Attachment_4_SOW_MORA_T-Woods_Fiber_Optic_Cable_Install_.pdf
PDF 452 KB Posted
- Attached to
- MORA TAHOMA WOODS FIBER OPTIC INSTALL
- Solicitation number
- 140P8326Q0014
About this file
This is a Statement of Work (SOW) for the Mount Rainier National Park Tahoma Woods Fiber Optic Cable Installation project. The project involves engineering, furnishing, installing, and testing a complete underground single-mode fiber optic passive FTTx feeder/distribution network to support a future Active Optical Network for government housing at Tahoma Woods, located approximately 38 miles southeast of Tacoma, Washington within Mount Rainier National Park boundaries. The work excludes installation of active electronics and spans approximately 0.4 miles within the developed housing area.
The scope includes installation of 120-strand single-mode fiber optic feeder cable from an Optical Distribution Frame in the Administration Building server room through existing and new vaults/conduit to Vault 10, with mid-span cable distribution through six subsurface vaults maintaining 50-75 feet of slack per vault. Inside Plant requirements include supplying and installing one high-density 120-fiber LC/UPC connector ODF in the server room. Building entrance work involves 12-strand SMFO riser/lateral cables to apartment buildings with low-count fiber patch panels, 6-fiber drops to 14 single-family homes and one trailer pad with exterior demarcation boxes, and EMT conduit with Cat6E Ethernet cables to four Wireless Access Point locations per apartment building. Testing requires 100% end-to-end Tier 1 and Tier 2 fiber optic testing with deliverables including as-built drawings, OTDR trace reports, and fiber termination maps. The contract anticipates award in early to mid-April 2026, with work expected to start within 10 days of notice to proceed and be completed within 45 days. A required site visit is scheduled for Wednesday, March 4, 2026, from 12 PM to 3 PM PT, with additional one-off visits available during March 2-6. Contractors must submit confirmation of site visit attendance by email to casey_hicks@nps.gov by Friday, February 27, 2026.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MORA – Tahoma Woods Fiber Optic Cable Install Solicitation No: 140P8326Q0014
TABLE OF CONTENTS - 1
MOUNT RAINIER NATIONAL PARK
TAHOMA WOODS (TWOODS) HOUSING FIBER
OPTIC CONDUIT & CABLE INSTALLATION
PROJECT SPECIFICATIONS December 2025
Developed By:
Division of Administration & Business Services Information Technology & Telecommunications Branch
55210 238th Avenue East
Ashford, WA 98304
MORA – Tahoma Woods Fiber Optic Cable Install
TABLE OF CONTENTS - 1
TABLE OF CONTENTS
DIVISION, SECTION & PARAGRAPH NUMBERING
The numbering and lettering of sections and paragraphs in this Statement of Work (SOW) are merely for identification. Sections included are listed in this Table of Contents together with the number of pages in each section.
NUMBER TITLE NO. OF PAGES
00 01 10 Table of Contents
DIVISION 01 – GENERAL REQUIREMENTS
01 00 00 General Requirements
DIVISION 27 – COMMUNICATIONS
27 05 00 Common Work Results for Communications 27 05 43 Underground Ducts and Raceways for Communications Systems 27 13 23 Optical Fiber Backbone Cabling……………………………………………………….32
END OF SECTION
DIVISION 01
GENERAL REQUIREMENTS
01 00 00 - 4 GENERAL REQUIREMENTS MORA – Tahoma Woods Fiber Optic Cable Install
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 – GENERAL
1.1 PROJECT LOCATION
This project is located at Tahoma Woods, an approximately 210-acre developed area along State Route 706 between Elbe and Ashford WA which is within the boundaries of Mount Rainier National Park.
This area is approximately thirty-eight (38) miles southeast of Tacoma, WA. The onsite project work area spans approximately four tenths (0.4) of a mile within the developed area.
SITE VISIT: A site visit is REQUIRED for this project.
Site Details:
Address: 55210 238th Ave E, Ashford, WA 98304. Interested contractors will meet Park staff at Park HQ and will be guided through the area where the work will be completed.
Interested vendors are required to contact Casey Hicks via email to sign up for the site visit at casey_hicks@nps.gov no later than Friday, February 27 at 3p PT. Phone calls will not be accepted.
A single consolidated site visit will be held on Wednesday, March 4, 2026 from 12pm to 3pm PT.
The Park is offering to do one-off site visits during the week of March 2 to March 6 for contractors that cannot make it during Wednesday’s site visit. Email Casey Hicks for scheduling.
1.2 SCOPE OF WORK
The Contractor shall Engineer, Furnish, Install, and Test (EFI&T) a complete, turnkey underground single-mode fiber optic (SMFO) passive FTTx feeder/distribution network to support a future Active Optical Network (AON) for the Tahoma Woods government housing area. This project excludes the installation of active electronics.
A. Outside Plant (OSP) Infrastructure
1. Feeder Cable Installation: The Contractor shall procure and pull a 120-strand single-mode fiber optic feeder cable from the designated Optical Distribution Frame (ODF) located in the server room of the Administration Building, through existing and new vaults/conduit to the furthest vault in the housing area for mid-span cable distribution.
