This document is a Statement of Work (SOW) appendix containing project layout maps, fiber/conduit distribution diagrams, and cable count specifications for Phase 2 of the Tahoma Woods Housing Fiber Install Project at Mount Rainier National Park in Ashford, Washington. The project involves the installation of fiber optic cable and conduit infrastructure to provide telecommunications connectivity to housing units and administrative facilities within the park.
The scope of work includes installation of approximately 3,705 linear feet of new conduit ranging from 1x2" to 2x2.5" in diameter, creation of 10 new distribution vaults (Vaults #5-10), and utilization of 6 existing vaults and infrastructure. The fiber distribution network utilizes 120-fiber single-mode cable as the primary backbone with 6-fiber and 12-fiber drops to individual buildings (trailers T-101 through T-118). Key infrastructure points include the Admin Building Server Room/Main Distribution Frame, two Admin Building conduit boxes, a Trailer Pad Pedestal, and multiple housing unit termination points. The cable distribution employs a color-coded binder system (BLU, ORA, GRN, BRN, RED, WHT, BLK, YEL, VIO) for organizational purposes. A critical constraint noted is that a 320-foot segment of 120-fiber SM conduit between Vaults #6 and #7 requires asphalt cutting. The project includes specifications for mid-span access splices at multiple vault locations and requires mule tape with integrated tracer wire in all new conduit paths for future cable locatability.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T-108
T-115
T-102
T-110
T-202
T-101
T-001
T-116
T-104T-103
T-113
T-107
T-105
T-109
T-111
T-118T-117
EXISTING Conduit 1x2" (Vault #4 to T116, Approx 100 ft)
EXISTING Conduit 1x2" (Admin Bldg Box #1 to Server Room, Approx 105 ft)
EXISTING Conduit 1x3" (Vault #1 to Admin Bldg Box #1, Approx 325 ft)
EXISTING Conduit 1x3" (Vault #1 to Vault
#4, Approx 1275 ft)
NEW Conduit 1x2" (Vault #10 to
T117, Approx 45 ft)
NEW Conduit 1x2" (Vault #8 to T104, Approx, 70 ft)
NEW Conduit 2x2.5" (Vault #4 to Vault #5, Approx 75 ft)
NEW Conduit 1x2" (Vault #9 to T105, Approx 75 ft)
NEW 1x2" Conduit (Vault #6 to T113, Approx 75 ft)
NEW 1x2" Conduit (Vault #7 to T102, Approx 80 ft)
NEW Conduit 1x2" (Vault #5 to T118, Approx 95 ft)
NEW 1x2" Conduit (Vault #7 to T111, Approx 95 ft)
NEW Conduit 1x2" (Vault #9 to T107, Approx 100 ft)
NEW Conduit 1x2" (Vault #6 to Trailer Pad
Pedestal, Approx 100 ft)
NEW Conduit 1x2" (Vault #8 to T103, Approx 110 ft)
NEW Conduit 2x2.5" (Vault #6 to Vault #7, Approx 320 ft)
EXISTING
Vault #1
EXISTING
Vault #1A
EXISTING
Vault #1B
EXISTING
Vault #2
EXISTING
Vault #3
EXISTING
Vault #4
NEW Vault #5
NEW Vault #6 NEW Vault #7
NEW Vault #8 NEW Vault #9
NEW Vault #10
Admin Bldg Server
Room / MDF
Admin Bldg Conduit Box #2
Admin Bldg Conduit Box #1
Trailer Pad Pedestal
Microsoft, Vantor
0 500 1,000250 Feet
Mount Rainier National Park
