Attachment 8 JOC SOW B5230 Demolition.pdf

PDF 119 KB Posted

Attached to
W911S6-24-R-0002-Dugway Proving Ground-Job Order Contract-Minor Construction
Solicitation number
W911S6-24-R-0002
Issued by

About this file

This document is a Statement of Work (SOW) for the removal of a concrete eyebrow structure at Building 5230 in the English Village area of Dugway Proving Ground. The work includes saw cutting the existing concrete eyebrow, backfilling the holes, treating the exposed surfaces, and painting the repaired area to match the adjacent surfaces. The SOW outlines the references, submittals, occupancy considerations, existing work requirements, and on-site permit procedures. It also addresses the handling of salvage materials and equipment, as well as requirements for protecting personnel from toxic materials during the work. This SOW is associated with a Firm Fixed Price Indefinite Delivery-Indefinite Quantity Job Order Contract (JOC) solicitation for a broad range of real property repair and construction work at Dugway Proving Ground, issued by the Department of the Army Mission and Installation Contracting Command Fort Hood.

View the file

Other files

File Type Posted
Conformed Copy Solicitation W911S6-24-R-0002.pdf PDF
Amedment Solicitation W911S6-24-R-0002-00006 dpg 080624.pdf PDF
Amedment Solicitation W911S6-24-R-0002-00005 dpg 073024.pdf PDF
Amedment Solicitation W911S6-24-R-0002-00004 dpg 072524.pdf PDF
Attachment 6 Coefficient Non-PrePriced Items - JOC 24R0002 DPG 072424-RV1.xlsx XLSX spreadsheet
Attachment C Floor Plan 5124 020.pdf PDF
Amedment Solicitation W911S6-24-R-0002-00003 dpg 072224.pdf PDF
Sign In Rooster-Industry Day dpg 071024.pdf PDF
Attachment 3 Past Performance Questionnaire JOC 24 R 0002 dpg 070824 RV1.docx DOCX document
Amedment Solicitation W911S6-24-R-0002-00002 dpg 070124.pdf PDF
Technical Exhibit A Division 1 Specification dpg 112823.pdf PDF
Attachment 7a JOC SOW Bldg 5124 Community Center.docx DOCX document
Attachment 5 Coefficient Other Than Normal JOC 24R0002 DPG 010324.xlsx XLSX spreadsheet
Attachment 6 Coefficient Non-PrePriced Items JOC 24R0002 DPG 010324.xlsx XLSX spreadsheet
Technical Exhibit D Davis-Bacon Act-UT20230097 JOC 24-R-0002 DPG 041224.pdf PDF
Attachment 4 Coefficient Normal-JOC 24R0002 DPG 010324.xlsx XLSX spreadsheet
DPG JOC Solicitation W911S6-24-R-0002 dpg 062424.pdf PDF
Attachment 3 Past Performance Questionnaire-JOC 24-R-0002-dpg 120523.docx DOCX document
Attachment 7 Notional One and two Task Order Req JOC 24R0002 DPG.docx DOCX document
Technical Exhibit B Areas of DPG with historical workload-JOC W911S6-24-R-0002 dpg 102423.pdf PDF
Technical Exhibit C Davis-Bacon Act-UT20230086 JOC 24-R-0002 DPG 053124.pdf PDF
Attachment 8a Exterior Details 5230-005.pdf PDF
Technical Exhibit E Davis-Bacon Act-UT20230112 JOC 24-R-0002 DPG 010524.pdf PDF
Attachment 8c 5230 011 Roof Framing Plan.pdf PDF
Amedment Solicitation W911S6-24-R-0002-00001 dpg 062424.pdf PDF
Attachment 8b 5230 010 Second Floor Framing B5230.pdf PDF
DPG JOC Scope of Work-W911S6-24-R-002 (1).pdf PDF
Attachment 7b Technical Drawings Bldg 5124 Community Center.pdf PDF
Attachment 1 Consent Letter - JOC-24-R-0002 dpg 120523.docx DOCX document
Attachment 2 Specific Relevant Contracts - JOC 24R0002 dpg 120523.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Concrete Eyebrow Demolition

Bldg. 5230

26 Feb 2024

1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.2.1 Project Description

1.2.2 Location

1.3 OCCUPANCY OF PREMISES

1.4 EXISTING WORK

1.5 ON-SITE PERMITS

1.5.1 Utility Outage Requests

1.5.2 Hot Work Permit

1.5.3 Excavation Permit

1.6 SALVAGE MATERIAL AND EQUIPMENT

C.2 PRODUCTS

C.3 EXECUTION

Statement of Work (SOW)

1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this SOW to the extent referenced. The publications are referred to within the text by the basic designation only.