2. Pathway & Containment: All underground cabling shall be installed in existing or new conduit systems as specified in the drawings included in the appendix of this document. The Contractor shall ensure the use of tracer wire and pull-tapes with linear length markers in all installed segments.
3. Subsurface Vaults & Splicing: The Contractor shall supply and install six (6) subsurface vaults (handholes) for mid-span access and express fiber splicing to distribute fibers to downstream buildings while maintaining continuity of remaining fibers toward subsequent vaults. Splicing shall be performed using the fusion splicing method to minimize attenuation, with all splices housed in environmentally sealed Fiber Optic Splice Closures (FOSC). A fiber splice spreadsheet is included in the appendix of this document to recommend which feeder fibers can be spliced to drop cables or expressed to prevent the need to split cable binders between vaults.
4. Slack Loops: Minimum slack storage (e.g., 50-75 feet) shall be maintained in each vault to facilitate future maintenance and re-splicing. Vaults should be appropriately sized to facilitate both FOSCs and slack loops without causing undue bend stress on cabling.
01 00 00 - 5
B. Inside Plant (ISP) & Terminal Equipment
1. Optical Distribution Frame (ODF): The Contractor shall supply and install one (1) high-density rackmount ODF sufficient for 120 fibers total and provide patching capability for future electronics. ODF shall be installed in an existing rack at a predetermined position within the server room of the Headquarters/Administration Building and fully spliced to the 120-fiber feeder cable entering the building. The ODF shall be fully populated with 120 LC/UPC connectors and include cable management hardware.
C. Building Entrances (MDU/Residential)
1. Apartment Buildings: For each 8-unit apartment building, the Contractor shall supply and install all necessary PVC building entrance conduit through the floor and 12-strand SMFO riser/lateral cable terminating to LC/UPC connectors in a low-count fiber patch panel supplied and installed by the contractor within an existing wall-mount equipment rack/cabinet located in the storage room of each building, adjacent to the mechanical room.
2. Single-Family Homes/Trailer Pad: Individual drops of 6-fiber cable shall be routed through newly placed drop conduits to 14 houses and one trailer pad. Contractor shall supply and install a fiber demarcation box (also known as a Network Interface Device, or NID) outside the laundry room of each house, terminating to the LC/UPC connections inside. For the trailer pad the demarcation box shall be located on the back side of a brown painted wood panel used to mount an electrical panel and EV charging equipment.
D. Future Wireless Access Point (WAP) preparation for Apartment Buildings
1. Conduit Installation: The Contractor shall supply and install Electrical Metallic Tubing (EMT) conduit, boxes, and associated hardware from the building’s equipment rack to four (4) predetermined WAP locations on the outside veranda of each apartment building.
2. Ethernet Cable Installation: The Contractor shall supply and install an RJ-45 patch panel and pull and terminate one (1) Cat6E Ethernet cable from the patch panel to each WAP location.
3. Specifications: EMT shall be installed with fittings appropriate for moisture resistance in outdoor/damp areas. At each WAP location, Contractor to supply and install 2-gang electrical boxes with no faceplate and terminated RJ-45 keystone jack coiled up inside each box.
E. Testing and Acceptance
1. Link Loss Testing: The Contractor shall perform end-to-end Tier 1 (Optical Loss Test Set) and
Tier 2 (Optical Time Domain Reflectometer - OTDR) testing on 100% of the newly installed fiber strands.
2. Documentation: Deliverables shall include As-Built drawings (showing vault locations and cable routes), OTDR trace reports, and a final fiber termination map.
3. Workmanship: All work shall be performed in a "neat and workmanlike manner" in compliance with NEC, BICSI, and local base telecommunications standards.
1.3 WORK RESTRICTIONS
A. Site Access: Contractor staff accessing the project site does not entail any special needs except for access to the ODF location within the server room of the Headquarters/Administration Building. Per federal regulations, staff without sufficient physical security credentials shall require an escort by local IT staff within the building.
01 00 00 - 6
D. Period of Performance: Timing of work shall be coordinated with the Contracting Officer and follow the approved Contractor’s work schedule. Anticipated contract award time frame is early to mid-April, 2026. Work is expected to start within ten (10) days after notice to proceed and be completed within 45 days of starting work.
E. Work Hours: Work hours are from 7:00 am to 5:30 pm Monday through Friday. Weekend and holiday work will normally not be allowed. Special requests may be made through the Contracting Officer / Contracting Officer’s Representative (COR).
F. Staging and Storage of Materials: Confine storage of equipment and materials to the staging/lay-down/storage areas identified within the area designated by the Contracting Officer / COR or as established at the preconstruction meeting. The parking lot near the Administration/Headquarters Building may be considered if normal operations are not impacted. All staging and stockpiling areas shall be returned to pre-construction conditions following construction.
G. Vehicles & Equipment: Confine parking to areas designated for parking or staging of materials and equipment throughout the non-public areas of the project site.
1. No unattended motors/engines are permitted. No idling of motors or engines for extended periods of time is permitted.
2. Fueling of any type, whether equipment or vehicles, must be done either on non-pervious surfaces such as concrete or asphalt, or deploy a spill containment pad.
