Attachment 8.2 - SOW_XDAT 26-1029 PAVEMENT REHABILITATION AND RECONSTRUCTION FOR BUILDING 31.pdf
PDF 185 KB Posted
- Attached to
- Pavement Rehabilitation B836 and B31
- Solicitation number
- FA442726Q1150
About this file
This is a Statement of Work for pavement rehabilitation and reconstruction at Building 31, Travis Air Force Base (AFB), California, with Base Project Number XDAT 26-1029, dated August 19, 2026. The project addresses pavement deficiencies identified through Pavement Condition Index (PCI) assessments, with Section 2 rated at PCI 35 requiring a 2-inch mill-and-overlay covering approximately 32,000 square feet, and Section 6 rated at PCI 5 requiring a minimum 4-inch full-depth reconstruction totaling about 5,060 square feet. The work encompasses all professional services, permits, equipment, labor, tools, materials, and ancillary items necessary to complete the pavement repairs, including demolition and removal of existing pavement, subgrade preparation, base aggregate placement and compaction, asphalt pavement placement and compaction, striping, and traffic control. The contractor must comply with Unified Facilities Criteria (UFC), Uniform Building Code (UBC), International Building Code (IBC), Air Force Standards, Department of Defense directives, California State Statutes, Travis AFB Facility Excellence Plan, OSHA requirements, Manual on Uniform Traffic Control Devices (MUTCD), and ADA Accessibility Compliance Requirements.
The contractor is responsible for acquiring all required state, local, and applicable permits, including base dig permits and USA Dig permits, with dig permit requests to be submitted a minimum of 30 calendar days in advance of planned excavation activities. Specific work requirements include removing and disposing of existing asphalt pavement, preparing the subgrade with proof-rolling to identify unsuitable areas, placing 6 inches of aggregate class II base course compacted to 95 percent maximum dry density for the full-depth area, performing a 2-inch mill and overlay with 2 inches of HMA Type A PG 64-22 asphalt for the mill-and-overlay area, and placing 4 inches of HMA Type A PG 64-22 asphalt for the full-depth reconstruction area with joint sealing using hot-applied sealant meeting ASTM D6690. The contractor must provide a detailed construction schedule capable of mobilizing within 14 days of award, conduct a pre-final inspection five days prior to final inspection, establish an effective quality control system compliant with FAR Clause 52.246-12, and submit required documentation including AF Forms 3064, 3065, and 3000, along with third-party material testing reports verifying soil and concrete material requirements.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
PAVEMENT REHABILITATION AND RECONSTRUCTION FOR BUILDING 31
TRAVIS AFB CALIFORNIA
Base Project Number: XDAT 26-1029
DATE: 19 Aug 2026
1. INTRODUCTION
1.1. Project Origin and Authorization
This Statement of Work (SOW) defines the requirements for the pavement rehabilitation and reconstruction of the parking lot at Building 31, Travis Air Force Base (AFB), California. The latest Pavement Condition Index (PCI) assessment identified two pavement sections in poor condition, with PCI values of 35 and 5, indicating the need for pavement rehabilitation and reconstruction. The project is required to correct identified pavement deficiencies, restore the pavement to an acceptable operational condition, and prevent continued deterioration.
1.2. Project Site and Existing Conditions
The project site is located at Building 31, a TWCF facility at Travis AFB, California. The purpose of this project is to address pavement deficiencies at Building 31 by performing both mill-and-overlay and full-depth reconstruction in the designated parking lot sections. Based on the latest PCI assessment, Section 2 has a PCI of 35 and requires a 2-inch mill and overlay covering approximately 32,000 square feet, while Section 6 has a PCI of 5 and requires a minimum 4-inch full-depth reconstruction totaling about 5,060 square feet. These repairs are necessary to restore a structurally sound and durable parking surface, improve safety, and extend the service life of the facility.
1.3. Execution Summary
The Contractor shall be responsible for all professional services, permits, equipment, labor, tools, materials, and ancillary items necessary to perform full-depth asphalt pavement repair in the designated parking spot areas. This includes but is not limited to demolition and removal of existing pavement, subgrade preparation, base aggregate placement and compaction, asphalt pavement placement and compaction, striping, and traffic control.
2. SCOPE OF WORK
2.1. Compliance with Standards
The Contractor shall adhere to specifications, applicable Unified Facilities Criteria (UFC), Uniform Building Code (UBC), those sections of the Southern Standard Building Codes not incorporated in the UBC/International Building Code (IBC) for, Air Force Standards, Department of Defense (DOD) Directives, California State Statutes, and the Travis AFB Facility Excellence Plan (Base Regulations), Occupational Safety and Health Administration (OSHA) Requirements, the Manual on Uniform Traffic Control Devices (MUTCD) and ADA Accessibility Compliance Requirements. If there is a conflict between these codes, regulations and specifications the most stringent requirements shall always apply. Documents listed by and/or provided by the Government are for reference only and do not relieve the Contractor from adherence with applicable codes not specifically addressed.
2.2. Permit Requirements
The Contractor shall develop, coordinate, and be responsible for labor, professional services and other costs associated with acquiring all required state, local, and other applicable permits; base access (including off-base easements and leases), agreements, licenses, and certificates required to perform and complete the project. The Contractor shall maintain a library of these documents on site as well as at the corporate facility handling each project. The Contractor shall comply with applicable permit conditions, environmental protection policies and appended guidelines. This specifically includes:
2.2.1. Base Dig Permit / USA Dig Permit:
a. The contractor shall obtain all required dig permits, verify the location of all underground utilities prior to excavation activities and shall comply with UFGS 01 56 00 – Temporary Environmental Control and UFGS 31 23 00 – Excavation and Fill.
b. Obtain a blank 60 AMW FM 66 (often called a digging permit) from 60 CES Customer Service, (707) 424-7525. Contractors shall request a digging permit at least ten (10) working days in advance. In-place utility locations shall be verified by the Contractor with on-site pit verification as needed prior to the start of construction activities.
c. The contractor shall obtain all required excavation/dig permits prior to performing any excavation, saw cutting, or subsurface work. This requirement applies to all excavation, saw cutting, milling, and any work that disturbs the ground surface. The contractor shall submit dig permit requests a minimum of 30 calendar days in advance of planned excavation activities so the Government can review, coordinate, and identify any potential conflicts. No excavation or surface work shall begin until dig permits are approved and all required coordination requirements are satisfied.
d. Mapping of underground utilities is not provided. The contractor shall be responsible for locating, verifying, and protecting all existing underground utility locations and avoiding conflicts.
2.3. Description of Work
Contractor shall perform pavement rehabilitation at Building 31, work includes the following:
2.3.1. Asphalt Pavement Removal and Disposal
a. Remove existing asphalt pavement in the designated areas at Building 31. The contractor is responsible for determining and verifying the exact boundaries of each parking area requiring repair.
b. Dispose of all asphalt removed and associated debris in accordance with local, state, and federal regulations.
Applicable Codes & Standards:
UFGS 02 41 00 - Demolition and Deconstruction
2.3.2. Subgrade Preparation (Full-depth Area Only)
a. Inspect the exposed subgrade for stability and suitability prior to placement of aggregate base.
b. Proof-roll the exposed subgrade to identify soft, unstable, or unsuitable areas.
c. Remove unsuitable material encountered and replace with suitable compacted fill as required.
d. Grade and compact the subgrade to the required elevation and slope. Maintain positive drainage and prevent ponding adjacent to existing structures.
Applicable Codes & Standards:
UFC 3-250-01 – Pavement Design for Roads and Parking Areas UFGS 31 00 00 – Earthwork
2.3.3. Base Aggregate Placement and Compaction (Full-depth Area Only)
a. Place 6” of new aggregate class II base course material over the prepared subgrade.
b. Compact each lift to a minimum of 95% of maximum dry density as determined by
AASHTO T 99, AASHTO 180.
