This is a Statement of Work (SOW) for RFQ No. 19SP5026Q0008 issued by the U.S. Department of State's OBO Facilities Management Division for a hydraulic distribution system project at the U.S. Embassy Madrid located at Calle de Serrano, 75, 28006 Madrid, Spain, with an effective date of January 2026.

The contractor must supply and install a complete hydraulic distribution system including: Schedule 40 black steel distribution piping (1/2" to 8" diameter) per ASTM A53/A106 or equivalent EU standards with two coats of primer; closed-cell elastomeric thermal insulation (Armaflex or equivalent) with anti-condensation barrier; a GRUNDFOS or equivalent accelerator pump group (56,000 l/h flow rate, 10 m.c.a. pressure, DN80 connections); a plate-type stainless steel heat exchanger (Indelcasa or equivalent, 1,000 kW power, DN100 connections) with mounting frame, PTFE gaskets, and counterflow operation for hydraulic circuit separation; butterfly shut-off valves, flat weld flanges, vibration dampers, Y-type filters, check valves, and concentric reducers; analog thermometers and automatic air vents; electrical protection equipment and control wiring; and replacement of three boiler safety valves rated to 5 bars. All work must comply with OSHA, International Building Code, International Mechanical Code, ASHRAE, SMACNA, and NFPA 101 standards. Prior to implementation, the contractor must submit product data, shop drawings, design specifications, bill of materials, and a Critical Path Method schedule within 15 days of award, along with an Activity Hazard Analysis and personnel list for Embassy approval. The contractor is responsible for site visits, obtaining local permits, area isolation planning, water protection measures, and providing as-built documentation upon completion with site walkover inspection by the Contracting Officer's Representative before final acceptance.

View the file

Other files

File Type Posted
ATTACHMENT 7 - TECHNICAL SHEET.zip ZIP file
RFQ No. 19SP5026Q0008.pdf PDF
Signed invitation letter.pdf PDF
ATTACHMENT 8 - TOTALCOST BREAKDOWN.pdf PDF
ATTACHMENT 5 - DRAWINGS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ No. 19SP5026Q0008

STATEMENT OF WORK

U.S. DEPARTMENT OF STATE

OBO FACILITIES MANAGEMENT DIVISION

Attachment 6. SPECIFICATIONS

U.S. Embassy Madrid Spain

January 2026

1 INTRODUCTION / SUMMARY OF WORK PROJECT

This Scope of Work (SOW) outlines the supply and installation of a heat exchanger for the separation and decoupling of hydraulic circuits, completed with sealed connections and PTFE gaskets, mounting frame and support, counterflow operation, fully installed, with the following technical specifications at the U.S. Embassy in Madrid.

The Contractor shall provide all labor, materials, equipment, and supervision necessary to perform the tasks detailed below, in compliance with applicable safety and construction regulations.

The project will be located on:

Calle de Serrano, 75, 28006 Madrid, Spain

2 SCOPE OF WORK

2.1 PRIOR TO IMPLEMENTATION

2.1.1 Site visit and survey. The contractor shall be responsible for researching the existing conditions and matters that affect the cost or performance of the services. Contractor is encouraged to attend the site visit to confirm all measurement and survey existing layout prior to submission of BOM and quotation. Measurements provided are approximate and US Embassy shall not be held responsible for inaccurate dimensions.

2.1.2 The contractor shall coordinate and obtain any permit required by local authorities for the execution of the project.

2.1.3 DOCUMENT SUBMITTAL PACKAGE. The Offeror will include the follows as part of its offer:

2.1.3.1 Product Data: Manufacturer’s data sheets on each product to be used.

2.1.3.2 Shop Drawings:

2.1.3.2.1 Show complete layout and location of the area, including required clearances. Include site layout drawings or any other plans required for this project.

2.1.3.2.2 Show typical details of assembly, erection, and anchorage.

2.1.3.3 Design, bill of material to be installed, materials provided by the contractor must be approved before prefabrication and installation.