3. Equipment must be free of any fluid leaks (fuel, oil, hydraulic fluid, etc.) upon arrival to the work site and will be inspected at the beginning of each shift for leaks. Leaking equipment will be removed off site for necessary repairs before the commencement of work.
H. Existing Utilities: Notify Contracting Officer / COR of proposed locations and times for excavation.
1. Pursuant to the Federal Enclave Doctrine, Washington State laws concerning utility locates (RCW 19.122) do not apply on lands within exclusive federal jurisdiction, however OSHA and other applicable federal regulations and statutes still apply. It is imperative for the safety of all personnel involved that the need for utility locates be fully communicated ahead of time with both project and contracting staff, and requests fully signed off prior to any excavation taking place.
2. Utilities infrastructure within the boundaries of the Park is owned by a combination of Mount Rainier National Park and other utility companies (primarily Puget Sound Energy, Lewis County PUD, and CenturyLink). An internal park-level utilities locate request form MUST be completed in full and submitted through the COR for ANY AND ALL underground utilities. The Park will contact DigSafeWA OneCall (“811”) on the contractor’s behalf as needed for locates of contracted utilities.
3. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repairs shall be made at no additional expense to the Government.
4. If damage occurs to an unknown utility, an equitable adjustment will be made for repairs in accordance with the Changes clause of the contract.
I. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer / COR not less than five (5) business days in advance of
01 00 00 - 7 proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
J. Preservation of Natural Features:
1. Before entering the park, all workers shall check vehicles, equipment, tools, boots, and backpacks for weed seeds, mud that could harbor weed seeds, and plant parts. All equipment shall be power washed and inspected before work begins to ensure it is free of non-native weeds and/or seeds. The park requires and will perform inspections to ensure non-transport of non-native species BEFORE equipment is off-loaded. Contact the COR at least (3) three days in advance of park entry to arrange for an inspection(s) at the loading dock or point of origin.
2. Re-use fill, rock, or topsoil from the project area, if possible. If not possible, or for utility bedding purposes, Contractor shall submit a list of proposed sources, end-use, and temporary storage requirements for imported material, 30 calendar days before delivery.
The sources of imported rock, sand, gravel, and soil shall be inspected for invasive non-native plants, weeds, and/or seeds. The material must not be stockpiled at the quarry for more than 1 week after washing. If material comes from older stockpiles, the quarry must be certified weed-free by the County Noxious Weed Coordinator, or a qualified weed inspector designated by NPS. For details on obtaining pit inspections and topsoil specifications, contact Contracting Officer’s Representative (COR) and provide at least 14 days’ notice that an inspection is needed. Imported material shall be free of non-native weeds and/or seeds. Imported material shall be shipped directly from the source to the park without intermediary storage or staging. Shipping vessels shall be covered, if necessary, to prevent spillage or blowing off their contents while in transit.
3. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
4. Provide temporary barriers to protect existing trees and plants and root zones.
5. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer’s Representative (COR) and remove agreed-on roots and branches that interfere with construction.
6. Do not fasten ropes, cables, or guys to existing trees.
7. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage. Where utility excavation or trenching intersects root systems of larger trees, cut roots greater than 3 inches in diameter cleanly with a sharp tool such as a saw (i.e. do not tear with the excavator).
8. Care shall be taken not to disturb any wildlife species (reptiles, migratory birds, raptors, or bats) found nesting, hibernating, estivating, or otherwise living in, or immediately nearby, worksites.
9. Remove all materials, including trash and food wastes, from project site daily to reduce the attraction of murrelet predators, such as crows and jays.
10. All disturbed ground shall be reclaimed using appropriate best management practices, which may include planting or seeding with native vegetation, or, in the case of small treatment areas, allowing native vegetation to reclaim the area naturally. Contractor shall consult with Contracting Officer’s Representative to determine the best methods for restoration.
I. Archaeological Resources: Archaeological resources are physical pieces of evidence of past human activity, including evidence of the effects of that activity on the environment.
01 00 00 - 8
Archaeological resources are found above and below the ground and underwater.
1. No archaeologically sensitive areas have been identified within the proposed project area. However, archaeological monitoring will be required during all ground-disturbing activity unless deemed otherwise by the NPS. Contractor shall provide a minimum of three weeks’ notice before beginning trenching or excavation so that an archaeologist can be available.
2. If unknown archaeological resources are discovered during construction, the contractor shall stop work or relocate work to a non-sensitive area until resources can be properly recorded and evaluated and contact the Contracting Officer / COR immediately.
Measures shall be taken to avoid further resource impacts or to mitigate their loss or disturbance.
K. Driveways and Entrances: Keep driveways, areas specifically designated by the Contracting Officer, and entrances serving premises clear and available to Government, Government employees, user groups, and emergency vehicles always. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize the use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for the storage of materials and equipment on-site.
L. Construction Camp: The establishment of a camp within the park is not permitted.
M. Hauling Restrictions: Comply with legal load restrictions in hauling of materials.
Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment
N. Restore all traffic/parking/security signs and markings, including space numbers, designations, and lines, to their original form if such signs/markings are defaced or deleted during construction/repair.
O. Control and provide security of Contractor-owned equipment and materials at the worksite.
Report immediately missing/lost/stolen property to Park Dispatch at 360-569-6100.
