This document is a Fire Protection Symbols, Legend, Notes, and Index drawing prepared by TLC Engineering Solutions for Valencia College's East Campus Black Box Theater Fire Sprinkler Installation project located in Orlando, Florida. The drawing provides comprehensive technical specifications for a fire protection system design, including detailed notes on installation requirements, design criteria, and compliance with NFPA 13 and Florida Fire Prevention Code standards. The project involves installing a wet pipe sprinkler system in the Black Box Theater and surrounding areas, with specific design parameters including ordinary hazard classification, design density of 0.20 GPM/sq. ft., and a hydraulic remote area of 1,500 sq. ft.
The technical specifications outline rigorous requirements for materials, installation methods, valve and accessory selections, and testing protocols. Key technical elements include using Schedule 10 and Schedule 40 black steel piping, UL/FM approved components, semi-recessed chrome-finished sprinklers rated at 165°F, and comprehensive hydrostatic testing procedures. The project includes provisions for flow switches, tamper switches, and integration with the fire alarm system. Flow test data conducted on May 10, 2024, demonstrates adequate water supply pressures, with static pressures ranging from 74-77 PSI and flow rates of 1,260-1,350 GPM, which supports the proposed fire protection system design.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FIRE PROTECTION GENERAL NOTES
1. FIRE PROTECTION SYSTEM TO COMPLY WITH NFPA 13 AND ALL APPLICABLE STATE CODES.
2. FINAL INSPECTION AND APPROVAL BY LOCAL FIRE MARSHAL AND ARCHITECT/ENGINEER.
3. SPRINKLER SHOP DRAWINGS AND MATERIAL SUBMITTALS SHALL BE SUBMITTED TO THE ARCHITECT/ENGINEER AND STATE
FIRE MARSHAL AND SHALL BE APPROVED PRIOR TO ANY INSTALLATION.
4. PIPE ROUTING SHOWN IS SCHEMATIC ONLY. IT IS THE RESPONSIBILITY OF THIS CONTRACTOR TO PROVIDE ANY ADDITIONAL
OFFSETS REQUIRED FOR PROPER INSTALLATION AND COORDINATION WITH OTHER TRADES.
5. PIPING IN AREAS WITH EXPOSED STRUCTURE SHALL BE INSTALLED AS HIGH AS POSSIBLE TO ALLOW THE OWNER MAXIMUM
USE OF THE SPACE.
6. REFER TO ARCHITECTURAL REFLECTED CEILING PLANS FOR CEILING DESCRIPTIONS AND HEIGHTS.
7. SPRINKLERS ARE TO BE COORDINATED WITH ALL DIFFUSERS, SPEAKERS, LIGHTING FIXTURES AND CEILING SYSTEMS.
SPACING OF SPRINKLERS SHALL BE IN ACCORDANCE WITH NFPA 13 AND THE LISTING OF THE SPRINKLER.
8. SPRINKLER LOCATIONS SHALL BE CENTERED IN THE TILE. PROVIDE ARMOVER OR SWING JOINT AS REQUIRED.
9. SPRINKLERS IN AREAS WITH EXPOSED STRUCTURE (OBSTRUCTED CONSTRUCTION) SHALL BE INSTALLED WITH DEFLECTOR 1" BELOW THE BOTTOM OF THE BEAM (MAXIMUM 22" BELOW ROOF DECK). EXPOSED BAR JOISTS THAT HAVE SPRAY-ON FIRE PROOFING THAT MAKES THE JOIST SOLID SHALL BE TREATED LIKE A BEAM WITH THE SPRINKLERS 1" BELOW THE BOTTOM OF
THE FIRE PROOFING.
10. SLEEVE AND/OR FIRESTOP ALL PENETRATIONS THROUGH RATED WALLS, CEILINGS, AND FLOORS WITH U/L LISTED ASSEMBLIES. FIRESTOP ASSEMBLIES SHALL BE EQUAL OR EXCEED THE RATING OF THE WALL, CEILING OR FLOOR. SEE
ARCHITECTURAL DRAWINGS FOR FINAL FINISHES.