2.1.3.4 Complete finalized Work Plan including Critical Path Method (CPM) schedule.

2.1.4 DOCUMENT SUBMITTAL PACKAGE. Submit to the COR within 15 days of award, document submittal package that includes:

2.1.4.1 Activity Hazard Analysis (AHA) with detail specification of the safety plan to be implement.

2.1.4.2 List of personnel to be approved by the Embassy for the access request.

2.2 IMPLEMENTATION

2.2.1 AREA ISOLATION AND ACCESS RESTRICTION

2.2.1.1 The contractor shall provide a plan for the isolation and restriction of access to the area to be intervened.

2.2.1.2 Works must only be carried out by staff with technical knowledge to do so and always complying with the security rules.

2.2.1.3 Protection and isolation of the area. Please include water protection like provisional roof in case of rain.

2.3 PROJECT DETAILS

The project involves the supply, installation, and commissioning of a hydraulic distribution system, including the following key components and works:

2.3.1.1 Distribution Piping: Installation of Schedule 40 black steel piping, in compliance with ASTM A53 or ASTM A106 or equal EU standard with all necessary fittings, supports, and pressure/leak testing, for diameters ranging from 1/2" to 8", finished with two coats of primer.

2.3.1.2 Thermal Insulation: Application of closed-cell elastomeric insulation (e.g., Armaflex) with anti-condensation barrier, fully installed on all relevant piping and fittings.

2.3.1.3 Pumping System: Supply and installation of an accelerator pump group (Grundfos or equivalent) with all required accessories, including impeller, seals, flanges, and pressure gauges.

Brand: GRUNDFOS or similar ·Type: Single ·Flow Rate: 56,000 l/h ·Pressure: 10 m.c.a.

·Connections (Ø): DN80

2.3.1.4 Heat Exchanger: Installation of a plate-type stainless steel heat exchanger (Indelcasa or equivalent) for hydraulic circuit separation, complete with mounting frame, PTFE gaskets, and counterflow operation.

·Type: Plate ·Power: 1,000.00 kW ·Connections (Ø): DN100 ·Material: Stainless Steel

2.3.1.5 Valves and Fittings: Installation of butterfly shut-off valves, flat weld flanges, elastomeric vibration dampers, Y-type filters, check valves, and concentric reducers, all fully installed and operational.

2.3.1.6 Instrumentation: Installation of analog thermometers and automatic air vents at specified points in the system.

2.3.1.7 Electrical and Control: Supply and installation of electrical protection equipment (differential, circuit breakers, contactors, thermal relays), static starters for pump, and all necessary power and control wiring, fully connected and labeled.

2.3.1.8 Replace the 3 boiler safety valves to release excess pressure up to 5 bars (safe limit).

2.3.1.9 Additional Works: Includes optional heat exchanger insulation/enclosure, disassembly and reconnection of existing pump, and all required supports, anchors, and mounting hardware.

All equipment and materials will be installed, tested, and commissioned in accordance with relevant standards (UNE, DIN, EN), ensuring full functionality and compliance.

2.4 AFTER IMPLEMENTATION

2.3.2 Detail engineering and "as-built" documents: After final completion of the work, but before final acceptance thereof, the Contractor shall provide: a complete set of "as-built" drawings, based upon the record set of drawings, marked to show the details of construction as actually accomplished.

2.3.3 When all site work is complete, the Contractor's site superintendent shall review all activities and walk the project area with the COR to ensure that the embassy staff is satisfied, and all work items are acceptable. If any items are not completed, they shall be noted and provided to the Contractor to be addressed and completed immediately.

2.3.4 The Contractor shall ensure that, upon demobilization, the site is left in a clean and orderly appearance, equal to or better than prior to start of work.

3 Codes and Standards

3.1 Any design specifications shall conform to the more stringent requirements of the following attached codes and standards.

3.1.1 Occupational Safety & Health Administration Codes (OSHA)

3.1.2 International Building Code (ICBO)

3.1.3 International Mechanical Code (ICBO).

3.1.4 Mechanical Systems - ASHRAE and SMACNA Standards.

3.1.5 National Fire Protection Association (NFPA 101) Life Safety Code.

File details come from the government source that posted it. Updated .