Attachment_7_ONPVC_Sewer_Technical_Specs.pdf
PDF 42 KB Posted
- Attached to
- OLYM REPAIR ONPVC SEWER
- Solicitation number
- 140P8326Q0022
About this file
This is a technical specification section for sanitary utility sewerage piping installation outside buildings, specifically Section 33 31 00 from the Olympia project (OLYM-175023). The specification establishes requirements for gravity-flow, nonpressure sanitary sewerage systems serving the City of Port Angeles Department of Public Works & Utilities, with a required pressure rating of 10-foot head of water.
The specification requires PVC Type PSM sewer pipe (ASTM D 3034, SDR 35) with bell-and-spigot ends for pipe sizes NPS 4 to NPS 15, installed with elastomeric gaskets and gasketed joints. Piping must be pitched downward at a minimum slope of 1 percent in the direction of flow, with a minimum 36-inch cover depth unless otherwise indicated. Installation requires nonpressure-type flexible couplings for joining gravity-flow piping, with specific coupling types designated based on pipe size and material compatibility. Cleanouts must be PVC with threaded plugs, and standard precast concrete manholes must be 48 inches minimum diameter with ASTM C 478 specifications, including eccentric-cone tops, ASTM C 443 gaskets, and FRP steps at 12-inch intervals for depths exceeding 60 inches. Concrete channels and benches within manholes require a minimum 3000 psi design mix. Testing requirements include hydrostatic tests at 10-foot head of water maintained for 15 minutes with maximum allowable leakage of 50 gallons per inch of nominal pipe size per mile during a 24-hour period, air tests per ASTM F 1417, and manhole hydraulic tests per ASTM C 969. Tap connections to existing sewer mains must be coordinated with the City inspector at the contractor's expense, and all work must comply with City of Port Angeles Department of Public Works & Utilities Urban Services Standards and Guidelines Chapter 2 Wastewater.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OLYM - 175023
33 31 00 - 1
SANITARY UTILITY SEWERAGE
PIPING
SECTION 33 31 00- SANITARY UTILITY SEWERAGE PIPING
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes: gravity-flow, nonpressure sanitary sewerage outside the building, with the following components:
1. Pipe and fittings.
2. Nonpressure and pressure couplings.
3. Cleanouts.
4. Manholes.
1.2 PERFORMANCE REQUIREMENTS
A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water.
1.3 SUBMITTALS
A. Product Data: For the following:
1. Cleanouts
2. Pipe material.
B. Shop Drawings: For manholes. Include plans, elevations, sections, details, and frames and covers.
C. Field quality-control reports.
1.4 PROJECT CONDITIONS
A. Site information: Research public utility records and verify existing utility locations prior to ordering any materials. Notify the Contracting Officer immediately if any discrepancies are found in the project survey.
B. Requirements: Comply with “City of Port Angeles Department of Public Works & Utilities, Urban Services Standards and Guidelines, Chapter 2 Wastewater” as applicable.
C. Coordination: Coordinate tap to existing sewer main with City inspector. Tap to be installed by City at contractor’s expense unless otherwise approved.
PART 2 PRODUCTS
2.1 PIPING MATERIALS
A. Refer to Part 3 “Piping Applications” Article for applications of pipe, fitting, and joining materials.
33 31 00 - 2
2.2 PVC PIPE AND FITTINGS
A. PVC Type PSM Sewer Piping:
1. Pipe: ASTM D 3034, SDR 35, PVC Type PSM sewer pipe with bell-and-spigot ends for solvent-cemented or gasketed joints.
2. Fittings: ASTM D 3034, PVC with bell ends.
3. Gaskets: ASTM F 477, elastomeric seals.
2.3 NONPRESSURE-TYPE TRANSITION COUPLINGS
A. Comply with ASTM C 1173, elastomeric, sleeve-type, reducing or transition coupling, for joining underground nonpressure piping. Include ends of same sizes as piping to be joined and corrosion-resistant-metal tension band and tightening mechanism on each end.