Tahoma Woods Housing Fiber Install Project
Ashford, WA
Phase 2 Project Main Layout Map
SOW Appendix A
Vaults - NEW NEW Vault #10
NEW Vault #5
NEW Vault #6
NEW Vault #7
NEW Vault #8
NEW Vault #9
Points Admin Bldg Conduit Box #1
Admin Bldg Conduit Box #2
Admin Bldg Server Room / MDF
Trailer Pad Pedestal
Vaults - EXISTING EXISTING Vault #1
EXISTING Vault #1A
EXISTING Vault #1B
EXISTING Vault #2
EXISTING Vault #3
EXISTING Vault #4
Conduit Paths - NEW NEW 1x2" Conduit (Vault #6 to T112, Approx 105 ft)
NEW 1x2" Conduit (Vault #6 to T113, Approx 75 ft)
NEW 1x2" Conduit (Vault #7 to T101, Approx 105 ft)
NEW 1x2" Conduit (Vault #7 to T102, Approx 80 ft)
NEW 1x2" Conduit (Vault #7 to T110, Approx 110 ft)
NEW 1x2" Conduit (Vault #7 to T111, Approx 95 ft)
NEW Conduit 1x2" (Vault #10 to T117, Approx 45 ft)
NEW Conduit 1x2" (Vault #4 to Vault #10, Approx 180 ft)
NEW Conduit 1x2" (Vault #5 to T118, Approx 95 ft)
NEW Conduit 1x2" (Vault #6 to Trailer Pad Pedestal, Approx 100 ft)
NEW Conduit 1x2" (Vault #8 to T103, Approx 110 ft)
NEW Conduit 1x2" (Vault #8 to T104, Approx, 70 ft)
NEW Conduit 1x2" (Vault #8 to T108, Approx 120 ft)
NEW Conduit 1x2" (Vault #8 to T109, Approx 70 ft)
NEW Conduit 1x2" (Vault #9 to T105, Approx 75 ft)
NEW Conduit 1x2" (Vault #9 to T107, Approx 100 ft)
NEW Conduit 2x2.5" (Vault #4 to Vault #5, Approx 75 ft)
NEW Conduit 2x2.5" (Vault #5 to Vault #6, Approx 280 ft)
NEW Conduit 2x2.5" (Vault #6 to Vault #7, Approx 320 ft)
NEW Conduit 2x2.5" (Vault #7 to Vault #8, Approx 250 ft)
NEW Conduit 2x2.5" (Vault #8 to Vault #9, Approx 205 ft)
Conduit Paths - EXISTING Description
EXISTING Conduit 1x2" (Admin Bldg Box #1 to Server Room, Approx 105 ft)
EXISTING Conduit 1x2" (Vault #4 to T115, Approx 12 ft)
EXISTING Conduit 1x2" (Vault #4 to T116, Approx 100 ft)
EXISTING Conduit 1x3" (Vault #1 to Admin Bldg Box #1, Approx 325 ft)
EXISTING Conduit 1x3" (Vault #1 to Vault #4, Approx 1275 ft)
Trails
Buildings
Roads
Inset 1
Inset 2
To SR706
238th Ave E Housing Area Loop Road
238th Ave E Admin Building & Parking Area
Staging Area
Staging Area
Staging Area
Inset 3
T-001
T-117
EXISTING Conduit 1x2" (Admin Bldg Box #1 to Server Room, Approx 105 ft)
EXISTING Conduit 1x3" (Vault #1 to Admin Bldg Box #1, Approx 325 ft)
EXISTING Conduit 1x3" (Vault #1 to Vault
#4, Approx 1275 ft)
EXISTING Conduit 1x3" (Vault #1 to Vault
#4, Approx 1275 ft)
EXISTING
Vault #1
EXISTING
Vault #1A
EXISTING
Vault #1B
EXISTING
Vault #2
Admin Bldg Server Room / MDF
Admin Bldg Conduit Box #2
Admin Bldg Conduit Box #1
Microsoft, Vantor 0 150 30075 Feet
Staging Area
Mount Rainier National Park Tahoma Woods Housing
Fiber Install Project Ashford, WA
Phase 2 Project Layout Map - Inset 1
238th Ave E Admin Building & Parking Area
To SR706
238th Ave E Housing Area Loop Road
T-115
T-116
T-113
T-118 T-117
EXISTING Conduit 1x2" (Vault #4 to
T115, Approx 12 ft)
EXISTING Conduit 1x2" (Vault #4 to T116, Approx 100 ft)
EXISTING Conduit 1x3" (Vault #1 to Vault
