This is a specification stamp sheet and master specifications document for a construction project at Hampton VA Medical Center in Hampton, Virginia. The project (590-24-450, designated "Valhalla 24.10") involves renovating transitional residences and is currently at 100% construction documents stage as of January 27, 2026. The specifications document establishes technical requirements across 33 divisions covering general requirements, existing conditions, concrete, masonry, metals, wood, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, exterior improvements, and utilities. Key general requirements include contractor responsibility for site preparation, demolition, equipment testing, labor, and materials; mandatory site visits by appointment only; security compliance with VA regulations including badge requirements, key control, and vehicle restrictions; protection of existing structures and vegetation; asbestos and lead-based paint abatement; maintenance of utility services; comprehensive insurance and bonding requirements; and detailed warranty provisions including one-year construction warranty with extended warranties for roofs, HVAC balancing, pumps, motors, transformers, and commissioned systems. The contractor must develop a Critical Path Method schedule, maintain as-built drawings, submit detailed shop drawings and product data for VA approval within specified review periods, conduct testing and commissioning of all systems, provide operation and maintenance manuals, and deliver photographic documentation of construction progress. Preconstruction requirements include an Accident Prevention Plan, Activity Hazard Analyses, Site Safety and Health Officer designation, personal protective equipment compliance, tuberculosis screening, fire safety protocols, and fall protection measures in accordance with OSHA standards and VA security procedures.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS STAMP SHEET
CIVIL LANDSCAPE STRUCTURAL
ARCHITECTURAL FIRE ALARM FIRE SUPPRESSION
PLUMBING MECHANICAL ELECTRICAL
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents January 27, 2026
Project # 590-24-450
ZMiller Snapshot
ZMiller Snapshot
ZMiller Stamp
06-01-24
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS (NOT USED)
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 35 26 Safety Requirements for Major Projects 05-24
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construction Waste Management 04-22
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 01-21
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 01-21
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
05 51 00 Metal Stairs 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 20 00 Finish Carpentry 01-21
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents January 27, 2026
Project # 590-24-450
00 01 10-2
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 01-21
07 21 13 Thermal Insulation 01-21
07 31 13 Asphalt Shingles 02-21
07 31 26 Slate Shingles 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 71 00 Roof Specialties 01-21
07 92 00 Joint Sealants 04-22
DIVISION 08 - OPENINGS
08 14 00 Interior Wood Doors 01-21
08 51 13 Aluminum Windows 01-21
08 80 00 Glazing 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 23 00 Gypsum Plastering 01-21
09 29 00 Gypsum Board 04-20
09 30 13 Ceramic/Porcelain Tiling 01-21
09 65 19 Resilient Tile Flooring 05-18
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 28 00 Toilet, Bath, and Laundry Accessories 01-21
DIVISION 11 – EQUIPMENT (NOT USED)
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 08-17
12 32 00 Manufactured Wood Casework 01-21
12 36 00 Countertops 12-23
DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)
DIVISION 14– CONVEYING EQUIPMENT (NOT USED)
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
00 01 10-3
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 01-23
22 05 12 General Motor Requirements for Plumbing Equipment 09-20
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 05 33 Heat Tracing for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 11 00 Facility Water Distribution 05-21
22 11 23 Domestic Water Pumps 09-15
22 13 00 Facility Sanitary and Vent Piping 09-20
22 33 00 Electric Domestic Water Heaters 09-20
22 40 00 Plumbing Fixtures 05-24
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
03-23
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
03-23
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 03-23
23 23 00 Refrigerant Piping 03-24
23 31 00 HVAC Ducts and Casings 03-23
23 34 00 HVAC Fans 03-23
23 37 00 Air Outlets and Inlets 03-23
23 40 00 HVAC Air Cleaning Devices 03-23
23 81 43 Air-Source Unitary Heat Pumps 03-23
DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 20 Cables 10-25
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 05 41 Underground Electrical Construction 11-22
26 24 16 Panelboards 11-22
26 27 26 Wiring Devices 11-22
26 29 21 Enclosed Switches and Circuit Breakers 11-22
26 43 13 Surge Protective Devices 11-22
26 51 00 Interior Lighting 03-24
DIVISION 27 – COMMUNICATIONS (NOT USED)
Renovate Transitional Residences
100% Construction Documents
00 01 10-4
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
32 31 23 Vinyl Fences and Gates CUSTOM
32 90 00 Planting 08-16
DIVISION 33 – UTILITIES (NOT USED)
DIVISION 34 – TRANSPORTATION (NOT USED)
DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED)
Renovate Transitional Residences
100% Construction Documents
12-01-21
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish equipment, testing, labor and materials and perform work for project
no. 590-24-450 (Valhalla 24.10) – Renovate Transitional Residences at the Hampton VA Medical Center in Hampton Virginia, as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Contracting Officer Representative (COR). Only one organized site visit for each site shall be conducted.
