This is Amendment 0003 to Solicitation 140P8326Q0014, issued by the National Park Service (NPS), Power (PWR) - Olympic Mountains Area Maintenance Operations (OLYM MABO) located in Port Angeles, Washington. The amendment is effective February 18, 2026, and extends the contractor questions deadline from March 9, 2026 at 12:00 PM PT to March 23, 2026 at 12:00 PM PT, and extends the solicitation close date from March 19, 2026 at 3:00 PM PT to April 2, 2026 at 3:00 PM PT.

The amendment provides an amended Statement of Work (SOW) with specific technical modifications. Key changes include: (1) Feeder Cable Installation (Section 1.2(a)(1)) now specifies a "minimum" 120-strand single-mode fiber optic cable with an alternative option for a 144-fiber cable if sourcing the 120-fiber cable is more difficult or costly; (2) Ethernet Cable Installation (Section 1.2(d)(2)) replaces Cat6E requirements with Cat6A cable, with standard Cat 6 Ethernet cable as an acceptable alternative; and (3) Asphalt work (Section 3.6) includes additional construction and asphalt application requirements as mandated by park maintenance operations, with all other sections remaining unchanged. The amendment also incorporates contractor questions and answers from the March 4, 2026 site visit and includes an example Network Interface Device (NID) diagram. Offers must acknowledge receipt of this amendment prior to the extended solicitation close date by completing the required forms or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Marzjele Chisolm

See continuation page

NPS, PWR - OLYM MABO

600 E. Park Avenue Port Angeles WA 98362-6757

PPY

140P8326Q0014

02/18/2026

02/18/2026

1 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P8326Q0014/0003

Amendment 0003 - The purpose of this amendment is to:

1. Post continued contractor's Questions and

Answers.

2. Extend contractor questions deadline from

3/9/2026 at 12p PT to 3/23/2026 at 12p PT.

3. Extend solicitation close date from

3/19/2026 at 3p PT to 4/2/2026 at 3p PT.

2. Provide amended SOW to include the changes listed below:

List of changes:

1.2(a)(1)

Original Text:

Feeder Cable Installation: The Contractor shall procure and pull a 120-strand single-mode fiber optic feeder cable from the designated Optical

Distribution Frame (ODF) located in the server room of the Administration Building, through existing and new vaults/conduit to the furthest vault in the housing area for mid-span cable distribution.

Changes:

Added "minimum" after "120-strand"

Added "A 144-fiber cable is alternately acceptable if sourcing a 120-fiber cable is more difficult or costly." at the end of the paragraph

1.2(d)(2)

Original text:

Ethernet Cable Installation: The Contractor shall supply and install an RJ-45 patch panel and pull and terminate one (1) Cat6E Ethernet cable from the patch panel to each WAP location.

Changes:

Replaced "Cat6E" with "Cat6A"

Added "Use of standard Cat 6 Ethernet cable is also acceptable." at the end of the paragraph.

3.6 ASPHALT

Added additional requirements in sections E

"construction" and F "asphalt application" as required by park maintenance responsible for maintaining the road. All other sections were kept intact.

Amendment 0002 - The purpose of this amendment is to publish Amendment 0001's documents that

Continued...

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P8326Q0014/0003 were not uploaded properly.

Amendment 001 - The purpose of this amendment is to publish contractor questions and answers that came out of the site visit held on

3/4/2026. Please see attached Q&A's, along with an example of a NID as covered in the Q&A's.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .