127EAX27Q0007_Gila Toilet Decommissioning.pdf

PDF 431 KB Posted

Attached to
Gila National Forest Vault Toilet Decommissioning
Solicitation number
127EAX27Q0007
Issued by

About this file

This is a Request for Quote (RFQ) for construction services issued by the USDA Forest Service for the Gila National Forest Toilet Decommissioning project (RFQ# 127EAX27Q0007). The solicitation requires contractors to furnish all materials, labor, equipment, supervision, tools, and utilities to demolish five existing vault toilets and decommission and relocate three CXT® style vault toilets at various locations within the Gila National Forest in New Mexico. Two optional line items are included: one involving the demolition of a single-user Romtec® vault toilet and procurement/installation of a new CXT® "Gunnison" toilet at Head of Ditch Campground, and a second for procurement and delivery only (without installation) of one CXT® toilet to Fort Bayard Administrative Site. Work locations include Big Horn Campground, Gomez Peak, Little Walnut Day Use Area, Kingston Campground, Emory Pass Heliport, and Lower Gallinas Campground.

The RFQ was issued October 20, 2026, with sealed quotes due November 17, 2026, at 12:00 PM Mountain Time, addressed to Melissa Heckenlaible at melissa.heckenlaible@usda.gov. A 20% bid bond is required with all quote submissions. The contractor must commence work within 10 calendar days of receiving notice to proceed and complete all work within 90 calendar days. Evaluation will be based on technical approach (including schedule capability, company experience, personnel qualifications, safety plan, demolition/relocation methods, and equipment), price (firm-fixed price for all line items), and past performance (acceptable or neutral rating required). Award will be made to the highest technically rated offeror with fair and reasonable pricing; award is not necessarily to the lowest bidder. The contract will include performance and payment bonds, and contractors must comply with construction wage rate requirements, Buy American provisions, and other applicable FAR and AGAR clauses. Questions may be submitted via email by October 29, 2026, at 12:00 PM Mountain Time.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1172722

USDA-FS CSA SOUTHWEST 7

333 BROADWAY BLVD SE

ALBUQUERQUE NM 87102-3498

7EAX

email only to:

Melissa Heckenlaible, Contract Specialist melissa.heckenlaible@usda.gov

MELISSA HECKENLAIBLE 304-715-2632

110/20/2026

127EAX27Q0007

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Gila National Forest Toilet Decommissioning

Furnish all materials, labor, equipment, supervision, tools, and utilities required to perform operations necessary to (A) demolish five (5) existing vault toilets and

(B) decommission, then relocate, three (3) CXT® style vault toilets at various locations.

One option item includes the demolition of one single user vault toilet and the procurement and installation of a new single user vault toilet at the same location. A second option is for the procurement and delivery of one toilet without installation.

There is no formal scheduled site visit for this requirement. See photos.

Requests for Information (RFI) are due Thursday, October 29, 2026, at 12:00PM noon

Mountain Time emailed to Melissa Heckenlaible at melissa.heckenlaible@usda.gov.

A bid bond of 20% is required to be included with any submitted quote package.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 90 calendar days and complete it within ________________ ________________ calendar days after receiving

11/17/2026

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA-FS CSA SOUTHWEST 7

333 BROADWAY BLVD SE

ALBUQUERQUE NM 87102-3498

7EAX

TROY A. MCCULLOUGH

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 13

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

127EAX27Q0007

Delivery: 90 Days After Notice to Proceed

Delivery Location Code: 8399

USDA FOREST SERVICE

GILA NATIONAL FOREST SUPERVISORS

3005 E CAMINO DEL BOSQUE

SILVER CITY NM 88061 US

Demolish Big Horn Campground toilet; Decommission

San Fran Hot Springs toilet, remove concrete sidewalk, and relocate to Bighorn Campground

Demolish Gomez Peak toilet and remove 5- 5'x 5' sections of concrete sidewalk; Decommission

Mogollon toilet relocate to Gomez Peak

Demolish Little Walnut Day Use toilet;

Decommission Lower Gallinas Campgound toilet and relocate to Little Walnut Day Use Area

OPTIONAL ITEM: Demolish Head of Ditch Campground

North toilet; Procure and install a new Gunnison style 6'6" x 14'8" (Brand Name or Equal) Right

Hand Screen, "Buckskin" color standard precast concrete toilet building for installation.