1.4 PROJECT MEETINGS
A. Preconstruction Conference: Before the start of construction, the Contracting Officer will arrange an on-site or virtual meeting with the Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Coordination of Subcontractors
5. Labor law application
6. Modifications
7. Payments to Contractor
01 00 00 - 9
8. Payroll reports
9. Contract time
10. Display of required posters
11. Notice to proceed
12. Correspondence procedures
13. Acceptance/rejection of work
14. Progress meetings
15. Submittal procedures
16. Environmental requirements
17. Saturday, Sunday, holiday, and night work
18. Schedule of Values
B. Progress Meetings: The Contracting Officer’s Representative may schedule weekly or biweekly site meetings with the Contractor once onsite work commences. The Contractor shall be responsible for facilitating progress meetings and ensuring that the appropriate entities involved in planning, coordination, or performance of upcoming work activities are represented at these meetings.
1.5 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one (1) week after the Pre-Construction Conference. Contracting Officer will notify the Contractor of the tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A comprehensive breakdown of the Schedule of Values
4. Accident Prevention Plan and/or SSSP
5. Safety Plan (SSSP) is a written plan that outlines the scope of work proposed, the safety practices and mitigations to be taken for identified hazards/risks, contractor roles and responsibilities, and any additional pertinent program element or requirements for a specific construction project that the provided scope of work is associated with.
6. A list of Subcontractors for this project
7. Written statements from subcontractors certifying compliance with applicable labor standard clauses, using SF1413
8. Satisfactory evidence of liability insurance coverage and worker’s compensation for the
Contactor and all subcontractors
9. Quality Control Plan
B. All items listed must be provided to the Contracting Officer after the Pre-Construction
Conference is held. Failure to provide these documents within one (1) week of the Pre- Construction Conference will result in the Notice to Proceed not being issued, and the Contracting Officer will consider other contractual remedies. On-site work shall not commence until a written Notice to Proceed has been issued.
C. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Contracting Officer will return without review, submittals received from sources other than the Contractor.
1. CM-16 Transmittal Form: All material submittals shall be transmitted using National
Park Service form CM-16. (This form can be downloaded from the Workflows website at http://www.nps.gov/dscw/con_subreview21.htm.) No action will be taken on a http://www.nps.gov/dscw/con_subreview21.htm
01 00 00 - 10 material submittal item unless accompanied by the transmittal form.
2. Documents required in Division 1 should be submitted with the CM-16 Transmittal form, as well, but may be submitted as a single Division 1 package.
1.6 ACCIDENT PREVENTION PROGRAM
A. The Contractor is responsible for establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1. Ensure compliance with OSHA and project requirements.
2. Provide adequate first aid facilities for the number of employees and the type of construction at the site.
B. Accident Reporting:
1. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to the Contracting Officer an Accident/Property Damage Report (Form CM-22). This form may be obtained from the Contracting Officer.
2. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
1.7 QUALITY CONTROL PROGRAM
A. The Contractor is responsible for all testing and inspections required by the project Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance comply with applicable specifications, drawings, and codes.
1. Engage a qualified testing agency to perform these quality-control services.
2. Submit the appropriate report for each quality-control service.
3. Testing and inspecting requested by the Contractor and not required by the
Contract Documents are the Contractor's responsibility.
4. The Contracting Officer / COR may designate test locations.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve the Contractor of responsibility for compliance with the Contract Document requirements. The quality of all work shall be the responsibility of the Contractor.
1.8 TEMPORARY FACILITIES
A. Sanitary Facilities: Public restrooms are available at the Headquarters building.
Contractor may supply properly lighted and ventilated, weather-proof, lockable, portable toilets with handwashing or sanitizing capability located in the designated material and equipment staging area. The contractor shall properly pump/empty these toilets regularly, and keep the toilet clean so as not to attract insects/animals.
B. Water: Potable water is available at the site in small quantities. Note that there are no fire
01 00 00 - 11 hydrants available for rapid filling. Coordinate any use and connection with Contracting Officer / COR.
C. Telephone Service: No landline telephone service is available on site for the Contractor’s use.
The project site does have reliable cellular phone coverage.
D. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Recycling is encouraged.
E. Fire Prevention & Protection: A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe work procedures.
1. Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters.
2. Locate internal combustion equipment so that exhausts are discharged well away from combustible materials.
3. Smoking: Smoking on the construction site is prohibited.
4. Vehicles & Equipment: Provide one extinguisher on each vehicle or piece of equipment.
F. Traffic Controls: Erect and maintain barricades, lights, danger signals, and warning signs following the Manual on Uniform Traffic Control Devices (MUTCD), the latest edition.
1. Protect existing site improvements to remain including curbs, pavement, and utilities.
2. Adequately barricade and post open cuts in or adjacent to thoroughfares.
3. Protect pedestrian traffic by guardrails or fences.
4. When pedestrian traffic is detoured onto a roadway, provide temporary walkways with protection as required at ends.
5. Cover pipes, hoses, and power lines crossing sidewalks and walkways with troughs using beveled edge boards.
6. Install Barrier Tape where directed by the Contracting Officer / COR. Keep a minimum of two
(2) rolls on-site at all times.