#4, Approx 1275 ft)
EXISTING Conduit 1x3" (Vault #1 to Vault
#4, Approx 1275 ft)
EXISTING Conduit 1x3" (Vault #1 to Vault #4, Approx 1275 ft)
NEW Conduit 1x2" (Vault #10 to T117, Approx 45 ft)
NEW Conduit 2x2.5" (Vault #6 to Vault #7, Approx 320 ft)
NEW Conduit 2x2.5" (Vault #4 to Vault #5, Approx 75 ft)
NEW Conduit 1x2" (Vault #5 to T118, Approx 95 ft)
NEW Conduit 1x2" (Vault #6 to Trailer Pad
Pedestal, Approx 100 ft)
NEW Conduit 1x2" (Vault #4 to Vault
#10, Approx 180 ft)
NEW Conduit 2x2.5" (Vault #5 to Vault #6, Approx 280 ft)
EXISTING
Vault #2
EXISTING
Vault #3
EXISTING
Vault #4
NEW Vault #5
NEW Vault #6
NEW Vault #10
Trailer Pad Pedestal
Microsoft, Vantor 0 150 30075 Feet
Staging Area
Mount Rainier National Park Tahoma Woods Housing
Fiber Install Project Ashford, WA
Phase 2 Project Layout Map - Inset 2
238th Ave E
T-108
T-112
T-102
T-110
T-101
T-104T-103
T-113
T-107
T-105
T-109
T-111
NEW Conduit 1x2" (Vault #6 to Trailer Pad
Pedestal, Approx 100 ft)
NEW Conduit 1x2" (Vault #8 to T104, Approx, 70 ft)
NEW Conduit 1x2" (Vault #8 to T109, Approx 70 ft)
NEW Conduit 1x2" (Vault #9 to T105, Approx 75 ft)
NEW 1x2" Conduit (Vault #6 to T113, Approx 75 ft)
NEW 1x2" Conduit (Vault #7 to T102, Approx 80 ft)
NEW 1x2" Conduit (Vault #7 to T111, Approx 95 ft)
NEW Conduit 1x2" (Vault #9 to T107, Approx 100 ft)
NEW 1x2" Conduit (Vault #7 to T101, Approx 105 ft)
NEW 1x2" Conduit (Vault #6 to T112, Approx 105 ft)
NEW 1x2" Conduit (Vault #7 to T110, Approx 110 ft)
NEW Conduit 1x2" (Vault #8 to T103, Approx 110 ft)
NEW Conduit 1x2" (Vault #8 to T108, Approx 120 ft)
NEW Conduit 2x2.5" (Vault #8 to Vault #9, Approx 205 ft)
NEW Conduit 2x2.5" (Vault #7 to Vault #8, Approx 250 ft)
NEW Conduit 2x2.5" (Vault #6 to Vault #7, Approx 320 ft)
NEW Vault #6
NEW Vault #7
NEW Vault #8 NEW Vault #9
Microsoft, Vantor 0 150 30075 Feet
Asphalt Cut
Staging Area
Mount Rainier National Park Tahoma Woods Housing
Fiber Install Project Ashford, WA
Phase 2 Project Layout Map - Inset 3
238th Ave E
1" = 1 1
1- -
Twoods/Nisqually Conduit/Fiber Install (Phase 2)
Hicks, Casey A 15 FEB 2026
NPS MORA IT/
Telecom Program
55210 238 th
Ave E
Ashford, WA 98304
360-569-6555
SOW Appendix B
Fiber/Conduit Layout Diagram
1" = 1 1
1- -
Twoods/Nisqually Conduit/Fiber Install (Phase 2)
Hicks, Casey A 15 FEB 2026
NPS MORA IT/
Telecom Program
55210 238 th
Ave E
Ashford, WA 98304
360-569-6555
SOW Appendix B
Fiber/Conduit Layout Diagram
B
SCALE
SIZE
SHEET OF
REVFSCM NO DRAWING NUMBER
DRAWING TITLE
PROJECT
DRAWN BY DATE
COMPANY
C DBA
C DBA
B
SCALE
SIZE
SHEET OF
REVFSCM NO DRAWING NUMBER
DRAWING TITLE
PROJECT
DRAWN BY DATE
COMPANY
C DBA
C DBA
NOTES:
Statement of Work supersedes this drawing. This drawing is intended to provide clarity in the work to be completed, but is not intended to deviate from what has been contractually obligated within the Statement of
Work. Any discrepancies shall be brought to the attention of the COR & Project Lead.
