes, including Federal, State, & Local where applicable.

File details come from the government source that posted it. Updated .