11. PROVIDE ACCESS PANELS TO ALL VALVES ABOVE NON-ACCESSIBLE CEILINGS AND CHASES.
12. PROVIDE A PERMANENTLY ATTACHED NAME TAG TO THE RISER STATING THE REQUIRED DESIGN CRITERIA FOR EACH
HYDRAULICALLY-DESIGNED SYSTEM.
13. PROVIDE SPRINKLERS UNDERNEATH ALL EXPOSED DUCTWORK WHICH IS OVER 48" WIDE AND SPACE HEADS AROUND ALL OBSTRUCTIONS IN ACCORDANCE WITH NFPA 13. HEADS UNDER DUCTS ARE NOT INDICATED ON THE DRAWINGS BUT ARE REQUIRED AND SHALL BE PROVIDED IN ACCORDANCE WITH NFPA 13. SPRINKLER LOCATIONS UNDER DUCTWORK AND
AROUND OBSTRUCTIONS SHALL BE GOVERNED BY FINAL INSTALLED LOCATIONS.
14. PROVIDE SPRINKLERS AT THE TOP AND BOTTOM OF ALL STAIRWELLS AND AT THE LANDING OF EACH FLOOR THAT OPENS
INTO MORE THAN ONE FIRE ZONE.
15. PROVIDE SPRINKLER GUARDS ON ALL HEADS IN ELECTRIC ROOMS, TELEPHONE ROOMS, ELEVATOR ROOMS, ELEVATOR
SHAFTS AND ON ANY HEADS LESS THAN 7'-0" ABOVE THE FLOOR.
16. IF SYSTEM PRESSURE EXCEEDS 100 PSI, ALL HANGERS ON END HEADS IN PENDANT POSITION SHALL BE WITHIN 12" OF END
OF LINE IN ACCORDANCE WITH NFPA 13.
17. COORDINATE PIPING WITH ALL ELECTRICAL EQUIPMENT (PANELS, TRANSFORMERS, ETC.) PRIOR TO ANY INSTALLATION. DO NOT ROUTE ANY PIPING OVER ANY ELECTRICAL PANELS UNDER ANY CIRCUMSTANCES. ANY PIPING RUN OVER ELECTRICAL
SHALL BE REROUTED AT NO ADDITIONAL COST.
18. THE WATER MAIN TO BUILDING IS EXISTING WATER MAIN AND IS TO REMAIN.
19. THE LOCAL WATER SUPPLIER HAS NOT INDICATED THAT THE WATER SUPPLY COULD LEAD TO MICROBIAL INDUCED
CORROSION.
20. ALL VALVES SHALL BE PROVIDED WITH TAMPER SWITCHES AND ALL ZONES SHALL BE PROVIDED WITH FLOW SWITCHES
WIRED TO THE FIRE ALARM SYSTEM.
DESIGN CRITERIA
BLACK BOX THEATER 100 & STORAGE 100A :
OCCUPANCY CLASSIFICATION:
SYSTEM TYPE:
DESIGN DENSITY:
HYDRAULIC REMOTE AREA:
SPRINKLER ORIFICE SIZE:
DURATION OF SUPPLY:
MAX. COVERAGE/SPRINKLER HEAD:
HOSE STREAM ALLOWANCE:
STAIR 178, CONTROL ROOM 200/200B:
OCCUPANCY CLASSIFICATION:
SYSTEM TYPE:
DESIGN DENSITY:
HYDRAULIC REMOTE AREA:
SPRINKLER ORIFICE SIZE:
DURATION OF SUPPLY:
MAX. COVERAGE/SPRINKLER HEAD:
HOSE STREAM ALLOWANCE:
STANDPIPE:
SYSTEM DESCRIPTION:
REFERENCE PUBLICATIONS:
THE FOLLOWING PUBLICATIONS SHALL BE USED AS A REFERENCE FOR DESIGN OF THE FIRE SUPPRESSION SYSTEM ON THIS
PROJECT.
• FLORIDA FIRE PREVENTION CODE, 8th EDITION (2023)
• NFPA 13, STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS, 2019 EDITION
• NFPA 25, STANDARD FOR THE INSPECTION, TESTING, AND MAINTENANCE OF WATER-BASED FIRE PROTECTION
SYSTEMS, 2020 EDITION
SPRINKLER TYPE CRITERIA:
ALL SPRINKLERS IN CEILINGS TO HAVE SEMI-RECESSED SPRINKLERS (CHROME FINISH), AND SHALL BE RATED AT 165°F WITH A 5.6
K-FACTOR.