Applicable Codes & Standards:
UFGS 32 11 23 – Aggregate Base Course and/or Graded Crushed Aggregate Base
Course for Flexible Paving
2.3.4. Mill and Overlay Area
a. Perform a 2” mill of the existing asphalt pavement surface.
b. Clean and prepare the milled surface prior to placement of new asphalt pavement.
c. Apply tack coat to the prepared surface in accordance with the applicable specification.
d. Place 2” of HMA Type A, PG 64-22, and compact to the specified density.
e. Match adjacent existing pavement elevations and maintain a positive drainage.
2.3.5. Full-depth Reconstruction Area
a. Apply tack coat to the prepared base aggregate.
b. Place 4” of HMA Type A, PG 64-22 over the prepared aggregate base.
c. Place and compact asphalt pavement to the required elevation, grade, and density.
d. Construct pavement joints to provide a smooth transition to existing pavement and minimize water infiltration.
e. Seal applicable pavement joints with hot-applied sealant meeting ASTM D6690.
Applicable Codes & Standards:
UFGS 32 12 16.16 – Road-Mix Asphalt Paving UFGS 32 12 13 – Bituminous Tack and Prime Coats
2.3.6. Striping and Pavement Markings
a. Restore parking stall striping and other pavement markings disturbed by the work in accordance with the approved striping layout provided by the contractor. Provide accessible parking spaces, access aisles, and associated markings in accordance with ABA requirements.
Applicable Codes & Standards:
UFGS 32 17 23.16 – Road and Parking Lot Pavement Markings Architectural Barriers Act (ABA) Accessibility Standards Manual on Uniform Traffic Control Devices (MUTCD)
2.3.7. Utility Adjustments and Drainage
a. All Government-owned utility covers, including manholes, sewer lines, communication lines, and drainage inlets, shall be adjusted as necessary to match the final pavement grade. The contractor shall coordinate these adjustments and ensure the affected utilities remain functional. Utilities not owned by the Government shall not be adjusted, raised, lowered, or otherwise modified by the Contractor. Water lines are owned by Cal Water, and electrical lines are owned by City Light and Power (CLP). If adjustment of non- Government owned utilities is required, the contractor shall notify the Government, and coordination shall be made with the designated utility owner.
b. The contractor shall not adjust, raise, lower, or modify utilities not owned by the Government, including water lines and electrical lines. If conflicts with non- Government owned utilities are encountered, the contractor shall notify the Government immediately for coordination and further direction. Communication and Sewer lines are Government owned.
c. The contractor shall construct the pavement to maintain positive drainage and match existing grades at all tie-in locations. Existing gutters shall be used to maintain drainage flow and shall be adjusted as necessary to match final pavement grades. Any ponding or improper drainage shall be corrected. Grading plan shall be submitted as a pre-construction design drawing.
2.4. Haul Routes and Base Access
2.4.1. The contractor shall be responsible for hauling and disposal of all removed materials off base in accordance with UFGS 31 00 00 Earthwork. The contractor shall provide Construction & Debris report within 30 days of disposal for 60 CES/CEI tracking of recycled materials.
2.4.2. The contractor will provide a haul route to the Government prior to construction for review and approval.
2.4.3. Construction vehicles shall enter the installation through the South Gate and may exit through the Main Gate with Government approval. The Government will assist in obtaining base access passes; however, the contractor shall be responsible for submitting required documentation.
2.4.4. Work hours shall be in accordance with Division 01 – Travis AFB General Requirements Section 01 00 00, section 1.8 Working Hours
3. CONSTRUCTION
3.1. Upon approval by the CO for all preconstruction requirements, submittals, and applicable permits; the Contractor may commence on-site construction activities. The Contractor shall conform to all specifically reference and other applicable requirements during performance of the work as described in the Contract Documents:
3.1.1. Schedule:
a. The contractor shall submit a detailed construction project schedule for Government review and approval. The schedule shall identify the proposed duration required to complete the project.
