Attachment A11-A14.docx

DOCX document 88 KB Posted

Attached to
FINAL SOLICITATION- Environmental Remediation Services for Rocky Mountain Arsenal
Solicitation number
W91CRB23R0005
Issued by

About this file

This final solicitation is seeking proposals for environmental remediation services at Rocky Mountain Arsenal. The U.S. Army Contracting Command-Aberdeen Proving Ground will award an Indefinite Delivery/Indefinite Quantity contract with one 3-year base period and two 3-year option periods to provide operation and maintenance of remediation systems. Services will include water treatment plant operations, groundwater and surface water sampling, landfill and cover maintenance, regulatory compliance support, and non-routine requirements such as engineering modifications or demolition of decommissioned systems. The solicitation is set aside for small businesses with less than 750 employees and is a cost-plus-incentive-fee contract incorporating fixed price elements. Offerors must submit proposals through the DoD Secure Access File Exchange by 19 May 2023. Questions may be asked until the same date and responses will be posted on SAM.gov where amendments will also be issued.

View the file

Other files

File Type Posted
W91CRB23R0005 Amendment 0004.pdf PDF
W91CRB23R0005 Amendment 0003.pdf PDF
W91CRB23R0005 Amendment 0002.pdf PDF
A22 Response to Industry Comments ERS RFP Amd 2.pdf PDF
A21 SF330-21.pdf PDF
Attachment A19 Response to Industry comments DRAFT RFP.pdf PDF
Attachment A22 Response to Industry Comments ERS RFP.pdf PDF
L1 RMA ERS Cost Model 052523.xlsx XLSX spreadsheet
W91CRB23R0005 Amendment 0001.pdf PDF
A20_Purchasing_System_Review_Form.xlsx XLSX spreadsheet
L60 - Quality Assurance Surveillance Plan.pdf PDF
Attachment A3 - Project Vehicles and Trailers 2023 04 04.pdf PDF
Attachment A4-A9.docx DOCX document
Attachment A19 Response to Industry comments.pdf PDF
Attachment A10.docx DOCX document
L61 - Contract Data Requirements List (CDRL) Forms.pdf PDF
L42 Service Contract Wage Determination 2015-5419 Rev23.pdf PDF
Attachment A16 SUMMARY OF EXPERIENCE FORM.docx DOCX document
L43 Davis Bacon Wage Determination CO20230002 Heavy.pdf PDF
L60 - Quality Assurance Surveillance Plan 2023 04 12.docx DOCX document
Attachment A17.docx DOCX document
Attachment A15.docx DOCX document
L62 - Government Furnished Property Management Plan.pdf PDF
L43 Davis Bacon Wage Determination CO20230015 Building.pdf PDF
Attachment A1-A2.docx DOCX document
W91CRB23R0005 RFP 8MAY23.pdf PDF
Attachment A18 - Government Furnished Property.pdf PDF
L1 RMA ERS Cost Model.xlsx XLSX spreadsheet
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A11

RMA ERS Contract Target Cost Re-baselining procedure

As discussed in Section C1.22, the objective of the Incentive Fee Program is to use monetary incentives that encourage the Contractor to align its goals and vision for the long-term operations and maintenance work at the RMA with those of the Government. As part of that incentive, the Government has established the Target Cost Savings program which is described in more detail in Section C1.22 of the contract. The Target Cost is evaluated in three-year periods consistent with the Base and two Option Periods in the contract. For each three-year period, if total costs are under the established Target Cost the Contractor will receive 30% of the documented savings at the end of that period. The initial Target Cost for the three-year Base Period will be established as set forth in Section C1.22.

The Target Cost Savings portion of the Incentive program is not intended to be an area where savings are predictable, expected, or built into the Contractor’s anticipated profit. The base ERS scope at RMA has reached a consistent level of maturity and predictability and achieving additional savings is expected to require significant effort and innovation on the Contractor’s part. To account for any cost changes that are realized during each period, the Target Cost will be Re-Baselined at the beginning of each Option Period. The following sets forth the process for Re-Baselining.

1. The Contractors proposal includes reimbursable costs, fixed price items, and fee.

2. The original Target Cost is established from the Contractor’s proposed costs for the reimbursable CLINs Labor (XX01) and Reimbursable expenses (XX02) for the initial three-year Base Period.

Example: Assume the following was proposed on the bid schedule:

Note: $ values shown in the example bear no relationship to the actual scope and should not be inferred to have any meaning other than to provide a basis to explain how Re-Baselining will occur.

For this example, it is assumed that the Contractor proposed an escalation rate of 2% per year. Each year’s proposed costs are equal to the prior year plus the 2% escalation.

The initial Target cost for the Base Period is set at $4,590,600.

3. Assume the Contractor’s actual cost over the first 3-year base period was as follows:

Base Period Actual Cost

4. The target cost savings is the difference between the established Base Period Target Cost of $4,590,600 minus the actual cost of $4,425,000 or $165,600. The Contractor’s share of the Target Cost savings would be 40% of $165,600 or $66,240 which would be earned in addition to 100% of the Cost Fee Pool.

5. At the beginning of each Option Period the target cost will be Re-Baselined using the average actual cost realized during the prior three-year period. Using the 2% escalation rate discussed in item 2 above each year’s actual cost is escalated to the first year of the current option period as shown in the following example:

6. The New Target Cost for the First Option Period would then be established using the 3-year average above ($1,534,020) for the 1st year of the option period and escalating for each subsequent year as proposed in the Contractor’s original proposal. In this example using the 2% escalation rate described in item 1 above. The Re-Baselined Target Cost for the first Option Period would then be $4,694,714.81 as shown below.

New Target Cost – Option Period 1

7. If a significant change to the base PWS is directed by the Contracting Officer and is not the result of any Contractor efforts to achieve Target Cost savings, the Contracting Officer, at their discretion, may make an equitable adjustment to the existing Incentive Fee Pool and the Target Cost.

Attachment A12 – WBS Matrix

Attachment A13 – Computer Applications Recurring Costs

Company
2020
2021
Frequency
Renewal
DTSearch (Search for DDMS)
$350.00
$350.00
Annually
March
AWS Services (Web Hosting)
$1,300.00
$1,300.00
Monthly
No Renewal

Attachment A14 – Commercial Cloud Current Usage Requirements

Current Usage (Amazon Web Services)

Type of Server
CPU
RAM (GB)
Volume Size (TB)
Amazon Type
Number of HDD
Fileshare
4
16
1.87
t2.xlarge
3
Database 1
4
16
0.385
t2.xlarge
5
Database 2
4
16
0.03
t3a.xlarge
1
Webserver
2
8
0.26
t2.large
3

image6.emf image7.emf image1.emf image2.emf image3.emf image4.emf image5.emf