Installation location is Head of Ditch Campground.

(Option Line Item)

Demolish Kingston Campground toilet

Demolish Emory Pass Heliport toilet

OPTIONAL ITEM:Procure new CXT® Gunnison style 6'6" x 14'8" (Brand Name or Equal) Right Hand Screen,"Buckskin" color standard precast concrete toilet building and deliver to Fort Bayard Administrative Site (32.842075° X -109.140944°), delivery only, no installation (Option Line Item)

Install a 14'7-1/2" x 5' x 4" thick concrete slab with "Van Horn Roll" at each CXT toilet after installation, 3 CXT units in total.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

4 13

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

127EAX27Q0007

IPP:

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice

Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in the previous communications from USDA and Treasury.

All invoices are to be submitted via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S.

Department of Treasury and you can find more information at this website:

https://www.ipp.gov/index.htm.

Please make sure that your company has registered at:

https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account.

Payment documentation and process per (FAR

32.905). All invoices must include the following items:

*Name and address of the contractor.

*Invoice date and invoice number.

*Contract number or other authorization for supplies delivered.

*Description, quantity, unit of measure, unit price, and extended price of supplies delivered.

*Shipping and payment terms (e.g., shipment number and date of shipment, discount for prompt payment terms). Bill of lading number and weight of shipment will be shown for shipments on

Government bills of lading.

*Name and address of contractor official to whom payment is to be sent (must be the same as that in the contract or in a proper notice of assignment).

*Name, title, phone number, and mailing address of person to notify in the event of a defective invoice.

*Taxpayer Identification Number (TIN).

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Gila National Forest Toilet Decommissioning

RFQ# 127EAX27Q0007

Statement of Requirement Furnish all materials, labor, equipment, supervision, tools, and utilities required to perform operations necessary to demolish five existing vault toilets and to decommission and then relocate three other CXT® style vault toilets. There is one option item that includes the demolition of one single user Romtec® vault toilet and the procurement and installation of a new CXT® “Gunnison” single user vault toilet. A second option is to procure a toilet and have it delivered but with no installation.

See Attachment A – Statement of Work.

Schedule of Items See Attachment B - Schedule of Items.

Technical Data - Technical data and supporting documentation associated with this solicitation are available through the following attachments:

• Attachment A – Statement of Work

• Attachment B – Schedule of Items

• Attachment C – Photos

• Attachment D – Map1

• Attachment E – Map2

• Attachment F – Wage Determination

• Attachment G – Sustainable Products

Project Location Project locations are listed in:

Attachment A – Statement of Work Attachment C – Photos Attachment D – Map1 Attachment E – Map2

Definitization of Equitable Adjustments for Change Orders

Pursuant to FAR 36.101-4(b), information regarding USDA’s definitization of equitable adjustments for change orders under construction contracts may be found at Contracting with USDA under “Federal Acquisition Regulation 36.101-4”. USDA’s procedures that apply to the definitization of equitable adjustments for change orders under construction contracts may be found in AGAR

443.304 -70.

Federal Acquisition Regulation (FAR) and United States Department of Agriculture Acquisition Regulation (AGAR) Clauses and Provisions The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.

https://www.usda.gov/about-usda/general-information/staff-offices/departmental-administration/office-contracting-and-procurement-ocp/policies-regulations

Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.

As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

52.252-2 Clauses Incorporated by Reference Feb 1998 This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025) ☐ Alternate I (Nov 2025) of 52.212-4

This is a commercial construction acquisition. FAR 52.212-4 is amended as follows:

(b) Inspection/Acceptance. Inspection and Acceptance will be conducted in accordance with FAR 52.246-12, Inspection of Construction (Aug 1996).

(d) Changes. Changes will be handled in accordance with the following FAR clause(s):

☐ FAR 52.243-4, Changes (Nov 2025) ☒ FAR 52.243-5, Changes and Changed Conditions (Nov 2025)

(o) Warranty. FAR 52.246-21, Warranty of Construction is applicable to this contract.

52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

(Jan 2017) 52.222-50 Combating Trafficking in Persons (Nov 2025) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After Award (Sep 2025) 52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025) 52.240-91 Security Prohibitions and Exclusions (Nov 2025) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025) https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

The following clauses are applicable if checked:

☒ 52.204-13 System for Award Management—Maintenance (Nov 2025) ☒ 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025) ☒ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025) ☒ 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Nov 2025) ☒ 52.219-6 Notice of Total Small Business Aside (Nov 2025) ☒ 52.222-3 Convict Labor (June 2003) ☒ 52.222-35 Equal Opportunity for Veterans (Nov 2025) ☒ 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025) ☒ 52.222-37 Employment Reports on Veterans (Nov 2025) ☒ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) ☒ 52.222-90 Addressing DEI Discrimination by Federal Contractors (Apr 2026) ☒ 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (Nov 2025) ☒ 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008) ☒ 52.223-23 Sustainable Products and Services (Nov 2025) ☒ 52.225-1 Buy American-Supplies (Nov 2025) ☒ 52.226-4 Notice of Disaster or Emergency Area Set-Aside (Nov 2007) ☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018) ☒ 52.246-21 Warranty of Construction (Mar 1994)

The Contractor shall comply with the following FAR Clauses for Commercial Construction.

52.222-6 Construction Wage Rate Requirements (Nov 2025) 52.222-7 Withholding of Funds (Nov 2025) 52.222-8 Payrolls and Basic Records (Nov 2025) 52.222-9 Apprentices and Trainees (Nov 2025) 52.222-10 Compliance with Copeland Act Requirements (Nov 2025) 52.222-11 Subcontracts (Labor Standards) (Nov 2025) 52.222-12 Contract Termination-Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.

(May 2014) 52.222-14 Disputes Concerning Labor Standards (Nov 2025) 52.222-15 Certificate of Eligibility (May 2014) 52.236-5 Material and Workmanship (Jul 2025)

The following clauses are applicable when checked:

☒ 52.225-9 Buy American-Construction Materials (Nov 2025) ☒ 52.228-2 Additional Bond Security (Oct 1997)

☒ 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) ☒ 52.228-14 Irrevocable Letter of Credit (Nov 2014) ☒ 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) ☒ 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) ☒ 52.236-2 Differing Site Conditions (Jul 2025) ☒ 52.236-3 Site Investigation and Conditions Affecting the Work (Jul 2025) ☒ 52.236-6 Superintendent by the Contractor (Jul 2025) ☒ 52.236-7 Permits and Responsibilities (Jul 2025) ☒ 52.236-8 Other Contracts (Jul 2025) ☒ 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Jul 2025) ☒ 52.236-10 Operations and Storage Areas (Jul 2025) ☒ 52.236-11 Use and Possession Prior to Completion (Jul 2025) ☒ 52.236-12 Cleaning Up (Jul 2025) ☒ 52.236-13 Accident Prevention (Jul 2025) ☒ 52.242-14 Suspension of Work (Apr 1984)

Other Applicable Clauses

52.217-7 Option for Increased Quantity - Separately Priced Line Item (Mar 1989) 52.245-1 Government Property (Sep 2021) 52.245-9 Use and Charges (Apr 2012)

AGAR Clauses This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of the clause may be accessed electronically at Internet address https://www.usda.gov/guidance-documents/acquisition-policy/ocp/usda-agar30-sept-26pdf

AGAR 452.203-70 Unenforceable Supplier Terms (Sep 2026)

AGAR 452.204–70 Modification for Contract Closeout (Apr 2026)

AGAR 452.232-71 Progress Payments for Commercial Construction Contracts (May 2026)

AGAR 452.236-70 Electronic Submission of Payment Requests (Sep 2026)

Solicitation Information

Award Type It is anticipated that a Firm-Fixed Price contract will be awarded as a result of this synopsis/solicitation. The Government intends to make one award from this solicitation.