3.1.2. Mobilization:
a. Mobilize equipment, labor, tools, materials, and ancillary items necessary to complete the work defined in the Contract Documents. The Contractor shall be capable of mobilizing to begin work within 14 days of award.
3.1.3. Demolition/Construction:
a. Perform awarded tasks as defined in section 2.3 Description of Work.
b. Protect work areas with barricades, warning tape, signs and/or other appropriate methods for the work being completed to ensure the safety of pedestrians and Contractor personnel.
c. If utility relocation is required, the relocation shall be coordinated with and approved by the utility owner/operator and CO in advance of relocation efforts.
d. Care should be taken to avoid damaging other installed utilities. If other utilities are damaged during performance of the contract, the Contractor shall repair the damage at no additional cost to the Government.
e. Remove and dispose of all demolition and general construction debris from the site (off base).
f. Perform ancillary efforts required to complete the work to provide clean, complete and functional facility meeting the standard of quality for each trade utilized.
g. Limit disturbance to the natural vegetation, wildlife and base activities to the greatest extent practicable.
4. GENERAL REQUIREMENTS
4.1. Pre-CON Meeting
A Pre-CON meeting shall be accomplished with the Contractor, Contracting Officer, Civil Engineering Squadron (CES), and user. The meeting objective is to review project details, determine construction start date, security procedures for site, dumpster locations, and any applicable requirements during construction. The Contractor shall visit the job site to verify location, conditions, and dimensions prior to starting work.
4.2. Facility Occupancy
The Contractor is responsible for diverting and restricting pedestrian and vehicle traffic in the active work areas for the duration of the performance period.
4.3. Identification of Employees
The Contractor shall be responsible for obtaining security clearances and badges for each employee, and for requiring each employee engaged on the work to display identification as approved and directed by the CO and Security Forces. The contractor shall submit personnel background check applications for badging within three (3) days after award. During performance of the contract, prescribed identification shall immediately be delivered to the CO for cancellation upon release of any employee. When required, the Contractor shall obtain and provide fingerprints of persons employed on the project. All Contractor and sub-contractor personnel shall wear identifying markings clearly defining the company for whom the employee works.
4.4. Hazardous Waste Management
Contractor shall notify 60 CES/CEIE if any hazardous waste is encountered or generated. The Contractor shall stop all work in the event 60 CES/CEIE identifies noncompliance with federal and state regulations and shall correct any discrepancies immediately within two (2) hours of notification by 60 CES/CEIE. All hazardous waste shall be disposed of by the contractor in accordance with Division 01 General Requirements Section 01000 and General Section 01 56 00 Environmental General Requirements.
4.5. Protection and Maintenance of Traffic
During construction, the Contractor shall provide access and temporary relocated paths as necessary to maintain traffic that may be affected by construction activities. The Contractor shall maintain and protect traffic on all affected roads/pedestrian paths during the construction period except as otherwise specifically directed by the CO. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment and the work, and the erection and maintenance of adequate warning, danger, and direction signs, shall be as required by the State and local authorities having jurisdiction. The traveling public shall be protected from damage to person and property. The Contractor's traffic on roads selected for hauling material to and from the site shall interfere as little as possible with public traffic. The Contractor shall investigate the adequacy of existing roads and the allowable load limit on these roads. The Contractor shall be responsible for the repair of any damage to roads caused by construction operations.
4.6. Barricades
The Contractor shall erect and maintain temporary barricades to prevent public access to hazardous areas as required by OSHA, Caltrans, and CAMUTCD and/or like Agencies. Such barricades shall be required whenever safe public access to paved areas such as roads, parking areas, sidewalks or other work areas are prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. The minimum required number of barricades shall be securely placed in a neat and orderly fashion, clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night. Barricades shall be maintained in an orderly fashion during the duration of their placement.
