Attachment 4- Lake Pow WWTP Decomm SOI.pdf
PDF 80 KB Posted
- Attached to
- Lake Powhatan Sewer Project
- Solicitation number
- 12445226Q0007
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Bid Schedule for a construction project titled "Lake Powhatan Recreation Area WWTP Decommissioning and Municipal Sewer Connection" with the US Forest Service and Naventure listed as project owners. The date is listed as TBD.
The bid schedule contains 28 line items organized into five categories: Modifications at Sewer Pump Station (Items 1-6), Sewer Force Main Items (Items 7-11), Site Work and Erosion Control (Items 12-21), Facility Decommissioning (Item 22), and Allowances (Items 23-26), followed by two Alternate Bid Items (Items 27-28). Base bid items include mobilization and construction staking, submersible sewer pumps, control panel and electrical renovation, precast concrete meter vault, electromagnetic meter and sump pump, and 80 linear feet of chain link security fence. The sewer force main work requires 9,240 linear feet of 2" SDR 21 PVC sewer force main, 600 linear feet of 2" DR11 HDPE directional bore, 400 pounds of mechanical joint fittings, one connection to receiving manhole, and four air release/vacuum breaker valves. Site work and erosion control includes clearing and grubbing, 3,250 linear feet of standard silt fence and 120 linear feet of heavy-duty silt fence, 66 straw wattle check dams, 20 non-erosive outlets, eight inlet protection structures, site stabilization, final grassing and cleanup, 4,000 square feet of gravel repair, and 1,250 square feet of asphalt repair. The facility decommissioning item encompasses the wastewater treatment plant and sewer pump station components. Allowances are included for miscellaneous stone (10 tons), trench rock removal (10 cubic yards), unsuitable soil removal (20 cubic yards), and suitable backfill (24 cubic yards). Alternate bid items include a back-up power generator with automatic transfer switch and a propane tank. Unit prices and total prices are blank, to be completed by bidders.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Title: Lake Powhatan Recreation Area WWTP Decommissioning and Municipal Sewer Connection
Item
No. Description Unit Quantity Unit Price Total Price
1 Mobilization & Construction Staking LS 1
Submersible Sewer Pumps (see Measurement and Payment for description) LS 1
3 Control Panel and Electrical Renovation of Control Room LS 1
4 Precast Concrete Meter Vault and Internal Plumbing LS 1
5 2" Electromagnetic Meter and Sump Pump LS 1
6 6' Chain Link Security Fence LF 80
7 2" SDR 21 PVC Sewer Force Main LF 9,240
2" DR11 HDPE Directional Bore (for passing beneath paved roads and certain culverts) LF 600
9 2" - Mechanical Joint Fittings LB 400
10 Connection to Receiving Manhole (see detail) EA 1
11 Air Release/Vacuum Breaker Valve in MH EA 4
12 Clearing & Grubbing LS 1
13 Silt Fence (Standard, single row) LF 3,250
14 Silt Fence (Heavy Duty, double row) LF 120
15 Straw Wattle Check Dams EA 66
16 Non-Erosive Outlets EA 20
17 Inlet Protection EA 8
18 Site Stabilization LS 1
19 Final Grassing & Cleanup LS 1
20 Repair Gravel Areas SF 4,000
21 Repair Asphalt SF 1,250
BID SCHEDULE
Project Owner: US Forest Service and Naventure
Date: TBD
Modifications at Sewer Pump Station
Sewer Force Main Items
Site Work and Erosion Control
Decommissioning (WWTP and Components of Sewer Pump
Station and Force Main) LS 1
23 Misc. Stone (ALLOWANCE) TON 10
24 Trench Rock Removal (ALLOWANCE) CY 10
25 Unsuitable Soil Removal (ALLOWANCE) CY 20
26 Suitable Backfill (ALLOWANCE) CY 24
ALTERNATE BIDS ITEMS
Back-up Power Generator and ATS (see Measurement and
Payment for description) LS 1
28 Propane Tank (see Measurement and Payment for description) LS 1
Facility Decommisioning
Allowances
Base Bid Price
File details come from the government source that posted it. Updated .