This is a Closeout Specifications attachment document for the Illinois Department of Innovation and Technology (DoIT) related to contract B-50657, a rebid for Fiber Construction Services in the North Region. The document outlines the vendor's work acceptance process, which requires the vendor to submit a substantial completion notice, incorporate any incomplete work corrections within an established timeframe, and submit redlined as-built drawings in Adobe PDF format along with GIS ESRI Shape files and fiber test results in compliance with Data Submittal guidelines detailed in Attachments C and D. The Department will conduct a punch list walk-through to identify deficiencies, and the vendor must complete all corrections within a specified timeframe and submit them for DoIT clearance via email.

The vendor must provide supplemental documentation including warranties, guarantees, maintenance data, instruction manuals, a detailed list of extra materials and equipment owned by the State, and a final Waiver of Lien from all subcontractors and suppliers. Following correction of punch list deficiencies and receipt of all required documentation, DoIT or its authorized engineer will conduct a final inspection. The project is considered complete and accepted only when DoIT confirms that all build work requirements and closeout documentation have been satisfactorily completed.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Illinois Department of Innovation and Technology

B-50657 REBID Fiber Construction Services - North Region Attachment B – Closeout Specifications

Closeout Specifications

The Department of Innovation and Technology (“DoIT”) will accept the Vendor’s work based on the following process:

1. Vendor will make notification, via substantial completion notice, that the work is complete.

2. If only substantially complete, the Vendor will be notified of the incomplete work via email and given notice of incomplete scope and established time frame to complete project.

3. If requested, Vendor will submit redlined drawings electronically in Adobe PDF and GIS

ESRI Shape files reflecting the as-built project to DoIT, as well as fiber test results electronically. These shall comply with the Data Submittal guidelines provided in

Attachments C and D.

4. DoIT or DoIT A/E will perform a punch list walk through.

5. Vendor will receive punch list of deficiencies along with time-frame for correction of the deficiencies.

Upon completing corrections, Vendor will submit to DoIT for clearance of those deficiencies via email.

6. Vendor provides supplemental documentation:

a. Warranties, guarantees, maintenance data and instruction manuals

b. Detailed list of extra materials and equipment that are property of the State

c. Final Waiver of Lien from all subcontractors and suppliers

7. DoIT A/E or DoIT to perform final inspection notice after punch list deficiencies have been corrected and all documentation received.

8. Once DoIT is satisfied that all requirements have been met, both in the build work as well as the required closeout documentation, DoIT will consider the job complete and accepted.