This is an appendix image for a solar lighting installation project at the Dona Ana Firearms Range Complex in Chaparral, New Mexico. The aerial map shows the proposed solar lighting coverage areas marked in yellow, extending from the entrance gate to the classroom building and reaching the far corner of the firearms range. The image includes location markers for the entrance gate, classroom building, and far-reaching corners of the range, with geographic coordinates for Doña Ana County. The lighting installation requires complete solar light systems that provide illumination meeting Illuminating Engineer Society (IES) standards, with a 5-7 hour full brightness operating profile at dusk, followed by 40% brightness for the remainder of the night, and 5-7 days of battery autonomy. The project specifications include requirements for system warranties (5-year battery, 20-year photovoltaic panels, 2-year LED bulbs), daily site cleanup, providing construction dumpsters, portable toilets for work crews, and complete debris removal upon project completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Range 58 - Solar Lighting Installation Dona Ana Firearms Range Complex – Range 58

Chaparral, NM

•Install complete Solar Lights Systems to provide enough illumination to meet the most up to date Illuminating Engineer Society (IES) and industry Solar Lighting standards through the range parking lot from the entrance gate to the classroom building as well as to the far-reaching corner of the firearms range.

•The request is for solar lighting with poles to be installed providing adequate lighting for the area shown in appendix A.

•Operating profile is 5-7 hours (customer choice) full brightness at dusk and then dimming to 40% brightness for the remainder of the night.

Systems configured to include 5-7 days of autonomy (battery back-up), for days of limited sunlight.

•Provide all necessary material, parts, tools, wirings, and settings and programming to achieve the highest efficiency while meeting lighting and safety requirements.

•Provide a commissioning report for each complete light system installed to verify proper operation, back-up potential, and solar capacity.

•Upon installation, provide a report detailing required maintenance to the system as suggested by the manufactures warranty.

•Provide a minimum of five years manufacturer warranty on battery units, 20-year on photovoltaic panels, two-year on LED bulbs, and two-year on all other parts.

•Provide daily cleanup of the construction work areas, leaving them free from debris.

•The contractor is responsible for providing construction dumpsters as needed and arranging delivery and emptying as needed.

•The contractor shall provide portable toilets for work crews and, is responsible for making sure that all portable toilets are maintained properly including cleaning, emptying and re-supply of paper products and hand sanitizer.

•The contractor shall remove all debris from the work site at the end of the project.

Far-Reaching Corner of Range

Entrance Gate

Far-Reaching Corner of Range

Classroom Bldg.

Slide Number 1

File details come from the government source that posted it. Updated .