C. Offices of Valhalla Engineering Group, LLC., Englewood CO., as
Architect/Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting
Officer/COR.
D. Before placement and installation of work subject to tests by testing laboratory retained by the Contractor, the Contractor shall notify the
COR in sufficient time to enable the COR to be present at the site in time to observe proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID Work includes general construction, alterations, roads, walks, grading, drainage, and as necessary removal of portions of existing structures and construction and certain other items.
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 2
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these VA regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. No photography of VA premises is allowed without written permission of the Contracting Officer/COR. Patients and staff are not to be photographed at any time.
3. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting
Officer/COR.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officer’s representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
2. The General Contractor shall install locksets that accept the
Stanley/Best Corp. 7-pin, removable cores compatible with those used at this VA facility.
3. The General Contractor shall install all permanent cores at completion of the work.
D. Motor Vehicle Restrictions
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 3
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA COR.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer/COR. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer/COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer/COR, use only established roadways as authorized by the
Contracting Officer/COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any
Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as approved by the COR.
E. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 4 of such indication, where directed by COR. All such actions shall be coordinated with the COR and Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
F. Construction Area will be vacated by Government on contractors approved schedule by COR. VA vacating the space and the turnover of the space to the contractor shall be as determined. The contractor to provide a list of long lead items for the work and a turnover date will be coordinated to the extent possible between the VA and the construction contractor to coincide with the contractor being able to work continuously in the space. VA staff shall not be displaced for the construction contractor to perform demolition activities and then the site sits empty for several months while the contractor(s) await the arrival of material on site. The VA COR shall verify all materials are on site prior to turning the space over to the construction contractor.
G. Existing Buildings will not be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris.
H. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area. Provide gates as required for access with necessary hardware, including hasps and padlocks.
Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm
(15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
1. When a building is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
2. Contractor shall maintain conditioned space work areas at a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 5
3. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
I. When ceilings are removed, contractor shall provide sprinkler coverage in the space by making current sprinklers in the area extend upward towards the structural deck and provide appropriate sprinkler heads and system extension to provide complete sprinkler coverage. If this is not done, contractor shall provide fire watch within the space and record status every hour.
J. Utilities Services: Maintain existing utility services for Residences at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan and written approval.
K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
L. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 6
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the
Contracting Officer/COR. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items.
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such sidewalks and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 7
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse.
Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Residences.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When houses are vacated by the
Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 8 or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer/COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer/COR may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Prepare and submit a Stormwater Prevention Plan (SWPPP) and a monitoring plan.
E. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements.
Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the
Contractor's method of operations and operations planning and the
Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 9
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 10
1.11 PHYSICAL DATA – SOIL CONDITIONS - (NOT USED)
1.12 PROFESSIONAL SURVEYING SERVICES - (NOT USED)
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer/COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer/COR until authorized to remove them. If such marks are destroyed by the Contractor or through
Contractor's negligence before their removal is authorized, the
Contracting Officer/COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full-size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in hardcopy (prints) and electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 WARRANTY
A. Provide standard one (1) year warranty.
B. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit two (2) sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 11 that the Government receives all warranties to which it is entitled.
The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved.
Warranty information made available during the construction phase must be submitted to the Contracting Officer/COR for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9-month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer/COR.
Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 12
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
C. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer/COR will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer/COR will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 13 to respond will be cause for the Contracting Officer/COR to proceed against the Contractor.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads.
1.17 RESIDENT ENGINEER'S FIELD OFFICE - (NOT USED)
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 14
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
Pumps, feedwater heaters and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.19 TEMPORARY USE OF EXISTING ELEVATORS - (NOT USED)
1.20 TEMPORARY USE OF NEW ELEVATORS - (NOT USED)
1.21 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting
Officer/COR, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 15
C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials.:
1. Contractor is responsible for connecting and disconnecting to the heating systems and all costs associated. The contractor will not be charged a fee for using the utility.
D. Electricity (for Construction and Testing): temporary electric services.
1. Obtain electricity by connecting to the Residence electrical system.
E. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Residence water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
2. Before installation, obtain VA Chief Engineer approval of equipment and location proposed for connection.
3. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
1.23 NEW TELEPHONE EQUIPMENT
A. The contractor shall coordinate with the work of installation of telephone equipment by others. This work shall be completed before the building is turned over to VA.
1.24 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as-built documentation.
