Attachment A - PROPOSED SUBCONTRACTORS FORM.pdf
PDF 92 KB Posted
- Attached to
- Restroom Remodel at Macomb Corners Park
- Solicitation number
- RFP# 25-001
- Issued by
- Macomb County, Mcbride Village, Michigan
About this file
This document is a Proposed Subcontractors Form for Macomb Township's Restrooms Remodel project at Macomb Corners Park in Michigan, with Project No. 25-001. The form is designed to be completed by bidders as part of their bid submission, requiring them to list proposed subcontractors, suppliers, or manufacturers of products for the project. Upon contract award, the work must be performed using the listed subcontractors, with substitutions permitted only if the original subcontractor fails to meet specifications or cannot meet delivery requirements.
The form provides a structured template with columns for "Nature of Work/Product", "Subcontractor/Manufacturer", "Location of Business", and "Percent of Contract Amount". Bidders are instructed to fully execute this form and include it with their bid as a condition of submission. Any proposed substitutions must be submitted to the owner for approval. The document emphasizes transparency in subcontracting and ensures that the township has detailed information about the proposed team and their respective roles in the restroom remodel project.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Macomb Township Attachment A
PROPOSED SUBCONTRACTORS FORM
Restrooms Remodel at Macomb Corners Park, Macomb Township, Michigan
Project No. 25-001
(To be fully executed and included with Bid as a condition of the Bid)
As part of the Bid, Bidders shall furnish, in the spaces provided, the names of the subcontractors, suppliers, or manufacturers of products that Bidder proposes to provide as part of this Project.
Upon award of a Contract, the Work shall be performed using the listed subcontractor, supplier, or manufacturer of products. Substitutions will be permitted only if listed subcontractor, supplier, or manufacturer of products does not meet the specifications or supplier, or manufacturer is unable to meet delivery requirements of the work schedule. All substitutions shall be submitted to the OWNER.
Nature of Work / Product
Subcontractor / Manufacturer
Location of Business Percent of Contract Amount
File details come from the government source that posted it. Updated .