5. DELIVERABLES / SUBMITTALS
5.1. Contract Progress Schedule (AF Form 3064)
The Contractor shall submit a signed AF 3064 (or approved equivalent), Contract Progress Schedule, depicting an overall contract progress schedule for the main elements of work for the period of performance and submitted as described in the Table of Deliverables. The line items associated project percentages and dates shall accurately depict the planned work to be performed. The Contractor shall also provide a line graph depicting actual construction progress (solid line) versus scheduled construction progress (dotted line) throughout the period of performance. The progress schedule shall be signed by the either the COR or the government contract inspector recommending approval and approved by the CO. If the Contractor requires reimbursement of a high dollar value item, the item shall be identified on the AF 3065, an appropriate percentage applied, and the item must be received and stored on site.
5.2. Contract Progress Report (AF Form 3065)
The Contractor shall submit AF 3065 as described in the Table of Deliverables. This report shall be signed by the Contractor’s on-site representative in the Remarks section of the AF 3065. The work elements and percentages of the total job identified on the AF 3065 shall be identical to the work elements and percentages on the AF 3064. The Contractor shall obtain either the COR or the Government contract inspector’s acceptance by signature of the actual reported progress prior to submission to the CO. Additionally, the Contractor shall submit an updated AF 3064 as an attachment to each submission of the AF 3065.
5.3. Material Approval (AF Form 3000)
The Contractor shall prepare and submit the AF Form 3000 with all submittals to the Government.
The form shall document the contents of the submittal and be signed by the contractor.
5.4. Construction Material Testing
The Contractor shall employ a qualified third-party material testing company to verify that soil and concrete material requirements are met. Test reports will be submitted to the government when the formal reports are received. Field reports shall always be maintained on site for government reference.
5.5. Pre-Final Inspection
The Contractor shall conduct a pre-final walk-through inspection with Base personnel and publish the pre-final inspection findings in a pre-final inspection (punch list) report five (5) days prior to the Final Inspection.
5.6. Final Inspection
The Contractor shall conduct a final inspection with base personnel and publish the findings in a final inspection report for each project task upon substantial completion of work. The inspection shall concentrate on the items identified at the pre-final inspection and recorded in the pre-final inspection (punch list) report. A final inspection shall not be performed until the pre-final inspection (punch list) report has been resolved.
6. CONTRACTOR’S QUALITY CONTROL
6.1. Quality Control
The Contractor is responsible for quality control and shall establish and maintain an effective quality control system in compliance with FAR Clause 52.246-12, Inspection of Construction. The quality control system shall consist of plans, procedures, and organization necessary to manage all delivery orders to produce end products which comply with the contract requirements. The system shall cover all construction operations, both on site and off site, and shall be keyed to the proposed construction sequence. The Government will hold the project manager responsible for the quality of work on the job and is subject to removal by the CO for non-compliance with quality requirements specified in the contract. The Contractor shall verify full compliance with the contract documents prior to requesting final inspection(s).
6.2. Field Measurements
The Contractor shall be required to make his/her own field investigations to verify existing conditions, dimensions and other information shown on Government furnished reference drawings, solicitation documents and construction documents. Deviations, errors, or omissions in the government supplied reference materials or the contract documents shall be identified and addressed by the contractor prior to the start of construction.
//END of S.O.W//
7. ATTACHMENTS
7.1. Attachment 3a: Pavement Rehabilitation and Reconstruction Bldg 31 Site_Vicinity Map
7.2. Attachment 3b: Travis AFB BMP Construction Site Documents
7.3. Attachment 3c: Section 01 00 00 – Travis AFB General Requirements
7.4. Attachment 3d: Section 01 56 00 – Travis AFB Environmental General Requirements