Attachment A - 1809193 - NH-30 Statement of Work.pdf

PDF 8 MB Posted

Attached to
NH-30 Chiller Replacement
Solicitation number
N4008526R0077
Issued by

About this file

Scope of Work Summary

This is an Executable Scope of Work (SOW) for a construction project to replace an existing 50-ton outdoor air-cooled chiller and related controls at Building NH-30, Naval Support Activity (NSA), Norfolk, Virginia. The project is identified as eProjects Work Order No. 1809193 and Maximo SR Number 23804823. The customer is Commander, Navy Installation Command (CNIC), with primary points of contact including Project POC Melissa Eley and Funding POC Jason Etheridge. The FEAD Contracting Officer is Natalie Augsburger, and the Facility Maintenance Specialist is Melissa Eley. The work was prepared by NAVFAC MID-ATLANTIC's Facilities Engineering and Acquisition Division and approved on December 29, 2025.

The SOW specifies comprehensive demolition and installation requirements divided into mechanical and electrical components. Demolition work includes shutting down and disconnecting the existing chiller, evacuating refrigerant, removing associated electrical infrastructure (250A circuit breaker, conduit, and wiring from switchboard DP), and disposing of all material off-base. New work requirements include installing the 50-ton replacement chiller on the existing concrete pad, reconnecting chilled water supply and return lines, connecting controls per manufacturer specifications, installing a new 300A circuit breaker in switchboard DP, providing a 400A fused disconnect at the chiller location, and running 4-#350kcmil conductors with #4 ground in 3" RGS conduit between the disconnect and switchboard. The contractor must conduct testing and balancing, connect controls to the building automation system, and perform daily site cleanup. All work must comply with standard industry practices, applicable codes and regulations, Unified Facilities Criteria, U.S. Army Corps of Engineers Safety Health Requirements Manual EM-385-1-1, and must be performed during regular government working hours (Monday-Friday, 8.5-hour days, excluding holidays). Mandatory submittals include manufacturer product data, certificates, warranties, work schedule, equipment list, and site plan for construction laydown area.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

eProjects No: 1809193

Executable Scope of Work

Building NH-30 Replace Chiller at the

Naval Support Activity, Norfolk, Virginia

PREPARED BY:

NAVFAC MID-ATLANTIC

Facilities Engineering and Acquisition Division

Public Works Department

Norfolk, Virginia

SUBMITTED BY:

Design Manager: Richard Corbin

Plumbing / Mechanical Matthew Wright

Electrical / Telecom Joseph Godfrey, P.E.

Date: December 22, 2025

APPROVED BY:

Project Management & Engineering Director: John C. Miller, P.E.

Design Director: James M. Smith, R.A.

For Commander, NAVFAC MID-ATLANTIC:

Date:

NH-30 Replace Chiller and Related Controls

PWD Norfolk, Facilities Engineering and Acquisition Division Form Version 2024.06.27 Page 1 of 8 eProjects Work Order No: 1809193

Maximo SR Number: 23804823

Building: NH-30

Project Title: NH-30 Chiller Replacement & Related Controls

Customer:

Commander, Navy Installation Command (CNIC)

Project POC Melissa Eley Melissa.r.eley.civ@us.navy.mil 757-836-1994

Funding POC Jason Etheridge Jason.a.Etheridge2.civ@us.navy.mil 757-836-4099

Scope By: Electrical Mark Godfrey, P.E. Joseph.m.godfrey7.civ@us.navy.mil 757-341-1861

Mechanical Matthew Wright Matthew.R.Wright23.ctr@us.navy.mil 757-812-0971

Date:

December 22, 2025

1. Points of Contact:

FEAD Contracting Officer:

Natalie Augsburger

Natalie.g.augsburger.civ@us.navy.mil 757-341-0555

Facility Maintenance Specialist (FMS): Melissa Eley Melissa.r.Eley.civ@us.navy.mil 757-836-1994

2. General Description:

Contractor must provide supervision, labor, material, and equipment required to perform all work for the following project: Existing 50 Ton Air Cooled Chiller has reached the end of its useful life and needs replacing. Refer to section 7 “Project Overview and Work Requirements” for additional information.

All work must be performed in accordance with, but not limited to the following:

• Standard industry practices.

• Applicable local, state, federal codes, laws, and regulations.

• The Unified Facilities Criteria.

3. Location:

The work is located at building NH-30, Naval Support Activity (NSA), Virginia, approximately as indicated.

The exact location will be shown by the Contracting Officer. Refer to attachment 8.1 Location map of Naval Support Activity – Building NH-30.