ALL SPRINKLERS IN AREAS WITH NO CEILINGS TO HAVE BRASS UPRIGHT SPRINKLERS, AND SHALL BE RATED AT 165° F WITH A 5.6
K-FACTOR. PROVIDE SPRINKLER HEAD WITH GUARDS IN MECHANICAL/ELECTRICAL ROOMS.
ORDINARY HAZZARY GROUP II
WET PIPE
.20 GPM/SQ.FT.
1,500 SQ. FT.
1/2"
60 - 90 MIN.
130 SQ. FT.
250 GPM
ORDINARY HAZARD GROUP I
WET PIPE
.15 GPM/SQ.FT.
1,500 SQ. FT.
1/2"
60 - 90 MIN.
130 SQ. FT.
250 GPM
EXISTING AUTOMATIC WET
FLORIDA ADMINISTRATIVE CODE CHAPTER 61G15-32 NOTES:
1. THE FIRE PROTECTION SYSTEM SCOPE OF WORK SHALL INCLUDE THE PREPARATION OF THE FIRE PROTECTION SYSTEM LAYOUT DOCUMENTS (WORKING PLANS). PROVIDE ALL EQUIPMENT, MATERIALS, COMPONENTS, ASSEMBLIES AND SUPPORT SYSTEMS REQUIRED, AS DESCRIBED, IN NFPA 13. THE FIRE PROTECTION CONTRACTOR SHALL CONDUCT A HYDRANT FLOW TEST AND PERFORM HYDRAULIC CALCULATIONS FOR PREPARATION OF THE FIRE PROTECTION SYSTEM
LAYOUT DOCUMENTS (WORKING PLANS).
2. THE FIRE PROTECTION DESIGN, CALCULATIONS, INSTALLATION AND THE ACCEPTANCE TESTING OF THE FIRE PROTECTION SYSTEM SHALL BE IN ACCORDANCE WITH NFPA 13 ; NFPA 24 ; THE FLORIDA BUILDING CODE, THE FLORIDA FIRE PREVENTION CODE AND ALL LOCAL CODES REQUIRED BY THE AUTHORITY HAVING JURISDICTION.
3. AREA OCCUPANCIES AND HAZARD CLASSIFICATIONS ARE LISTED IN THE DESIGN CRITERIA NOTE LOCATED ON THE
CONTRACT DOCUMENTS.
4. THE STRUCTURAL SUPPORTS AND OPENINGS FOR THE FIRE PROTECTION SYSTEM HAVE BEEN COORDINATED WITH THE
STRUCTURAL ENGINEER.
5. ALL SYSTEM CONTROL VALVES SHALL BE PROVIDED WITH TAMPER SWITCHES AND INTERFACE WITH THE FACP ON THE SUPERVISORY CIRCUIT, ALL FLOW SWITCHES SHALL INTERFACE WITH THE FACP ON THE ALARM CIRCUIT.
6. THE FIRE PROTECTION CONTRACTOR SHALL PREPARE AND PROVIDE FIRE PROTECTION SYSTEM LAYOUT DOCUMENTS AND HYDRAULIC CALCULATIONS. FIRE PROTECTION SYSTEM LAYOUT DOCUMENTS WITH HYDRAULIC CALCULATIONS SHALL BE SUBMITTED TO THE ARCHITECT/ENGINEER AND THE LOCAL AHJ FOR ACCEPTANCE PRIOR TO PERMITTING.
7. ALL FIRE PROTECTION EQUIPMENT AND COMPONENTS SHALL BE LISTED AND TESTED FOR FIRE PROTECTION USE. ALL FIRE PROTECTION EQUIPMENT AND COMPONENTS SHALL BE THE U.L. LISTED AND FM APPROVED.
8. THE WATER SUPPLY FOR THE FIRE PROTECTION SYSTEM HAS NOT SHOWN ANY EVIDENCE OF MICROBIAL INDUCED CORROSION (MIC). THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE ARCHITECT/ENGINEER OF ANY EVIDENCE OF
MIC AND PROVIDE NECESSARY WATER TREATMENT AS NEED TO REDUCE OR ELIMINATE MIC.
