This solicitation requests proposals for improvements to the parking lot at Building 729 at Tyndall Air Force Base in Florida. The goal of the project is to address stormwater ponding issues in the rear of the building by assuring adequate drainage from the parking lot onto Suwannee Road. Proposals are due by March 13, 2023 at 2:00 PM Central Standard Time.
The solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses. A pre-bid site visit will take place on February 22, 2023 at 9:00 AM at the base visitor's center parking lot. Attendees are limited to two personnel per prime contractor. Names must be provided by February 14 for base access. Questions regarding the solicitation are due by February 28 at 1:00 PM Central Standard Time. The Department of the Air Force Air Combat Command is the issuing agency.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LEGEND
‐ ELEVATION LIDAR
‐ ELELVATION DERIVED
‐ (E) DESIGN FLOW
‐ (E) CROWN / FLOW
‐ PONDING / LOW AREA
28.24
2X.XX
SANDBOX
EXERCISE AREA
PROBLEM STATEMENT:
Up to 6” of storm water ponding in rear of BLDG 729 is reported as a hazard for users when walking from POV’s to doors/ramps entering the building – see blue ellipses below. The parking lot relies on sheet flow to Suwannee Rd. for all drainage. Future Zone 4 work will address some lacking drainage but does not improve or add any conveyance to the subject BLDG 729 area.
PROJECT INTENT:
The goal of this project is to assure adequate drainage from the B729 parking lot onto Suwannee Road where it will then sheet flow NE and SW into new Zone 4 drain inlets and infrastructure.
To assure this drainage, additional fall will be required.
LEGACY:
BLDG 729 interior has been recently remodeled, the addition of an exercise area and volleyball court (sandbox) which both have a concrete curbs preventing any sheet flow from parking lot rear toward HWY 98 and the previously used retention pond(s), permeable area was further reduced by the exercise area which is rubberized mat over concrete and is covered by a blue tent/roof. The original parking lot appears to have been crowned and provided drainage around the building (left/right) to Suwannee Rd. Over time it appears there has been some settlement and erosion which further contribute to the ponding problem. Survey data is very limited, design docs from the previous remodel are dated in 2017, elevation of that drawing is nearly one foot different from current LIDAR data available to me via the GOVT GIS system – that LIDAR data is used for the purpose of this evaluation and report. Elevation datum/data used for Zone 4 appears to be 1’ above lidar datum, compatibility will be confirmed prior to any improvements.
NOTES:
Limits of roadway construction (Zone 4) might minimize the area and scope of this project but should be ignored for quantity takeoffs used for this bid. Contractors should be encouraged to bring survey equipment to the pre-bid site walk.
POND
POND
BLDG 729 – 839 SUWANNEE ROAD ‐ STORM WATER DRAINAGE
OVERVIEW
LIMITS OF ZONE 4
ROADWAY
CONSTRUCTION (TYP)
(E) Drainage
EOD BLDG STORM DRAINAGE
XLWU23‐4011