This document contains a past performance questionnaire for a contractor proposing for an Indian Health Service construction contract, as well as details of Federal Contract Opportunity Number 75H70122R00079. The construction project is for installing dry coolers at the Quentin N. Burdick Memorial Healthcare Facility in North Dakota, with a period of performance of 230 calendar days from notice to proceed. The contract type will be firm fixed price. The solicitation is set aside for small businesses as a 100% small business opportunity under NAICS code 238220 with a size standard of $16.5 million. Offerors must submit quotes electronically by the due date specified in the solicitation. Award will be based on lowest price technically acceptable to the government.

View the file

Other files

File Type Posted
B05 Amendment 4.pdf PDF
B05 Amendment 3.pdf PDF
B05 Amendment 2.pdf PDF
B05 Amendment 1.pdf PDF
Attachment 7 WH347 PAYROLL.pdf PDF
Attachment 2 Combined Drawings.pdf PDF
Attachment 3 Self Performed Calculation Sheet.docx DOCX document
Attachment 8 Release of Claims.pdf PDF
Attachment 1 Wage Determination ND20220029.pdf PDF
Attachment 5 Technical Experience Offeror Worksheet.docx DOCX document
B01 75H70122R00079.pdf PDF
Attachment 4 Supporting Price Detail.xlsx XLSX spreadsheet
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 6 PAST PERFORMANCE QUESTIONNAIRE

Instructions to client:

The contractor is proposing for a construction contract with Indian Health Service https://www.ihs.gov/ You are requested to complete this form, sign, and return it to the contractor so it may be submitted with their proposal.

PART I CONTRACT INFORMATION (Contractor to complete)

Contractor Name:

Project Title

Award Value

Period of Performance

Prime Contractor or Subcontractor
☐ Prime ☐ Subcontractor

Agency or Entity Name and Address

PART II PERFORMANCE INFORMATION (Client to complete)

Name / Title

Phone #

Email Address

Contract Type

Signature

Instructions: Please select the adjective rating that best reflects your evaluation of the contractor’s performance. See Part III for rating guidance.

Category
Exceptional
Good
Satisfactory
Marginal
Unsatisfactory
N/A

Quality

Schedule

Cost Control

Management

Small Business

☐☐☐☐☐☐
Regulatory Compliance
☐☐☐☐☐☐
Comments (expand as needed)

PART III RATING GUIDANCE

RATING
DEFINITION
NOTE
(E) Exceptional
Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(G) Good
Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory
Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative.