- Solicitation number
- 127EAX27Q0007
- Issued by
-
Department of Agriculture Forest Service
About this file
This file is a Request for Information (RFI) Questions & Responses document for RFQ# 127EAX27Q0007 Vault Toilet Decommissioning, dated November 5, 2026, issued by the U.S. Forest Service. The RFI addresses 13 questions regarding site access, vault pumping and disposal, structure materials, vault treatment and backfilling, material disposal, concrete apron specifications, bonding requirements, wage rates, site visits, scheduling, and utilities. The contract involves decommissioning vault toilets at multiple sites located across Grant, Catron, and Sierra counties in New Mexico, with the majority of sites accessed via unpaved roads; contractors must visit sites independently or use mapping software for access verification. The contractor is responsible for pumping vault contents using licensed septage haulers and transporting waste to approved permitted disposal facilities per local regulations, as well as removing vault tanks and toilet superstructures for relocation and backfilling sites with either hauled-in material or excavated material from new CXT toilet installations. Concrete work, including new concrete aprons with "VanHorn roll" specifications, must be performed by the contractor. A bid bond of 20% of the quoted amount is required, and Davis-Bacon wage rates apply with separate determinations for three counties (Attachments F1, F2, F3). Work is anticipated to begin in December 2026 with a 90-day period of performance, with most work intended for completion before Spring Season 2027; concurrent work at multiple sites is permitted, and work suspension for winter weather is discretionary.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Questions & Responses
RFQ# 127EAX27Q0007 Vault Toilet Decommissioning
11-5-2026
1. Site list and access: How many separate sites are in scope, where are they (district / coordinates / road access), and what is the road condition to each site for a dump truck and a lowboy/excavator trailer? Any seasonal or weather access limits?
Coordinates of sites/ number of sites are provided in scope of work. Majority of sites are located off paved roads/state highways. Recommend visiting sites or using google earth or map program to research access.
2. Pumping: Will the Government pump out the vaults before demolition, or is pumping/handling of vault contents the contractor's responsibility? If the contractor's, what disposal facility and manifesting are required for the contents?
Vault pumping and disposal is contractors’ responsibility. See SOW excerpt below
“3.2 WASTE PUMP-OUT AND VAULT CLEANING
A. Pump the entire contents of the vault using a licensed and permitted septage hauler.
Spray down vault interior to remove any remaining solids, slurry, washdown residue, or debris from vault interior and pump out prior to backfilling.
B. Transport all pumped waste to an approved and permitted disposal or treatment facility in accordance with local regulations.”
3. Structures: What are the vault toilet buildings made of (precast concrete CXT-type, CMU/block, wood frame) and what are their approximate sizes/weights? Are drawings or photos of each structure available?
This information can be determined from the photos, Attachment C.
Weights or drawings are not available.
4. Vault treatment: For decommissioned vaults, is the requirement to remove the vault tank, or to pump, crush/collapse, and backfill in place? What backfill material, compaction, and final grade/restoration are required at each site?
Requirement is to pump and remove the vault and toilet superstructure and relocate it.
Please see 3.5 backfilling and compaction on page seven of SOW for information regarding backfill of these units. Backfill material will either need to be hauled in to Gomez Peak and
Little Walnut demolition sites or use excavated material from CXT toilet install to backfill old, demolished toilet area.
5. Disposal: Is there a designated landfill/disposal facility, or is the facility the contractor's choice? Any materials requiring special handling (treated wood, roofing, hazardous)?
There is no designated disposal facility. It shall be properly disposed of off forest service lands at a location identified by contractor.
6. Concrete aprons: What are the dimensions/spec for the new concrete aprons, and is concrete work performed by the contractor or by others?
Please see CONCRETE APRON WITH “VANHORN ROLL” section of the scope of work on page 13. Concrete work is to be performed by the contractor.
7. Bonding and wage rates: Please confirm the bid bond percentage and form required, and that Davis-Bacon wage rates apply (and which wage determination).
The bid bond percentage is 20% of the quoted amount. A complete and accurate digital version of the bid bond can be emailed with the quote submission per the directions in the solicitation. The Davis-Bacon Wage Determinations are found in Attachments F1, F2, and F3 of the solicitation documents found in the listing at SAM.gov.
8. Will a Catron County wage determination be added by amendment?
Work for this contract will be performed in Grant, Catron, and Sierra counties of NM.
Kingston CG toilet and Emory Pass Toilet →Sierra County (Attachment F3)
Head of Ditch, San Fransico, and Bighorn Toilets → Catron County (Attachment F2)
Remaining locations → Grant County (Attachment F1)
9. Site visit and schedule: Is there a scheduled site visit? If not, can the Forest Service share any guidance on accessing the sites on our own?
No scheduled site visit. Please see map 1 & 2 attachments and coordinate locations provided in scope of work. Recommend using google maps or similar software for navigation to sites.
10. What is the anticipated notice-to-proceed and period of performance?
Period of performance is 90-days after Notice to Proceed. There may be some lead time required for the procurement of a new precast toilet if that option line is awarded, but the Forest Service can be flexible with the time frame on that line item due to industry supply.
However, most of the work is intended to be completed prior to the Spring Season 2027.
The Start Date is intended to be sometime in December 2026.
11. Will work be suspended for winter weather?
If deemed necessary.
12. May work at multiple sites proceed concurrently?
Yes
13. Utilities and facilities: Is water available at any site for compaction/dust control?
Who furnishes temporary facilities for remote sites?
Please see page 1 of SOW.