All new conduit paths shall include mule tape with weaved-in tracer wire for future use and so cable can be locatable when dielectric fiber cable is used
T001 Admin Bldg – Server Room
ODF (120F SM LC/UPC)
Admin Bldg
Box #2
120F SM
550 ft
120F SM
40 ft
120F SM
90 ft
120F SM
40 ft
120F SM
115 ft
120F SM
160 ft
120F SM
250 ft
Vault #4
Mid-Span
Access Splice
120F SM
300 ft
12F SM
50 ft
12F SM
180 ft
6F SM
30 ft
6F SM
100 ft
Admin Bldg
Box #1 Vault #1B Vault #1A Vault #1
Vault #2 Vault #3
Vault #10 Bldg T117
Apartments Bldg T115
Exterior NID
Bldg T116
Exterior NID
Interior RM FDP
Vault #5
Mid-Span
Access Splice
120F SM
75 ft
Bldg T118
Apartments
Interior RM FDP
12F SM
100 ft
12 6 6 12
Bldg T112
Exterior NID
Bldg T113
Exterior NID
Trailer Pad
Pedestal
Exterior NID
6F SM
75 ft
6F SM
100 ft
6F SM
105 ft
120 SM
280 ft
Vault #6
Mid-Span
Access Splice
6 66
Vault #7
Mid-Span Access
Splice
6 66 6
120F SM – 320 ft - ASPHALT CUT REQUIRED
Bldg T110
Exterior NID
Bldg T101
Exterior NID
Bldg T102
Exterior NID
Bldg T111
Exterior NID
6F SM
105 ft
6F SM
80 ft
6F SM
110 ft
6F SM
95 ft
Vault #8
Mid-Span Access
Splice
6 66 6
Bldg T108
Exterior NID
Bldg T103
Exterior NID
Bldg T104
Exterior NID
Bldg T109
Exterior NID
6F SM
110 ft
6F SM
70 ft
6F SM
110 ft
6F SM
95 ft
120F SM
250 ft
ALL DISTANCES LISTED ARE APPROXIMATE. Vendors will need to wheel their own measurements if more accuracy is required.
Vault #9
End-Span
Access Splice
6 6
Bldg T105
Exterior NID
Bldg T107
Exterior NID
6F SM
75 ft
6F SM
100 ft
120F SM
205 ft
“Interior FDP RM” refers to rackmount 1U fiber patch (distribution) panel trays, 12-Fiber /w LC/UPC connectors.
“Exterior NID” refers to an outdoor wall-mount FTTH 6-fiber /w LC/UPC connectors. Boxes shall be mounted outside the utility/laundry room of each housing unit (near rear center of each building).
5 A Fiber Count Diagram has been established for mid-span access distribution of the 120F cable and is included with this drawing. All splicing shall follow the fiber count diagram.
SOW Appendix C Cable Distribution Count Diagram
Revision Date: 2/15/2026
Binder Fiber # Vault Building Fiber ID Binder Fiber # Vault Building Fiber ID
001 001 061 001 002 002 062 002 003 003 063 003 004 004 064 004 005 005 065 005 006 006 066 006 007 007 067 001 008 008 068 002 009 009 069 003 010 010 070 004 011 011 071 005 012 012 072 006 013 001 073 001 014 002 074 002 015 003 075 003 016 004 076 004 017 005 077 005 018 006 078 006 019 001 079 001 020 002 080 002 021 003 081 003 022 004 082 004 023 005 083 005 024 006 084 006 025 001 085 001 026 002 086 002 027 003 087 003 028 004 088 004 029 005 089 005 030 006 090 006 031 007 091 001 032 008 092 002 033 009 093 003 034 010 094 004 035 011 095 005 036 012 096 006 037 001 097 001 038 002 098 002 039 003 099 003 040 004 100 004 041 005 101 005 042 006 102 006 043 001 103 001 044 002 104 002 045 003 105 003 046 004 106 004 047 005 107 005 048 006 108 006 049 001 109 001 050 002 110 002 051 003 111 003 052 004 112 004 053 005 113 005 054 006 114 006 055 001 115 001 056 002 116 002 057 003 117 003 058 004 118 004 059 005 119 005 060 006 120 006
FEED DISTRIBUTION / DROP
BLU
Vault 04
T117 Apts
(via vault 10)
ORA
T115
T116
GRN Vault 05 T118 Apts
BRN
Vault 06
Trailer Pad
T112
SLT
T113 future (no splice)
T101
T102
RED
T110
T111
Mount Rainier National Park Tahoma Woods Housing Fiber Install Project - Phase 2
VIO Vault 09
T105
T107
FEED DISTRIBUTION / DROP
BLK
Vault 08
T103
T104
YEL
T108
T109
WHT
Vault 07
| Appendix A - Phase 2 Main Layout Map |
| Phase 2 Layout Inset 1 |
| Phase 2 Layout Inset 2 |
| Phase 2 Layout Inset 3 |
| Appendix B - Phase 2 Layout Diagrams |
| Phase 2 Layout Diagrams.vsdx |
| Phase 2 Diagram |
| Appendix C - Fiber Count Diagram |
| Cable Dist Count Diagram |
File details come from the government source that posted it. Updated .