FIRE PROTECTION LEGEND
OR - CONTROL VALVE W/ TAMPER SWITCH
SYMBOL DESCRIPTION
- CHECK VALVE
- FLOW SWITCH
- FIRE DEPARTMENT CONNECTION (WALL MOUNTED)
- FIRE DEPARTMENT CONNECTION (SIDEWALK SIAMESE)
- FIRE VALVE CABINET
- STANDPIPE WITH FIRE DEPARTMENT VALVE
- SPRINKLER DRAIN RISER
- COMBINATION RISER
- DRAIN VALVE
- REVISION REFERENCE
- DETAIL REFERENCE CALLOUT
FP3.01
DETAIL No.
SHEET SHOWN ON
- BACKFLOW PREVENTOR
- BACKFLOW PREVENTOR W/ FDC
X - HYDRAULIC NODE
FIRE PROTECTION SPECIFICATIONS
1.00 - GENERAL PROVISIONS
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
PROVIDE ALL LABOR, MATERIAL AND EQUIPMENT FOR A COMPLETE AND PROPERLY OPERATING FIRE PROTECTION
SYSTEM.
CODES AND STANDARDS: THE FIRE SPRINKLER PROTECTION SYSTEMS INSTALLATION, FLUSHING AND TESTING SHALL
COMPLY WITH THE REQUIREMENTS OF NFPA 13 AND ALL LOCAL CODES HAVING JURISDICTION.
PIPE THREAD PATTERN: ALL THREADS SHALL BE IN ACCORDANCE WITH LOCAL FIRE DEPARTMENT SPECIFICATIONS
AND NFPA 1963.
UL/FM APPROVAL: ALL EQUIPMENT, VALVES, COUPLINGS, HANGERS AND DEVICES SHALL BE APPROVED BY UNDERWRITERS' LABORATORY (UL) OR FACTORY MUTUAL (FM) FOR USE IN FIRE PROTECTION SERVICE.
LICENSURE: THE FIRE PROTECTION SYSTEMS SHALL BE INSTALLED BY A STATE CERTIFIED FIRE PROTECTION
CONTRACTOR.
ALL FIRE PROTECTION WORK SHALL BE DONE IN A NEAT AND WORKMAN-LIKE MANNER.
CONTRACTOR SHALL SECURE AND PAY FOR ALL PERMITS AND FEES, ETC., REQUIRED FOR THE EXECUTION OF THIS
WORK.
CONTRACTOR SHALL COORDINATE WORK WITH OTHER TRADES BEFORE FABRICATION OR INSTALLATION. OFFSETS AND/OR TRANSITIONS REQUIRED SHALL BE PROVIDED WITHOUT ADDITIONAL COST. CONTRACTOR SHALL COORDINATE
AND INSTALL WORK IN A TIMELY MANNER TO PREVENT DELAYS IN THE CONSTRUCTION.
CONTRACTOR SHALL BE RESPONSIBLE TO REPAIR OR REPLACE DAMAGED EQUIPMENT AND/OR MATERIAL.
PIPING SHOP DRAWINGS: SUBMIT 1/8" SCALE PIPING SHOP DRAWINGS. SHOP DRAWINGS SHALL INCLUDE SPRINKLER PIPING CUT LENGTHS, OFFSETS, FITTINGS AND DEVICES, ELEVATIONS, HANGER LOCATIONS, SPRINKLER HEAD COUNT BY TYPE, ELEVATION SECTIONS AND OTHER INSTALLATION INFORMATION. SUBMIT HYDRAULIC CALCULATIONS PROVING THE VIABILITY OF THE MOST HYDRAULICALLY-REMOTE AREAS OF THE PROJECT. INDICATE HYDRAULIC REFERENCE POINTS AND SUBMIT COMPUTER ANALYZED NODAL CALCULATIONS IN BOTH TABULAR AND GRAPHICAL FORMATS. HYDRAULIC IMBALANCE SHALL NOT EXCEED 0.01 GPM AT ANY NODE, AND WATER VELOCITY SHALL NOT EXCEED 20 FEET PER SECOND. DEMONSTRATE COMPLIANCE WITH THE REQUIREMENTS OF NFPA 13 REGARDING DENSITY, AREA OF APPLICATION, SELECTION OF HYDRAULICALLY-REMOTE AREAS, AND MAXIMUM COVERAGE PER
SPRINKLER.
