About this file
This solicitation is for a 5-Year Protective Coating Indefinite-Delivery Indefinite-Quantity contract at Minot Air Force Base in North Dakota. The contractor will provide all labor, equipment, materials, supervision and services for interior and exterior protective coatings, including painting airfield pavement markings, street and parking lot striping, installing vinyl wall coverings and taping, bedding and texturing walls and ceilings, finishing wood floors and trim, sealing masonry joints, and painting fire hydrants, sign posts and equipment. The estimated value is between $1,000,000 to $4,900,000. This is a 100% small business set-aside. A pre-proposal site visit will be held on March 27, 2024 and proposals are due by an unspecified date. The seed project involves interior painting of approximately 8,700 square feet in Buildings 870 and 221.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment - FA452824R00030001.pdf | ||
| Solicitation Amendment FA452824R00030001 SF 30.pdf | ||
| RFI Tracker - Protective Coating.pdf | ||
| RFI Attachment - Historical Data.pdf | ||
| RFI Attachment - B221 Floor Plan.pdf | ||
| RFI Attachment - B870 Floor Plan.pdf | ||
| Attachment 3 - Offer Schedule.xlsx | XLSX spreadsheet | |
| Attachment 5 - Financial Responsibility.docx | DOCX document | |
| Attachment 7 - Subcontractor Consent.docx | DOCX document | |
| Solicitation - FA452824R0003.pdf | ||
| Attachment 4 - Past Performance Information Form.docx | DOCX document | |
| Attachment 1 - Statement of Work.pdf | ||
| Attachment 2 - Wage Determination.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Building 870 Building 870 Room 139 Interior Painting
| SERVICE REQUIRED (to include approx. sq. footage etc. to be painted): |
| Interior Painting |
| 1st Coat Painting |
| 2nd Coat Painting |
| Repair Wall Surficed (routine) |
| Texture Walls (routine) |
Keep track of amount of Square feet painted per room and notate the amount on the back of this Control Sheet
| FY24 | |||
| CONTRACT INFORMATION: | Estimated SF | Unit Cost | |
| 1st Coat Painting | 875 | ||
| 2nd Coat Painting | 250 | ||
| Repair Wall Surficed (routine) | 189 | ||
| Texture Walls (routine) | 189 |
TOTAL PRICE FOR PROJECT: $0.00
&"Arial,Bold"&14MINOT AFB
PROJECT
CONTROL SHEET
Building 221 Building 221 Quads 107/108 and Room 105c Interior Painting
| SERVICE REQUIRED (to include approx. sq. footage etc. to be painted): |
| Interior Painting |
| 1st Coat Painting |
| 2nd Coat Painting |
| Repair Wall Surficed (routine) |
| Texture Walls (routine) |
Keep track of amount of Square feet painted per room and notate the amount on the back of this Control Sheet
| FY24 | |||
| CONTRACT INFORMATION: | Estimated SF | Unit Cost | |
| 1st Coat Painting | 6,914 | ||
| 2nd Coat Painting | 500 | ||
| Repair Wall Surficed (routine) | 350 | ||
| Texture Walls (routine) | 350 |
TOTAL PRICE FOR PROJECT: $0.00