1.9 PROJECT CLOSEOUT
A. Maintain one complete set of contract drawings and one full-size set of vendor-supplied drawings. Mark changes, deletions, and additions to show actual construction conditions.
Show additions in red, deletions in green and special instructions in blue. On completion of the total project, submit complete record drawings. Include all shop drawings, sketches, and additional drawings that are to be included in the final set, with clear instructions showing the location of these drawings.
B. Complete the following closeout requirements before requesting a final inspection:
1. Submit electronic copies of any product operation and maintenance manuals, product cut sheets, specific warranties, guarantees, final certifications, and similar documents.
2. Submit performance testing reports.
3. Remove temporary facilities, construction tools, and similar elements from the project site.
4. Complete final cleaning and site restoration requirements.
5. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.
01 00 00 - 12
6. Instruct NPS personnel in operation, adjustment, and maintenance of products, equipment, and systems.
1.10 FINAL INSPECTION, SUBSTANTIAL COMPLETION AND ACCEPTANCE PROCEDURES
A. Request final inspection in writing when project or designated portion of project is substantially complete. Contracting Officer will proceed with inspection within ten (10) days of receipt of written request or will advise Contractor of items that prevent project from being substantially complete.
B. If following final inspection, the work is determined to be substantially complete, the COR or Project Inspector will prepare a Punch List to be corrected before final acceptance and issue a Letter of Substantial Completion. The contractor shall complete the work described on the Punch List within seven (7) calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs following the Inspection of Construction clause of the contract.
C. If, following final inspection, the work is not determined to be substantially complete;
Contracting Officer will notify the Contractor in writing. Contractor shall request a new final inspection after completing work. All re-inspection costs may be charged against the Contractor following the Inspection of Construction clause of the contract.
D. After all Punch List items and deficiencies have been corrected, the Contracting Officer will issue a Letter of Final Acceptance.
PART 2 – PRODUCTS
1.1 ACTION SUBMITTALS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. Mark each copy of each submittal to show which products and options are applicable.
2. Include the following information, as applicable:
a. Manufacturer’s written recommendations.
b. Manufacturer’s product specifications.
c. Manufacturer’s installation instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to the Contracting Officer and keep another complete set of instructions at the project site until substantial completion.
d. Manufacturer’s catalog cuts: Submit only pertinent pages; mark each copy of standard printed data to identify specific products proposed for use.
e. Wiring diagrams showing factory-installed wiring.
f. Printed performance curves.
g. Compliance with specified referenced standards.
h. Testing by the recognized testing agency.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale.
01 00 00 - 13
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
g. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
C. Construction Materials: The Contractor is required to submit for approval a list of products and material. The National Park Service will review and approve these materials.
1.2 INFORMATIONAL SUBMITTALS
A. Contractor’s Construction Schedule: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during the execution of the work by the Contractor.
The Construction Schedule will assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment. It shall include the dates in the contract, phases, milestones, holidays, weather consideration, a critical path, and any other requirements of this contract.
B. Accident Prevention Plan: After the contract award and after the Pre-Construction conference, submit for review an Accident Prevention Plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of the onsite representative (Site Safety Supervisor) responsible for carrying out the program. The designated Site Safety Supervisor shall be responsible for:
a. Implementation and enforcement of the Accident Prevention Plan
b. Daily safety inspections
c. Conducting and documenting weekly and monthly safety meetings
d. Review of safety requirements at progress meetings
e. Compilation and maintenance of safety reference materials
f. Tracking and resolution of safety violations
g. Site personnel and visitor compliance with site safety and health requirements and the
Accident Prevention Plan
h. Investigation and reporting of accidents and injuries
2. Weekly and monthly safety meetings, documented with topics and attendees.
3. First aid and rescue procedures.
4. Traffic control plan.
5. Training, both initial and continuing.
6. Planning for possible emergency situations such as fires, floods, cave-ins, slides, explosions, power outages, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and the degree of exposure of persons and property.
C. Schedule of Values: Break down each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the
01 00 00 - 14 contract price for that lump-sum item. The Contracting Officer may request data to verify the accuracy of dollar values. Include general condition costs, overhead, and profit in the total dollar value of unit price items and the component work activities for each lump-sum item. The total cost of all items shall equal the contract price. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed
D. Quality Control Plan: The Quality Control Plan shall include:
1. A list of personnel responsible for quality control and assigned duties. Include each person's qualifications. Include alternate(s) and qualifications, where appropriate.
2. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties and authorities designated by principal or owner.
3. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
4. Methods of performing, documenting, and enforcing quality control of all work, including Contractor report forms and acknowledgment of NPS forms.
5. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
6. Provisions for substantial completion(s) and final inspection(s) per Contract.
7. Quality Control Daily Reports and Daily Test Report Information Sheets (attached) of quality control activities and tests, which shall be maintained each day onsite work activities occur and submitted to the Contracting Officer no less than weekly.
E. Material Test Reports: Prepare reports written by a qualified testing agency, on the testing agency’s standard form, indicating and interpreting test results of material for compliance with the requirements in the Contract Documents.
F. Product Test Reports: Prepare written reports indicating the current product produced by the manufacturer complies with the requirements in the Contract Documents. Base reports on the evaluation of tests performed by the manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
G. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of field tests performed either during the installation of the product or after the product is installed in its final location, for compliance with the requirements in the Contract Documents.