B. Sleeve Materials:
1. For Plastic Pipes: ASTM F 477, elastomeric seal or ASTM D 5926, PVC.
2. For Dissimilar Pipes: ASTM D 5926, PVC or other material compatible with pipe materials being joined.
C. Unshielded, Flexible Couplings:
1. Description: Elastomeric sleeve with stainless-steel shear ring and corrosion-resistant-metal tension band and tightening mechanism on each end.
D. Ring-Type, Flexible Couplings: Elastomeric compression seal with dimensions to fit inside bell of larger pipe and for spigot of smaller pipe to fit inside ring.
2.4 CLEANOUTS
A. PVC Cleanouts: PVC body with PVC threaded plug. Include PVC sewer pipe fittings and riser to cleanout.
2.5 MANHOLES
A. Standard Precast Concrete Manholes:
1. Description: ASTM C 478, precast, reinforced concrete, of depth indicated, with provision for sealant joints rubber gasketed joints.
2. Diameter: 48 inches minimum unless otherwise indicated.
3. Ballast: Increase thickness of precast concrete sections or add concrete to base section, as required to prevent flotation if site conditions warrant and/or as shown in plans.
4. Base Section: 6-inch minimum thickness for floor slab and 5 inch minimum thickness for walls and base riser section; with separate base slab or base section with integral floor.
5. Riser Sections: 5-inch minimum thickness, of length to provide depth indicated.
6. Top Section: Eccentric-cone type unless concentric-cone or flat-slab-top type is indicated;
with top of cone of size that matches grade rings.
7. Gaskets: ASTM C 443, rubber or preformed plastic.
33 31 00 - 3
8. Joint Sealant: ASTM C 990, bitumen or butyl rubber.
9. Resilient Pipe Connectors: ASTM C 923, cast or fitted into manhole walls, for each pipe connection.
10. Steps: Individual FRP steps or FRP ladder; wide enough to allow worker to place both feet on one step and designed to prevent lateral slippage off step. Cast or anchor steps into sidewalls at 12-inch intervals. Omit steps if total depth from floor of manhole to finished grade is less than 60 inches.
11. Adjusting Rings: Interlocking rings, with level or sloped edge in thickness and diameter matching manhole frame and cover, and with height as required to adjust manhole frame and cover to indicated elevation and slope. Include sealant recommended by ring manufacturer.
12. Grade Rings: Reinforced-concrete rings, 6- to 9-inch total thickness, with diameter matching manhole frame and cover, and with height as required to adjust manhole frame and cover to indicated elevation and slope.
B. Manhole Frames and Covers:
1. Description: Ferrous; 23-inch ID by 3- to 7-inchriser, with 3 ¼ -inch- minimum-width flange and 24 ¾-inch- diameter cover. Include indented top design with lettering cast into cover, using wording equivalent to "SANITARY SEWER."
2. Material: ASTM A 536, Grade 60-40-18 ductile iron designed for heavy duty service unless otherwise indicated.
2.6 CONCRETE
A. General: Cast-in-place concrete complying with ACI 318, ACI 350/350R, and the following:
1. Cement: ASTM C 150, Type II.
2. Fine Aggregate: ASTM C 33, sand.
3. Coarse Aggregate: ASTM C 33, crushed gravel.
4. Water: Potable.
B. Portland Cement Design Mix: 3000 psi minimum, with 0.45 maximum water/cementitious materials ratio.
1. Reinforcing Fabric: ASTM A 185, steel, welded wire fabric, plain.
2. Reinforcing Bars: ASTM A 615, Grade 60 deformed steel.
C. Manhole Channels and Benches: Factory or field formed from concrete. Portland cement design mix, 3000 psi minimum, with 0.45 maximum water/cementitious materials ratio. Include channels and benches in manholes.
1. Channels: Concrete invert, formed to same width as connected piping, with height of vertical sides to three-fourths of pipe diameter. Form curved channels with smooth, uniform radius and slope.
a. Invert Slope: Uniform slope through manhole to match invert elevations per plans, minimum 2 percent.
33 31 00 - 4
2. Benches: Concrete, sloped to drain into channel.
a. Slope: 8 percent.