NH-30 Replace Chiller and Related Controls eProjects No.: 1809193

Form Version 2024.06.27 Page 2 of 8

4. Special Scheduling Requirements / Work Procedures:

4.1 Utility Services will be in accordance with the procedures in FAR 41.202.

4.2 The work must be performed during regular Government working hours. Regular working hours must consist of an 8-1/2 hour period established by the Contracting Officer, Monday through Friday, excluding Government holidays.

4.3 The Contractor will be working around an existing building which is occupied. Do not enter the building without prior approval of the Contracting Officer.

4.4 The existing building and contents must be kept secure at all times. Provide dust covers or protective enclosures to protect existing work that remains.

4.5 Damage caused by construction operations must be repaired, patched and/or replaced to match adjacent areas to the satisfaction of the Contracting Officer at no additional cost to the Government.

4.6 Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

5. Safety:

5.1 All work must be conducted in a safe manner and must comply with all requirements of the U.S.

Army Corps of Engineers Safety Health Requirements Manual EM-385-1-1.

5.2 Contractor must submit an Accident Prevention Plan (APP), and Activity Hazard Analysis (AHA) for approval by the Contracting Officer. Submit the APP and AHA to the Contracting Officer 15 calendar days prior to the pre-performance conference for acceptance.

6. Submittals:

6.1 The Contractor must submit the following documents required for government approval, prior to the start of any construction activities:

• Manufacturer’s Product Data

• Certificates

• Manufacturer’s Warranties

• Work Schedule

• Equipment List

• Site Plan for Construction Laydown Area

• Submittals required by specifications

Form Version 2024.06.27 Page 3 of 8

7. Project Overview and Work Requirements:

7.1 Project Overview:

a. Replacement of 50 Ton outdoor air-cooled chiller and all related controls.

7.2 Demolition Work Requirements

Mechanical

1. Shut down existing 50 Ton Outdoor Air-Cooled Chiller.

2. Valve off Chilled water Supply and Return Lines and verify valves are holding.

3. Disconnect electrical power and associated controls.

4. Disconnect Chilled water piping and cap off to prevent debris from entering chilled water system.

5. Evacuate refrigerant from system.

6. Use crane to remove existing chiller.

Electrical

1. Disconnect 250A electrical connection at the existing chiller. Feeder is fed from existing 250A circuit breaker in switchboard DP. (See attached drawings)

2. Demolish existing conduit and wire feeding existing chiller back to existing 250A, 3P, circuit breaker in existing switchboard DP. (See attached drawings)

3. Demolish existing 250A, 3P, circuit breaker in existing switchboard DP. (See attached drawings)

7.3 New Work Requirements

Mechanical

1. Use crane to place new 50 Ton air cooled chiller onto existing concrete pad.

2. Connect chilled water supply and return lines taking into account any modifications for proper pipe fitting.

3. Connect necessary controls per manufacturer’s requirements.

4. Once tied-in mechanically and electrically, open chilled water supply and return valves.

5. Bring chiller online and verify unit is functioning properly and temperature and pressure gauges are functioning accurately.

6. Connect related controls to building automation system.

7. Testing and balancing required for chiller flow rates, pressure and temperature.

Electrical

1. Provide a 300A, 3P, circuit breaker in existing switchboard DP. (See attached drawings)

2. Provide a 400A, 3P, NEMA 4X fused disconnect with 300A fuses at new chiller location. (See attached drawings)

3. Connect fused disconnect to 300A, 3P, circuit breaker in switchboard DP with 4-#350kcmil, 1-

#4 ground, in 3” RGS conduit. (See attached drawings)

4. Connect fused disconnect to new chiller with 4-#350kcmil, 1-#4 ground, in 3” RGS conduit.

(See attached drawings)

Form Version 2024.06.27 Page 4 of 8

7.4 The Contactor must dispose of all existing demolished / removed material off base and must completely clean up the job site daily at the end of each workday.

8. Attachments:

8.1 Location map of Naval Support Activity (NSA) – Building NH-30.

8.2 Building NH-30 Site Plan

8.3 Photographs

Form Version 2024.06.27 Page 5 of 8

8.1 Location map Naval Support Activity (NSA) Norfolk-Building NH-30

LOCATION MAP

NOT TO SCALE

Form Version 2024.06.27 Page 6 of 8

8.2 Building NH-30 Site Plan

Form Version 2024.06.27 Page 7 of 8

8.3 Project Photographs

Photo # 1 Air Cooled Chiller Existing Conditions

Form Version 2024.06.27 Page 8 of 8

Photo # 2

Air Cooled Chiller Existing Conditions

2025-12-29T10:38:03-0500

2025-12-29T10:38:27-0500

File details come from the government source that posted it. Updated .