H. Manufacturer’s Instructions: Prepare written or published information that documents the manufacturer’s recommendations, guidelines, and procedures for installing or operating a product or equipment. Include the name of the product and the name, address, and telephone number of the manufacturer.
PART 3 - EXECUTION (Not Used)
DIVISION 27
COMMUNICATIONS
27 05 00 - 5 COMMON WORK RESULTS FOR COMMUNICATIONS MORA – Tahoma Woods Fiber Optic Cable Install
SECTION 27 05 00
COMMON WORK RESULTS FOR COMMUNICATIONS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This section specifies the basic requirements for communications installations as indicated or required and includes requirements common to more than one specification section of this division (such as related documents, related sections, definitions, governing requirements, contractor requirements, warranty requirements, submittal requirements/procedures, and project closeout requirements/procedures, as well as other requirements).
1.3 REFERENCES
A. Work shall be designed and installed per the following:
1. National Electrical Code (NEC)
2. National Electrical Safety Code (NESC)
3. OSHA Standards and Regulations
4. ANSI/TIA-758 Customer-Owned Outside Plant Telecommunications Infrastructure
Standard
5. UL444 – Standard for Safety of Communications Cable
B. Anywhere cabling standards conflict with one another or with electrical or safety codes, Contractor shall defer to the NEC and any applicable local codes or ordinances, or default to the most stringent requirements listed by either.
C. Any violations of applicable standards or codes committed by the Contractor shall be remedied at the Contractor’s expense.
1.4 SUBMITTALS
A. Product data
B. Wiring diagrams
C. Catalog cut sheets and data sheets containing physical and dimensional information, performance data, electrical characteristics, materials used in fabrication, and material finish.
27 05 00 - 6
Clearly indicate on each sheet what is being submitted on.
D. Provide applicable portions of the following information within seven (7) days after receiving each reel and/or box of cable:
1. Manufacturer’s product test data for fiber optic cable components.
2. On–reel OTDR testing of all fiber.
1.5 RESPONSIBILITIES AND COORDINATION
A. Contractor shall provide all materials, qualified labor and services required to ensure a complete and operational system, installed in accordance with the intent of the Contract Documents.
B. Contractor shall furnish and install all incidental items not actually shown or specified, but which are required by best practices to provide complete functional systems.
1.6 LABELING
A. Comply with TIA/EIA–606–A, TIA/EIA–606–A, Addendum 1 and UL 969 for a system of labeling materials, including label stocks, laminating adhesives, and inks used by label printers.
B. Store plastic pipes protected from direct sunlight. Support to prevent sagging and bending.
PART 2 – PRODUCTS (Not Used)
PART 3 – EXECUTION
3.1 WORKMANSHIP
A. Manufactured products, materials, equipment, and components shall be provided, conditioned, applied, installed, connected, and tested in accordance with the manufacturer’s specifications and printed instructions.
B. The installation of all system components shall be carried out under the direction of qualified personnel. Appearance shall be considered as important as mechanical and electrical efficiency. Workmanship shall meet or exceed industry standards.
3.2 INTENT OF DRAWINGS
A. The drawings show only general locations of equipment, devices, raceways, cable trays, boxes, etc., unless specifically dimensioned.
B. Follow as closely as practicable the schematic design shown on the drawings. Make all
27 05 00 - 7 necessary measurements in the field to verify exact locations and ensure precise location and fit of specified items in accordance with the drawings. Make no substantial alterations without prior approval of the Contracting Officer.
C. Contractor shall be responsible for the proper placement and routing of equipment, cable, raceways, and related components, according to the Contract Documents and subject to prior review by the Contracting Officer.
D. Contractor shall refer any conflicts with the Contract Documents to the Contracting Officer for resolution.
3.3 CABLE TERMINATION AND TEST PLANS
A. General
1. Provide proof of testing technician(s) certification for operation of the specific units of test equipment, which are proposed for use.
2. Inspection Requirements:
a. As part of any performance test, inspect cable, material, and equipment for physical damage, continuity, and proper connection.
b. Verify identification and labeling at required locations for visibility, condition, legibility, and accuracy.
3. Test Report Requirements – Each test report shall include the following sections:
a. Scope of testing
b. List of equipment used in the test
c. List of technicians performing the test
d. Summary of test results
e. Individual test data sheets
4. Fiber Optic Cable Tests: Testing shall be performed using a level IIIe tester, with approved test–heads
3.4 FINAL TEST AND ADJUST
A. Contractor shall be responsible for post–installation performance testing of all cabling systems specified elsewhere in the Contract Documents.
1. Testing procedures shall permit recording the length of each link, theoretical loss budget, and tested parameters for each pair and fiber.
2. Any cable links or fiber strands, which fail to meet performance test criteria, shall be re–terminated, re–connectorized, or replaced by the contractor free of charge.