D. Ballast and Pipe Supports: Portland cement design mix, 3000 psi minimum, with 0.58 maximum water/cementitious materials ratio.
1. Reinforcing Fabric: ASTM A 185, steel, welded wire fabric, plain.
2. Reinforcing Bars: ASTM A 615, Grade 60 deformed steel.
PART 3 EXECUTION
3.1 EARTHWORK
A. Excavating, trenching, and backfilling are specified in Section 31 20 00 "Earth Moving."
3.2 PIPING APPLICATIONS
A. Pipe couplings and fittings with pressure ratings at least equal to piping rating may be used in applications below, unless otherwise indicated.
1. Use nonpressure-type flexible couplings where required to join gravity-flow, nonpressure sewer piping, unless otherwise indicated.
a. Unshielded flexible couplings for same or minor difference OD pipes.
b. Unshielded, increaser/reducer-pattern, flexible couplings for pipes with different OD.
c. Ring-type flexible couplings for piping of different sizes where annular space between smaller piping’s OD and larger piping’s ID permits installation.
B. Gravity-flow, Nonpressure Sewer Piping: Use the following pipe materials for each size range.
1. NPS 4 to NPS 15: PVC sewer pipe and fittings gaskets, and gasketed joints.
3.3 PIPING INSTALLATION
A. Install tracer wire directly over piping and at outside edges of underground structures. See Section 31 20 00 “Earth Moving” for tracer wire material requirements.
B. General Locations and Arrangements: Drawing plans and details indicate general location and arrangement of underground sanitary sewer piping. Location and arrangement of piping layout take into account design considerations. Install piping as indicated, to extent practical. Where specific installation is not indicated, follow piping manufacturer's written instructions.
C. Install piping beginning at low point, true to grades and alignment indicated with unbroken continuity of invert. Place bell ends of piping facing upstream. Install gaskets, seals, sleeves, and couplings according to manufacturer's written instructions for using lubricants, cements, and other installation requirements.
D. Install manholes for changes in direction unless fittings are indicated. Use fittings for branch connections unless direct tap into existing sewer is indicated.
E. Install proper size increasers, reducers, and couplings where different sizes or materials of pipes and fittings are connected. Reducing size of piping in direction of flow is prohibited.
33 31 00 - 5
F. Install gravity-flow, nonpressure, sewer piping according to the following:
1. Install piping pitched down in direction of flow, at minimum slope of 1 percent unless otherwise indicated.
2. Install piping with 36-inch minimum cover unless otherwise indicated.
3. Install PVC Type PSM sewer piping according to ASTM D 2321 and ASTM F 1668.
G. Clear interior of piping and manholes of dirt and superfluous material as work progresses.
Maintain swab or drag in piping, and pull past each joint as it is completed. Place plug in end of incomplete piping at end of day and when work stops.
H. Protect existing piping and structures to prevent concrete or debris from entering while making tap connections. Remove debris or other extraneous material that may accumulate.
3.4 PIPE JOINT CONSTRUCTION
A. Join gravity-flow, nonpressure, drainage piping according to the following:
1. Join PVC Type PSM sewer piping according to ASTM D 2321 and ASTM D 3034 for elastomeric-seal joints or ASTM D 3034 for elastomeric-gasket joints.
2. Join dissimilar pipe materials with nonpressure-type, flexible couplings.
3.5 MANHOLE INSTALLATION
A. General: Install manholes complete with appurtenances and accessories indicated.
B. Install precast concrete manhole sections with sealants according to ASTM C 891.
C. Form continuous concrete channels and benches between inlets and outlet.
D. Set tops of frames and covers flush with finished surface for manholes that occur in pavements.
Set tops 3 inches above finished surface elsewhere.
3.6 CONCRETE PLACEMENT
A. Place cast-in-place concrete according to ACI 318.
3.7 CLEANOUT INSTALLATION
A. Install cleanouts and riser extensions from sewer pipes to cleanouts at grade. Use pipe fittings in sewer pipes at branches for cleanouts, and use PVC pipe for riser extensions to cleanouts. Install piping so cleanouts open in direction of flow in sewer pipe.
