About this file
This is a Performance and Payment Bonds (PPQ) template for the Lake Powhatan Wastewater Treatment Plant decommissioning project. The template is designed to facilitate the submission of bonding information by contractors bidding on this small business set-aside solicitation issued by the Department of Agriculture Forest Service. Both performance and payment bonds are required at 100% of the original contract award price, with bonds due within 5 days after award. Contractors may provide an irrevocable letter of credit or use Payment Bond Form SF-25A and Performance Bond Form SF-25 as alternatives, as permitted under FAR 52.228-13.
The template serves as a standardized format for qualified bonding companies to present their bonding capacity and terms for this construction project, which involves decommissioning and removing a 20,000-gallon-per-day wastewater treatment plant and related pump station components, then connecting to municipal sewer. The project magnitude is between $1,000,000 and $5,000,000. This template is an administrative document that does not contain specific pricing, performance requirements, or scope details, but rather provides the framework through which bonding information must be submitted to meet the mandatory bonding requirements of the solicitation.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Past Performance Questionnaire
Instructions:
The USDA Forest Service is soliciting proposals for Solicitation No. 12445226Q0007 – Lake Powhatan WWTP Disaster Recovery Decommissioning and Sewer Connection. As part of the procurement process, an emphasis is being placed on past performance as a source selection factor. In order to accurately evaluate the offeror’s past performance, your assistance is requested in obtaining and verifying the past performance history of this offeror.
Clients may return completed PPQ’s to the Contractor, or directly to the government. Clients who wish to submit their completed PPQ directly to the government may email the completed form to the Contracting Officer, Jalisa Sims at Jalisa.sims@usda.gov and Source Selection Board Chair, Tim Heim, at Timothy.Heim@usda.gov. Please make the subject line of the email read “12445226Q0007- Past Performance Questionnaire – [Insert Evaluated Company’s Name]”. If submitting to the government directly, please respond by March 2, 2026 at 5:00 PM EST.
Contractor Information:
(To be completed by Contractor)
Firm Name:
Point of Contact at the Firm:
POC Phone Number:
POC Email:
Project Information:
(To be completed by Contractor)
Contract/Task Order Number:
Project Title:
Project Description:
Project Location:
Award Date:
Completion Date:
Actual Completion Date:
Explain Difference:
Original Contract Price:
Final Contract Price:
Explain Difference:
CLIENT’S ASSESSMENT OF THE CONTRACTOR
(To be completed by Client)
Client Information:
Business/Organization Name:
Point of Contact for the Client:
Title:
Phone Number:
Email:
Point of Contact’s Role in the Project:
Date Questionnaire Completed:
Client’s Signature:
Rating Scale:
EXCEPTIONAL
(5) Performance EXCEEDS MOST contractual requirements to the Government’s benefit. The performance of areas being assessed was accomplished with few minor issues or concerns.
VERY GOOD
(4) Performance EXCEEDS SOME contractual requirements to the Government’s benefit. The performance of areas being assessed was accomplished with few minor issues or concerns, for which the Contractor’s corrective actions were highly effective.
SATISFACTORY
(3) Performance MEETS contractual requirements. The performance of the areas being assessed contains minor issues or concerns, for which corrective actions taken by the Contractor were effective.
MARGINAL
(2) Performance MEETS SOME contractual requirements. The performance of the areas being assessed includes significant problems, issues, or concerns for which corrective actions taken by the Contractor were only somewhat effective.
UNSATISFACTORY
(1) Performance DOES NOT MEET contractual requirement. The performance of the areas being assessed includes serious problems, issues, or concerns for which the Contractor’s corrective actions were ineffective.
| NOT APPLICABLE (N/A) |
| Performance information not recent or relevant as defined in the Solicitation. Unable to provide assessment. |
CLIENT’S ASSESSMENT OF THE CONTRACTOR, CONT.
(To be completed by Client) Quality of Product or Service:
| N/A |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
Quality of Deliverable (Met Specifications)
Conformance to good standards of workmanship
Adequacy of the QC Plan
Implementation of the QC Plan
Quality of QC Documentation
Identification/Correction of Deficient Work
Adequacy of Submittals
Use of Specified Materials
Comments:
Cost Control:
| N/A |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
Ability to meet the terms and conditions within the contractually agreed price(s)
Were invoices current, accurate, and complete
Reasonableness of price change proposals submitted
Proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client
Comments:
Schedule:
| N/A |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
Adequacy of Initial Schedule
Adherence to Approved Schedule
Resolution of Delays
Timely submission of Required Documentation
Timely submission of Updated and Revised Schedules
Comments:
Management / Business Relations:
| N/A |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
Management of Resources/Personnel
Key Personnel were Utilized Appropriately and Effectively
Coordination and Control of Subcontractors
Professional Conduct
Review/Resolution of Subcontractor’s Issues
Change Order Activity (By Contractor)
Maintains an Adequate Work Force
Responsiveness to Corrective Actions
Identifies and Mitigates Risk
Comments:
Regulatory Compliance:
| N/A |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
Complied With Contract Clause Requirements
Complied With Reporting Requirements
Complied With Design Requirements
Compliance With Labor Laws and Regulations
Complied With Safety Laws and Regulations
Correction Of Noted Deficiencies
Comments:
Overall Rating:
| N/A |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
Overall Rating
Comments:
Recommendation:
| Given what you know today about the contractor’s ability to perform the work required, would you recommend the selection of this firm for similar requirements in the future? |
| Would |
| Would Not |
Please use this space to provide additional comments, as needed. Identify Rating Category for each Comment.
Source Selection Information - See FAR 2.101 and 3.104
File details come from the government source that posted it. Updated .