3. Submit final field test documentation to Contracting Officer.
3.5 DEFINITION OF ACCEPTANCE
27 05 00 - 8
A. System acceptance shall be defined as that point in time when the following requirements
1. All submittals and documentation have been submitted, reviewed, and approved.
2. The complete system has successfully completed all testing requirements.
B. All punch list items have been corrected and accepted.
27 05 43 - 9
UNDERGROUND DUCTS AND RACEWAYS FOR
COMMUNICATIONS SYSTEMS MORA – Tahoma Woods Fiber Optic Cable Install
SECTION 27 05 43
UNDERGROUND DUCTS AND RACEWAYS FOR COMMUNICATIONS SYSTEMS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to the work of this Section.
1.2 SUMMARY
A. Provide all materials and labor for the installation of a pathway system for outside plant communications circuits. Work in this section includes excavation and trenching, conduit (raceway) construction, cutting and patching, concrete, plant-mixed hot mix asphalt paving, maintenance hole and handhole construction, and landscape restoration.
1.3 REFERENCES
A. Incorporate by reference the applicable portions of the following specifications, standards, codes into this specification section:
1. General:
a. National Electrical Code (NEC)
b. National Electrical Safety Code (NESC)
c. Occupational Safety and Health Act (OSHA)
2. Communications:
a. ANSI/TIA/EIA - 758 : Customer-owned Outside Plant Telecommunications Cabling Standard
b. ANSI/TIA/EIA - 568: Commercial Building Telecommunications Cabling Standard
c. ANSI/TIA/EIA - 569: Commercial Building Standard for Telecommunication Pathways and Spaces
d. ANSI/TIA/EIA - 606: The Administration Standard for the Telecommunications Infrastructure of Commercial Buildings
e. ANSI/TIA/EIA - 607: Commercial Building Grounding and Bonding Requirements for Telecommunications
f. ISO/IEC IS 11801: Generic Cabling for Customer Premises
g. BICSI: BICSI Telecommunications Cabling Installation Manual (CIM)
h. BICSI: BICSI Telecommunications Distribution Methods Manual (TDMM)
i. BICSI: BICSI Customer-Owned Outside Plant Design Manual (CO-OSP)
3. Concrete:
a. Reinforcement:
i. ACI 301: Structural Concrete for Buildings
27 05 43 - 10
ii. ACI SP-66: American Concrete Institute - Detailing Manual
iii. ANSI/ASTM A82: Cold Drawn Steel Wire for Concrete Reinforcement
iv. ANSI/AWS D1.4: Structural Welding Code for Reinforcing Steel
v. ANSI/AWS D12.1: Reinforcing Steel Welding Code
vi. ASTM A615: Deformed and Plain Billet Steel Bars for Concrete Reinforcement
vii. AWS D12: Welding Reinforcement Steel, Metal Inserts and Connections in Reinforced Concrete Construction
b. Cast-in-Place:
i. ACI 212.3R: Chemical Admixtures for Concrete
ii. ACI 301: Structural Concrete for Buildings
iii. ACI 304: Recommended Practice for Measuring, Mixing, Transporting and
Placing Concrete
iv. ACI 305R: Hot Weather Concreting
v. ACI 306R: Cold Weather Concreting
vi. ASTM C33: Concrete Aggregates
vii. ASTM C39: Standard Test Method for Compressive Strength of Cylindrical
Concrete Specimens
viii. ASTM C94: Ready-Mixed Concrete
ix. ASTM C150: Portland Cement
x. ASTM C143: Standard Test Method for Slump of Hydraulic Cement
Concrete
xi. ASTM C173: Standard Test Method for Air Content of Freshly Mixed
Concrete by the Volumetric Method
xii. ASTM C231: Standard Test Method for Air Content of Freshly Mixed
Concrete by the Pressure Method
xiii. ASTM C260: Air Entraining Admixtures for Concrete
xiv. ASTM C309: Standard Specifications for Liquid Membrane Forming
Compound for Curing Concrete
xv. ASTM C494: Chemical Admixtures for Concrete
c. Pre-Cast:
i. ASTM C478: Standard Specification for Precast Reinforced Concrete Manholes Sections
ii. ASTM C857: Standard Practice for Minimum Structural Design Loading for Underground Precast Utility Structures
iii. ASTM C858: Standard Specification for Underground Precast Concrete Utility Structures
iv. ASTM C891: Standard Practice for Installation of Underground Precast Concrete Utility Structures
v. ASTM C1037: Standard Practice for Inspection of Underground Precast Concrete Utility Structures
vi. ASTM D1751: Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)
4. Trenching and Backfill:
a. ASTM D1557: Test Method for Laboratory Compaction Characteristics Using
Modified Effort
5. Asphalt Paving:
27 05 43 - 11
a. Washington State Department of Transportation (WSDOT)/American Public Works Association (APWA) Standard Specifications for Road Bridge and Municipal Construction (most recent Edition)
1.4 DEFINITIONS
A. Aggregate: Mineral materials such as sand or stone used in making concrete.
B. Backfill: Earth material used specifically for filling and grading excavations back to a finished state. Backfill is placed on top of the bedding surrounding encased ductbanks and direct-buried conduits.
C. Base: Earth material used specifically to level and grade an excavation’s subgrade for the subsequent placement of encased ductbanks, direct-buried conduit, maintenance holes and handholes. Base material is placed on top of the subgrade and beneath the bedding surrounding encased ductbanks, conduits, maintenance holes or handholes.