COORDINATE ALL PIPE ROUTING WITH ALL OTHER TRADES PRIOR TO INSTALLATION. ROUTE ALL PIPING TO AVOID
DUCTWORK, PIPING, AND BUILDING STRUCTURE.
2.00 - BASIC MATERIALS AND METHODS
GENERAL: ONLY THE FOLLOWING MATERIALS DESIGNED FOR 175 PSIG CWP SHALL BE USED FOR FIRE PROTECTION
PIPING UNLESS SPECIFICALLY INDICATED OTHERWISE.
PIPE AND FITTINGS: ALL PIPING JOINED BY GROOVED COUPLINGS TO BE SCHEDULE 10 BLACK STEEL PIPE. ALL PIPING
JOINED BY THREADED JOINTS TO BE SCHEDULE 40 BLACK STEEL PIPE.
HANGERS: ALL HANGER SPACING SHALL COMPLY WITH THE REQUIREMENTS OF NFPA-13.
ACCESS PANELS: PROVIDE ACCESS PANELS TO ALL VALVES WITHIN CHASES OR ABOVE NON-ACCESSIBLE CEILINGS.
REFER TO ARCHITECTURAL DRAWINGS FOR CEILING TYPES.
HYDROSTATIC TESTS: ABOVE GROUND AND BELOW GROUND PIPING SYSTEMS SHALL BE HYDROSTATICALLY TESTED AT NOT LESS THAN 200 PSI PRESSURE, OR AT 50 PSI IN EXCESS OF THE MAXIMUM PRESSURE, WHICHEVER IS GREATER, FOR A PERIOD OF 2 HOURS. THE TEST PRESSURE SHALL BE READ FROM A GAUGE LOCATED AT THE LOW ELEVATION POINT OF THE INDIVIDUAL SYSTEM OR PORTION OF THE SYSTEM BEING TESTED. THE SPRINKLER PIPING SHALL NOT HAVE LEAKAGE EXCEEDING THE AMOUNTS SPECIFIED IN NFPA 24. LEAKAGE QUANTITIES SHALL BE DETERMINED BY PUMPING AT THE SPECIFIED TEST PRESSURE FROM A CALIBRATED CONTAINER. REPAIR LEAKING JOINTS AND RETEST AS NECESSARY UNTIL ALL SYSTEMS HAVE BEEN TESTED. TEST THE PIPING BETWEEN THE CHECK VALVE IN THE FIRE DEPARTMENT INLET PIPE AND THE OUTSIDE CONNECTION THE SAME AS THE BALANCE OF THE SYSTEM.
2.1
2.2
2.3
2.4
2.5
3.00 - FIRE PROTECTION VALVES AND ACCESSORIES
BUTTERFLY TYPE ISOLATION, 2-1/2 INCH AND LARGER: ISOLATION VALVES 2-1/2 INCH AND LARGER SHALL BE CAST IRON BODY BUTTERFLY VALVES WITH THE VALVE SIZE, PRESSURE RATING, MANUFACTURER AND "UL" AND "FM" CAST INTO THE BODY. VALVE SHALL HAVE BRONZE OR CAST IRON DISC, NEOPRENE DISC LINER, CAST IRON HANDWHEEL WITH DISC POSITION INDICATOR, INTEGRAL TAMPER SWITCH, 175 PSIG CWP WORKING PRESSURE, 350 PSIG CWP TEST
PRESSURE, AND FLANGED OR GROOVED CONNECTIONS - GRINNELL 8000 FP OR EQUAL.
FLOW SWITCH: PROVIDE AN ELECTRIC FLOW SWITCH WHERE INDICATED OR REQUIRED. FLOW SHALL BE SENSED BY AN IMMERSION PADDLE, WITH AN ADJUSTABLE RETARD SETTING FROM 0 TO 70 SECONDS TO MINIMIZE FALSE ALARMS.
