5 Year Protective Coating IDIQ - Minot AFB, ND Federal contract opportunity
Solicitation number
FA452824R0003
Issued by
Department of the Air Force Global Strike Command

About this file

This solicitation is for a 5-Year Protective Coating Indefinite-Delivery Indefinite-Quantity contract at Minot Air Force Base in North Dakota. The contractor will provide all labor, equipment, materials, supervision and services for interior and exterior protective coatings, including painting airfield pavement markings, street and parking lot striping, installing vinyl wall coverings and taping, bedding and texturing walls and ceilings, finishing wood floors and trim, sealing masonry joints, and painting fire hydrants, sign posts and equipment. The estimated value is between $1,000,000 to $4,900,000. This is a 100% small business set-aside. A pre-proposal site visit will be held on March 27, 2024 and proposals are due by an unspecified date. The seed project involves interior painting of approximately 8,700 square feet in Buildings 870 and 221.

View the file

Other files for this federal contract opportunity

Other files attached to 5 Year Protective Coating IDIQ - Minot AFB, ND, newest first.
File Type Posted
Solicitation Amendment - FA452824R00030001.pdf PDF
Solicitation Amendment FA452824R00030001 SF 30.pdf PDF
RFI Tracker - Protective Coating.pdf PDF
RFI Attachment - Historical Data.pdf PDF
RFI Attachment - B221 Floor Plan.pdf PDF
RFI Attachment - B870 Floor Plan.pdf PDF
Attachment 3 - Offer Schedule.xlsx XLSX spreadsheet
Attachment 5 - Financial Responsibility.docx DOCX document
Attachment 7 - Subcontractor Consent.docx DOCX document
Solicitation - FA452824R0003.pdf PDF
Attachment 4 - Past Performance Information Form.docx DOCX document
Attachment 1 - Statement of Work.pdf PDF
Attachment 2 - Wage Determination.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building 870 Building 870 Room 139 Interior Painting

SERVICE REQUIRED (to include approx. sq. footage etc. to be painted):
Interior Painting
1st Coat Painting
2nd Coat Painting
Repair Wall Surficed (routine)
Texture Walls (routine)

Keep track of amount of Square feet painted per room and notate the amount on the back of this Control Sheet

FY24
CONTRACT INFORMATION:Estimated SFUnit Cost
1st Coat Painting875
2nd Coat Painting250
Repair Wall Surficed (routine)189
Texture Walls (routine)189

TOTAL PRICE FOR PROJECT: $0.00

&"Arial,Bold"&14MINOT AFB

PROJECT

CONTROL SHEET

Building 221 Building 221 Quads 107/108 and Room 105c Interior Painting

SERVICE REQUIRED (to include approx. sq. footage etc. to be painted):
Interior Painting
1st Coat Painting
2nd Coat Painting
Repair Wall Surficed (routine)
Texture Walls (routine)

Keep track of amount of Square feet painted per room and notate the amount on the back of this Control Sheet

FY24
CONTRACT INFORMATION:Estimated SFUnit Cost
1st Coat Painting6,914
2nd Coat Painting500
Repair Wall Surficed (routine)350
Texture Walls (routine)350

TOTAL PRICE FOR PROJECT: $0.00