American Conference of Governmental Industrial Hygieneists (ACGIH)

ACGIH 0100 Documentation of the Threshold Limit Values and Biological Exposure Indices

Society for Protective Coatings (SSPC)

SSPC Guide 6 Guide for Containing Surface Preparation Debris Generated During Paint Removal Operations

SSPC Guide 7 Guide to the Disposal Lead-Contaminated Surface Preparation Debris

US National Archives and Records Administration (NARA)

29 CFR 1910.1000 Air Contaminants

29 CFR 1910.1025 Lead

29 CFR 1926.62 Lead

1.2 SUBMITTALS

Submit the following in accordance with Section 01 33 00, SUBMITTAL PROCEDURES, of the base contract:

SD-03 Product Data

SD-04 Samples

SD-11 Closeout Submittals

1.2.1 Project Description

The work includes removal of the existing concrete eyebrow and incidental related work.

1.2.2 Location

The work is located at Bldg. 5230 in English Village at Dugway Proving Ground. The exact location will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

Building(s) will [not] be occupied during performance of work under this Contract.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 ON-SITE PERMITS

1.5.1 Utility Outage Requests

Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.

Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 21 calendar days in advance of the time required for work taking place in English Village and at least 30 calendar days in advance for work in all other areas. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.

1.5.2 Hot Work Permit

Obtain a hot work permit from the Dugway Fire Department before commencing any activities that may or could start a fire. Activities that require a hot work permit include, but are not limited to: open flames, welding, grinding, cutting, and activities that may create sparks.

Burning of trash or rubbish is not permitted.

1.5.3 Excavation Permit

Obtain digging permits prior to start of excavation and comply with Installation requirements for locating and maintaining underground utilities markings. Verify existing utility locations indicated on contract drawings within area of work by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. Use mechanical equipment when digging within 24 inches of a known utility is not permitted. If excavation is parallel within 60 inches to an existing utility, expose the utility by hand digging every 100 feet.

Allow a minimum of 30 days for processing excavation permit requests.

Notify the Contracting Officer at least 48 hours prior to starting excavation work.

1.6 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the storage area.

Maintain property control records for material or equipment designated as salvage. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

2 PRODUCTS

2.1 Toxic Materials

3.4.1 To protect personnel from overexposure to toxic materials, conform to the most stringent guidance of:

a. The applicable manufacturer's Safety Data Sheets (SDS) or local regulation.

b. 29 CFR 1910.1000.

c. ACGIH 0100, threshold limit values.

d. The appropriate OSHA standard in 29 CFR 1910.1025 and 29 CFR 1926.62 for surface preparation on painted surfaces containing lead. Additional guidance is given in SSPC Guide 6 and SSPC Guide 7.

3 EXECUTION

3.1 Saw cut all existing concrete eyebrows and haul to the Dugway landfill.

3.1.1 Provide physical boundaries around the work area by roping off the area or providing curtains, portable partitions, or other enclosures. Prohibit the general public from accessing the work areas.

3.2 Back gouge rebar to a minimum depth of 1.5 inches below the remaining concrete surface.

Fill holes with epoxy grout.

3.3 Treat exposed surfaces as needed by grinding or other methods to provide an even and uniform surface.

3.4 Paint exposed concrete to match adjacent finished surfaces. Provide primer and 2 coats of a low VOC exterior latex paint.

3.4.1 Do not apply coating when air or substrate conditions are:

a. Less than 3 degrees C 5 degrees F above dewpoint;

b. Below 50 degrees F or over 95 degrees F, unless specifically pre-approved by the Contracting Officer and the product manufacturer. Do not, under any circumstances, violate the manufacturer's application recommendations.

3.4 Cleanup

Maintain surfaces of the work area free of accumulations of dust and debris. Restrict the spread of dust and debris; keep waste from being distributed over the work area. Do not dry sweep or use pressurized air to clean up the area. At the end of each shift clean the controlled area of all visible contamination by vacuuming with a HEPA filtered vacuum cleaner, wet mopping the area and wet wiping the area. Reclean areas showing dust or debris. After visible dust and debris is removed, wet wipe and HEPA vacuum all surfaces in the controlled area.

File details come from the government source that posted it. Updated .