Therefore, to be considered responsive, contractors must submit pricing for all items, including the two option items.

Period of Performance The Contractor is required to commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed and the entire work ready for use not later than 90 calendar days after notice to proceed. The time stated for completion shall include final cleanup of the premises.

Organized Site Visit Due to the distances from one location to another there will be no pre-bid site visit. Photos of each site have been included in Attachment C – Photos, as well as their GPS coordinates listed in the Statement of Work, Attachment A. Interested contractors may visit the sites and research site locations on Google Earth™ or similar mapping applications to fully understand logistics and travel time to and from all sites. Contractors may visit the site to make any detailed measurements and familiarize themselves with existing conditions. Any questions about the location and/or logistics may be asked during the solicitation Request for Information (RFI) period.

In no event shall failure to inspect the site constitute grounds for a claim after contract award.

Evaluation and Basis for Award The provision at FAR 52.212-2, Evaluation—Commercial Products and Commercial Services is not applicable to this solicitation. In lieu of this provision, quotes will be evaluated in accordance with FAR 12.203 based on the criteria listed below. Award will be made to the offeror representing the best value to the Government.

Technical Approach:

The technical approach will evaluate the ability of the offeror to provide a sound and compliant approach that meets all requirements and shows a thorough understanding of them. It is the contractor's responsibility to ensure their quotation clearly demonstrates their capability to meet these requirements. All offerors must provide the following minimum information and documentation with their quotations to be considered responsive and have their offers evaluated:

• Ability of the offeror to meet the schedule requirements listed in the Statement of Work

(SOW).

o History and experience of the company and workers in related work.

o The personnel planned for use on the project as well as any subcontractors and their experience and capabilities.

o Safety Plan.

o Method(s) to be used for demolishing existing units, removing existing units, and relocating/installing units to be relocated.

o Equipment that is expected to be used.

• Detailed explanation of any requirement listed in the SOW that cannot be successfully accomplished by the offeror.

Price:

The offeror shall provide pricing as requested in the Schedule of Items in Attachment B of this Request for Quote. Failure to propose pricing for all individual line items, including the optional line item, may result in a quotation being excluded from further consideration. The offeror’s quotation will be evaluated in accordance with FAR 12.204, to determine if it is fair and reasonable.

Past Performance:

The Government may utilize any references provided by the Contractor, along with information available from past contracts/orders with the USDA and any information found using sources such as Federal Government sources or the Contractor Performance Assessment Reporting System (CPARS) to determine if the Contractor has acceptable or neutral Past Performance. Past Performance will be evaluated using the following rating system:

• Acceptable: The contractor shows a demonstrated ability to meet contract requirements in prior or current contracts, including quality of work, timeliness, cost control, business relations, and adherence to contract terms.

• Neutral: Offeror does not have a past performance record.

• Unacceptable: The contractor has a documented history of failing to meet contract requirements, including poor quality, missed deadlines, cost overruns, lack of responsiveness, or unethical behavior.

Evaluation Method:

All quotations will be evaluated to identify the offeror presenting the most technically advantageous solution based on the stated evaluation criteria. Once the highest technically rated offeror is identified, their price will be evaluated to determine whether it is fair and reasonable. Past performance will also be assessed to ensure it is acceptable or neutral.

Award will be made to the offeror whose proposal is determined to be the highest technically rated, provided that:

• The proposed price is fair and reasonable, and

• Past performance is assessed as acceptable or neutral.

Award will not necessarily be made to the lowest-priced offeror. Tradeoffs will not be conducted.

52.252-1 Solicitation Provisions Incorporated by Reference Feb 1998 This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-1 Instructions to Offerors - Commercial Products and Commercial Services (Nov 2025) FAR 52.212-1 is amended as follows:

Period for acceptance of offers.