1. Use Light-Duty, top-loading classification cleanouts in earth or unpaved foot-traffic areas.
2. Use Medium-Duty, top-loading classification cleanouts in paved foot-traffic areas.
3. Use Heavy-Duty, top-loading classification cleanouts in vehicle-traffic service areas.
B. Set cleanout frames and covers in earth in cast-in-place-concrete block, per the Detail. Set with tops 1 inch above surrounding grade.
C. Set cleanout frames and covers in concrete pavement and roads with tops flush with pavement surface.
33 31 00 - 6
3.8 CONNECTIONS
A. Connect nonpressure, gravity-flow drainage piping to building's sanitary building drain. Use transition fitting to join dissimilar piping materials.
B. Make connections to existing piping and underground manholes.
1. Use commercially manufactured wye fittings for piping branch connections. Remove section of existing pipe, install wye fitting into existing piping, and encase entire wye fitting plus 6-inch overlap with not less than 6 inches of concrete with 28-day compressive strength of 3000 psi.
2. Make branch connections from side into existing piping, NPS 4 to NPS 20. Remove section of existing pipe, install wye fitting into existing piping, and encase entire wye with not less than 6 inches of concrete with 28-day compressive strength of 3000 psi.
a. Use concrete that will attain a minimum 28-day compressive strength of 3000 psi unless otherwise indicated.
b. Use epoxy-bonding compound as interface between new and existing concrete and piping materials.
3. Protect existing piping and manholes to prevent concrete or debris from entering while making tap connections. Remove debris or other extraneous material that may accumulate.
C. Make connections to existing piping and underground structures so finished Work complies with requirements specified for new Work.
3.9 FIELD QUALITY CONTROL
A. Inspect interior of piping to determine whether line displacement or other damage has occurred.
Inspect after approximately 24 inches of backfill is in place, and again at completion of Project.
1. Submit separate report for each system inspection.
2. Defects requiring correction include the following:
a. Alignment: Less than full diameter of inside of pipe is visible between structures.
b. Deflection: Flexible piping with deflection that prevents passage of ball or cylinder of size not less than 92.5 percent of piping diameter.
c. Damage: Crushed, broken, cracked, or otherwise damaged piping.
d. Infiltration: Water leakage into piping.
e. Exfiltration: Water leakage from or around piping.
3. Replace defective piping using new materials, and repeat inspections until defects are within allowances specified.
4. Reinspect and repeat procedure until results are satisfactory.
B. Test new piping systems, and parts of existing systems that have been altered, extended, or repaired, for leaks and defects.
1. Do not enclose, cover, or put into service before inspection and approval.
33 31 00 - 7
2. Test completed piping systems according to requirements of authorities having jurisdiction.
3. Schedule tests and inspections by authorities having jurisdiction with at least 24 hours' advance notice.
4. Submit separate report for each test.
5. Hydrostatic Tests: Test sanitary sewerage according to requirements of authorities having jurisdiction and the following:
a. Fill sewer piping with water. Test with pressure of at least 10-foot head of water, and maintain such pressure without leakage for at least 15 minutes.
b. Allowable leakage is maximum of 50 gal. /inch of nominal pipe size per mile of pipe, during 24-hour period.
c. Close openings in system and fill with water.
d. Purge air and refill with water.
e. Disconnect water supply.
f. Test and inspect joints for leaks.
g. Option: Test concrete gravity sewer piping according to ASTM C 924 .
6. Air Tests: Test sanitary sewerage according to requirements of authorities having jurisdiction, UNI-B-6, and the following:
a. Option: Test plastic gravity sewer piping according to ASTM F 1417.
7. Manholes: Perform hydraulic test according to ASTM C 969.
C. Leaks and loss in test pressure constitute defects that must be repaired.
D. Replace leaking piping using new materials, and repeat testing until leakage is within allowances specified.
3.10 CLEANING
A. Clean dirt and superfluous material from interior of piping. Flush with potable water.
END OF SECTION