FLOW SWITCH SHALL HAVE 2 SEPARATE SINGLE POLE, DOUBLE THROW MICROSWITCHES TO ACTIVATE A FLOW ALARM, OR TO INDICATE A TROUBLE SIGNAL IF THE FLOW SWITCH HOUSING IS TAMPERED. FLOW ALARM SHALL BE AUTOMATICALLY RESETTING. PROVIDE CLAMP-ON HOUSING TO SECURE UNIT TO PIPE, OR THREADED CONNECTION
FOR TEE FITTING - POTTER ELECTRIC SIGNAL CO. VSR-S.
3.1
3.2
FIRE PROTECTION FLOW TEST DATA
STATIC HYDRANT
STATIC - 74 PSI
RESIDUAL - 65 PSI
FLOW HYDRANT
1260 GPM
DATE - 05-10-2024
TIME - 7:45AM
LOCATION - HYDRANT #3 - #P12298
TEST CONDUCTED BY - FARRELL FIRE PROTECTION, LLC (ROBERT FARRELL #20815200012011)
STATIC HYDRANT
STATIC - 77 PSI
RESIDUAL - 68 PSI
FLOW HYDRANT
1350 GPM
DATE - 05-10-2024
TIME - 7:45AM
LOCATION - HYDRANT #4 - #P10676
GAGE
INSPECTOR'S TEST
FLOW SWITCH
GROOVED BUTTERFLY
W/TAMPER SWITCH
PIPE TO EXTERIOR(SEE PLANS)
GROOVED CHECK
TOP BEAM CLAMP
(U.L. LISTED OR F.M. APPROVED)
PIPE HANGER RING
(U.L. LISTED OR F.M. APPROVED)
ALL THREAD ROD
CONCRETE FASTENER
(U.L. LISTED OR F.M. APPROVED)
PIPE HANGER RING
(U.L. LISTED OR F.M. APPROVED)
ALL THREAD ROD
This item has been digitally signed and sealed by Francis M. Robertson, PE, on the date adjacent to the seal.
Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.
255 S. Orange Avenue Suite 1600
Orlando, FL 32801 P 407.841.9050 www.tlc-engineers.com
© Copyright 2019 TLC Engineering Solutions, Inc.
TLC Project No. :
COA 15
Seal
Drawing No.:
Scale:
Revisions:
Drawing Title:
Approved By:
Issue Date:
Project No.:
Drawn By:
Consultants:
124060
As indicated
/2 /2
:0
:2
P M
C U s e rs \k o h n e n .b a rr y \O n e D ri v e
T L C
E n g in e e ri n g S o lu ti o n s \D o c u m e n ts \1
E A
S T
M
E P
R k o h n e n .b a rr y tl c -e n g
.c o m .r v t
V A
L E
N C
IA
C
O L L E
G E
B
L A
C K
B O
X E
A S
T B
U
IL
D
IN
G
N o rt h E c o n lo c k h a tc h e e
T ra il, O rl a n d o
124060
10-25-2024
DEP
KFB
FIRE PROTECTION
SYMBOLS, LEGEND,
NOTES AND INDEX
FP001
FIRE PROTECTION DRAWING INDEX
SHEET DESCRIPTION
FP001 FIRE PROTECTION SYMBOLS, LEGEND, NOTES AND INDEX
FP101 LEVEL 01 - FIRE PROTECTION
FP301 ENLARGED - FIRE PROTECTION
No Scale
SPRINKLER ZONE VALVE - WET PIPE SYSTEM
A
No Scale
HANGER - STEEL
B
No Scale
HANGER - CONCRETE
C
No. Date Description
10-25-2024 PERMIT / BID SET
Frank.Robertson Date 10/25/2024
| Sheets |
| CS001 - COVER SHEET |
| E001 - ELECTRICAL SYMBOL LEGEND, GENERAL NOTES AND INDEX |
| E101 - ELECTRICAL - 1ST LEVEL |
| FP001 - FIRE PROTECTION SYMBOLS, LEGEND, NOTES AND INDEX |
| FP101 - LEVEL 01 - FIRE PROTECTION |
| FP301 - ENLARGED - FIRE PROTECTION |
| 2024-10-25T15:43:43-0400 | |
| Francis M Robertson |