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 16
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting
Officer/COR. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonable period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.25 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (two hard copies and one PDF format electronic copy each, with Drawings on
AutoCAD format in version compatible with the VA facility) for each separate piece of equipment shall be delivered to the COR coincidental
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 17 with the delivery of the equipment to the job site. Drawings shall be in AutoCAD format, version compatible with that in use at this facility. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub assembly components. Manuals shall include an index covering all component parts clearly cross referenced to diagrams and illustrations. Illustrations shall include
"exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished.
Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 18 request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.26 GOVERNMENT-FURNISHED PROPERTY - (NOT USED)
1.27 RELOCATED EQUIPMENT AND ITEMS (NOT USED)
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT - (NOT USED)
1.29 CONSTRUCTION SIGN - (NOT USED)
1.30 SAFETY SIGN - (NOT USED)
1.31 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and at selected milestones including electronic indexing, navigation, storage and remote access to the documentation, as per these specifications.
1. Submit 50 progress photos each week documenting the progress of all trades working on the site.
B. Photographic documentation elements:
1. Documentation shall combine indexing and navigation system with inspection-grade digital photography designed to capture actual conditions throughout construction and at critical milestones.
Documentation shall be accessible on-line through use of an internet connection. Documentation shall allow for secure multiple-user access, simultaneously, on-line.
2. Regular (8 max) interior progressions of all walls of the entire project to begin at time of substantial framed or as directed by the
COR through to completion.
3. Finished detailed Interior exact built overlapping photos of all walls, ceilings, and floors to be scheduled by COR prior to occupancy.
4. In event a greater or lesser number of images than specified above are required by the COR, adjustment in contract price will be made in accordance with clause entitled "CHANGES" (FAR 52.243-4).
1.32 FINAL ELEVATION DIGITAL IMAGES - (NOT USED)
1.33 HISTORIC PRESERVATION
A. Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 00 00 - 19 shall immediately notify the COR verbally, and then with a written follow up.
1.34 VA TRIRIGA CPMS - (NOT USED)
PART 2 - PRODUCTS - (NOT USED)
PART 3 - EXECUTION - (NOT USED)
- - - E N D - - -
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
11-01-21
01 32 16.15 - 1
SECTION 01 32 16.15
PROJECT SCHEDULES
(SMALL PROJECTS – DESIGN/BID/BUILD)
PART 1- GENERAL
1.1 DESCRIPTION:
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements
(Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.
1. If the VA hires a Construction Period Services (CPS) firm, the
Contractor shall provide Project Schedules to both the COR and their
Construction Period Services Firm at the same time within ten days of award and with each update.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (COR).
B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.
C. The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.
1.3 CONTRACTOR'S CONSULTANT:
A. The Contractor shall submit a qualification proposal to the COR, within
10 days of bid acceptance. The qualification proposal shall include:
1. The name and address of the proposed consultant.
2. Information to show that the proposed consultant has the qualifications to meet the requirements specified in the preceding paragraph.
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 32 16.15 - 2
3. A representative sample of prior construction projects, which the proposed consultant has performed complete project scheduling services. These representative samples shall be of similar size and scope.
B. The Contracting Officer has the right to approve or disapprove the proposed consultant, and will notify the Contractor of the VA decision within seven calendar days from receipt of the qualification proposal.
In case of disapproval, the Contractor shall resubmit another consultant within 10 calendar days for renewed consideration. The
Contractor shall have their scheduling consultant approved prior to submitting any schedule for approval.
1.4 COMPUTER PRODUCED SCHEDULES
A. The contractor shall provide monthly, to the Department of Veterans
Affairs (VA), all computer-produced time/cost schedules and reports generated from monthly project updates. This monthly computer service will include: three copies of up to five different reports (inclusive of all pages) available within the user defined reports of the scheduling software approved by the Contracting Officer; a hard copy listing of all project schedule changes, and associated data, made at the update and an electronic file of this data; and the resulting monthly updated schedule in PDM format. These must be submitted with and substantively support the contractor’s monthly payment request and the signed look ahead report. The COR shall identify the five different report formats that the contractor shall provide.
B. The contractor shall be responsible for the correctness and timeliness of the computer-produced reports. The Contractor shall also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.
C. The VA will report errors in computer-produced reports to the
Contractor’s representative within ten calendar days from receipt of reports. The Contractor shall reprocess the computer-produced reports and associated diskette(s), when requested by the Contracting Officer’s representative, to correct errors which affect the payment and schedule for the project.
Hampton VA Medical Center Hampton, Virginia Renovate Transitional Residences
100% Construction Documents
01 32 16.15 - 3
1.5 THE COMPLETE PROJECT SCHEDULE SUBMITTAL
A. Within 45 calendar days after receipt of Notice to Proceed, the
Contractor shall submit for the Contracting Officer's review; three blue line copies of the interim schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in the previously approved
CPM schedule program. The submittal shall also include…