The Offeror agrees to hold the prices in its offer firm for 90 calendar days from the date specified for receipt of offers.

Questions Questions shall be submitted via email to melissa.heckenlaible@usda.gov and are due no later than October 29, 2026, at 12:00 PM Mountain Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name and number as the subject line of the email.

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017) 52.209-2 Prohibition on Contracting with Inverted Domestic Corporations - Representation (Sep 2025) 52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law (Sep 2025) 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Nov 2025)

The following provisions are applicable if checked:

☒ 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions (Sep 2024) ☒ 52.204-7 System for Award Management—Registration (Nov 2025) ☒ 52.222-5 Construction Wage Requirements, Secondary Site of the Work (Nov 2025) ☒ 52.223-1 Biobased Product Certification (May 2024) ☒ 52.223-4 Recovered Material Certification (May 2008) ☒ 52.225-2 Buy American Certificate (Oct 2022) ☒ 52.225-10 Notice of Buy American Requirement- Construction Materials (May 2014) ☐ Alternate I (May 2014) of 52.225-10 ☒ 52.228-1 Bid Guarantee (Sep 1996) ☒ 52.229-11 Tax on Certain Foreign Procurements—Notice and Representation (Jul 2025)

AGAR Provisions This solicitation incorporates one or more provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of the clause may be accessed electronically at Internet address mailto:melissa.heckenlaible@usda.gov

NOTICE FOR FILING AGENCY PROTESTS

United States Department of Agriculture (USDA) Protest Procedures The United States Department of Agriculture (USDA) is committed to fair, transparent, and efficient acquisitions. Interested parties with concerns about this solicitation are encouraged to seek resolution through the following USDA procedures.

Tier 1: Contracting Officer Concern Resolution

Submission: Interested parties with concerns about either the solicitation or subsequent award should first submit their concern directly to the Contracting Officer, providing sufficient detail to allow the Contracting Officer to understand and assess the issue.

Process: The Contracting Officer will review the concern, seek clarification as needed, and engage with the interested party to attempt prompt resolution.

Review Timeline: The Contracting Officer will make every effort to provide a response or resolution within 10 business days of receiving the concern.

Effect on Award or Performance: Tier 1 engagement is not considered an official notification of filing an agency protest and does not pause solicitation deadlines, delay award decisions, or suspend contract performance.

Next Steps: If the matter cannot be resolved at Tier 1, the interested party may file a written agency protest under Tier 2. USDA encourages all parties to seek resolution with the Contracting Officer before filing an agency protest.

Tier 2: Agency Protest If concerns cannot be resolved at Tier 1, an interested party may file a written agency protest with either the Contracting Officer or the USDA Independent Review Authority. The decision by the USDA Independent Review Authority is an alternative to a decision by the Contracting Officer. The USDA Independent Review Authority will not consider an appeal of the Contracting Officer’s decision on an agency protest.

The protest must state whether the protester elects review by the Contracting Officer, by the UDSA Independent Review Authority. If no election is stated, the Contracting Officer will decide the protest.

Required Information: Protests shall include the information set forth in FAR 33.104-4 (a)(3).

Failure to submit the required information may result in a delay or dismissal of the protest.

Submission: Agency protests should be submitted electronically to SPE.inquiry@usda.gov and the Contracting Officer.

Timeliness: Protests must be filed within the timeframes specified in FAR 33.104.

mailto:SPE.inquiry@usda.gov

Effect on Award or Performance: Contract awards or performance will be suspended during the protest period unless justified in writing for urgent and compelling reasons or determined to be in the best interest of the Government.

Review Timeline: USDA strives to resolve agency-level protests within 35 business days of receipt.

Election of Forum: By filing a protest with USDA, the protesters agree not to file a protest on the same matter with the Government Accountability Office (GAO) or any other external forum while the agency protest is pending. If such a protest is filed externally, the USDA agency protest will be dismissed.

Questions: Questions regarding this notice or protest procedures should be directed to the Contracting Officer identified in this solicitation.