D. Bedding: Earth material used specifically for filling excavations. Bedding is placed around encased ductbank, conduits, maintenance holes or handholes. Bedding is placed on top of the base and beneath the backfill.
E. Fill: The collective term for base, bedding, and backfill.
F. Handhole (HH): A structure similar to a small maintenance hole through which cable can be pulled, but not large enough for a person to fully enter to perform work.
G. Maintenance Hole or Manhole (MH): A vault located in the ground or earth as part of an underground conduit system and used to facilitate placing, connectorization, and maintenance of cables as well as the placing of associated equipment, in which it is expected that a person will enter to perform work.
H. RNC: Rigid Non-Metallic Conduit (PVC).
1.5 SUBMITTALS
A. Product Data: For each type of product indicated below. Provide submittal information for review before materials are delivered to the job site. Provide product data submittals for all products at the same time.
1. For those items noted as allowing “or equal,” and which are not being provided as specifically named, submit standard manufacturer's cut sheets or other descriptive information, along with a written description detailing the reason for the substitution.
2. Provide standard manufacturer’s cut sheets and the operating and maintenance (O&M) instructions at the time of submittal review for each device in the system, regardless of whether it is submitted as specified or as an approved equal. These instructions shall detail how to install and service the equipment and shall include information necessary for rough-in and preparation of the building facilities to receive the materials.
B. Quality Assurance/Control:
27 05 43 - 12
1. Submit a copy of the delivery receipt for each concrete delivery. Include date, strength ordered, and location used.
C. Closeout Submittals: Provide submittal information for review as follows:
1. O&M Manual for Communications - At the completion of the project, submit O&M information from product data submittals (above), updated to reflect any changes during the course of construction, to the Designer in the telecommunications-specific O&M Manual for Communications binder labeled with the project name and description.
2. Records - Maintain at the job site a minimum of one set of Record Drawings, Specification, and Addenda. Record Drawings shall consist of redline markups of drawings, specifications and spreadsheets, including maintenance hole/handhole butterfly drawings.
PART 2 - PRODUCTS
2.1 GENERAL
A. Materials shall consist of fill, topsoil, concrete formwork, concrete, plant-mixed hot mix asphalt, raceway, maintenance holes, handholes and other incidentals and accessories as required.
2.2 BASE, BEDDING AND BACKFILL
A. Base: Readily compactable and meeting the following gradation requirements:
1. For Maintenance Holes and Handholes (provide gravel):
Sieve Size PercentPassing 1” Square 100 ¼” Square 25 - 80
U.S. No. 200 15 max Sand Equivalent 30 min
2. For Trenches (provide sand):
Sieve Size Percent Passing
U.S. No. 10 35 - 100 U.S. No. 20 20 - 80 U.S. No. 40 10 - 55 U.S. No. 100 0 - 10 U.S. No. 200 0 - 3
B. Bedding: Same as Base – For Trenches, above.
C. Backfill:
1. For Maintenance Holes and Handholes – Same as Base (gravel).
2. For Trenches – re-use onsite soils, if acceptable.
27 05 43 - 13
2.3 CAST-IN-PLACE CONCRETE
A. Formwork:
1. Forms: Metal or plywood in cood condition
a. Form Release Agent: Burke Form Coating (or equal)
B. Reinforcement:
1. Reinforcing Steel: ASTM A615, Grade 40. Uncoated, free from rust, dirt, and loose scale.
2. Tie Wire: 18 gauge 40 or heavier black annealed wire.
3. Embedded Anchor Bolts: Mild galvanized steel, cold bent.
C. Concrete
1. Cement: Different types of cement, including the same type of cement provided by more than one manufacturer, are not acceptable. Cement shall conform to:
a. ASTM C150-7, type 1.
b. 2500 psi minimum compressive at 28 days per ASTM C39.
c. 4 inches macimum slump per ASTM C-143.
2. Aggregate:
a. Course: ASTM C33-71 with maximum size of 1 ¼”.
b. Fine: ASTM C33-71.
3. Water: Fresh, clean, potable and not detrimental to concrete.
4. Admixtures:
a. Air Entrainment: Conform to ASTM C260 and ASTM C173 or C231 with 5% to 7% air entrainment.
b. Other: Not allowed without prior approval from the Designer.
5. Curing Compound: Conform to ASTM C319. Free from petroleum resins or waxes.
Formulated for sealing, surface hardening, and curing concrete.
2.4 CONDUIT
A. All conduit installed in-ground between maintenance holes or handholes shall be 4-inch inside diameter Schedule 40 rigid PVC or approved equal, conforming to NEMA standards TC-2 and UL651. All conduit installed above-ground shall be Schedule 40 rigid PVC sized per the drawings.
1. Rigid Non-Metallic Conduit (RNC):
a. UL listed, NEMA TC2 Schedule 40 rigid polyvinyl chloride (PVC) approval for burial.
2. Fittings:
b. Sweeps: The minimum radius for all conduit between pulling points shall be ten times its diameter. PVC elbows shall have a minimum radius of 36”.
c. End Caps (Plugs): Pre-manufactured and water-tight. Tape is not an acceptable end cap or cover.
3. Pull Ropes: ¼ inch polypropylene with a…
This is the start of the file's text. The full file is on GovTribe.