Attachment 6 AF66 Template.xls
XLS spreadsheet 140 KB Posted
- Attached to
- Handyman IDIQ - Beale AFB - Amendment 0001 - Bid Opening Ceremony Update Federal contract opportunity
- Solicitation number
- FA468621B0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Initial SF 1409 Beale AFB Handyman.pdf | ||
| Attch 12 Site Map.pdf | ||
| FA468621B0001 Amendment 0001.pdf | ||
| Attch 9.2 Seed Project SON Revised.pdf | ||
| Attch 11 RFIs and Responses.pdf | ||
| Attachment 7 AF3000 Template.pdf | ||
| Attachment 1 Handyman SOW.pdf | ||
| Solicitation - FA468621B0001.pdf | ||
| Attachment 3 Bonding Information Request.pdf | ||
| Attachment 4 Mandatory Carpet Policy.pdf | ||
| Attachment 8 Wage Determinations.pdf | ||
| Attachment 5 NAF General Provisions.pdf | ||
| Attachment 9.1 Seed Project FOPR.pdf | ||
| Attachment 9.2 Seed Project SON.pdf | ||
| Attachment 9.3 Seed Project Price Worksheet.xls | XLS spreadsheet | |
| Attachment 2 Beale DCG.pdf | ||
| Attachment 10 EAL for Base Access.xls | XLS spreadsheet |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal 1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT NAME | SOLICITATION /CONTRACT NUMBER | |||||||||||||||||||
| BAEY XXXXX | PAX Terminal Repair and Renovation | FA4686-17-D-000X-00XX | ||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||
| LINE NUMBER | Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal. | CERTIF. OF COMPLIANCE | SHOP DRAWINGS | COLOR SELECTION | MANUFATURUR'S RECOMMENDATION | CATALOG DATA | O&M RECOMMENDATIONS | CALCULATIONS | WARRANTY | DRAWINGS | REPORT | TEST RESULTS | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL | |
| GENERAL | ||||||||||||||||||||||
| Project Specific Form 66 | X | NTP + 3 | ||||||||||||||||||||
| Construction Schedule | X | NTP + 7 | ||||||||||||||||||||
| TCN Schedule (electronic required, hard copy optional) | X | NTP + 7 | ||||||||||||||||||||
| Contractor's Health, Safety, and Environment Plan | X | NTP + 7 | ||||||||||||||||||||
| Contractor's QA/QC Plan | X | NTP + 7 | ||||||||||||||||||||
| Copy of Engineering License(s) of person or consultancy responsible for design | X | Design | ||||||||||||||||||||
| DESIGN | ||||||||||||||||||||||
| All submissions to be provided in hard copy and electronically unless noted otherwise. 65%, 95%, and 100% Design Documents to include: | X | NTP + 21 (65%) NTP + 35 (95%) NTP + 45 (100%) | ||||||||||||||||||||
| Roof Drain Storm Sewer Tie In | X | NTP+45 | ||||||||||||||||||||
| Wind Loading Diagrams for Roof | X | X | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||
| Structural Connection Details for Shear Walls | X | X | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||
| Structural Connection Details for Framing | X | X | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||
| Structural Connection Details for Blast Resistant Doors & Windows | X | X | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||
| HVAC Calculations | X | X | NTP+45 | |||||||||||||||||||
| Sprinkler Layout | X | NTP+45 | FPE or NICET Tech stamp req'd | |||||||||||||||||||
| Fire Alarm Layout | X | NTP+45 | FPE or NICET Tech stamp req'd | |||||||||||||||||||
| Communications Layout | X | NTP+45 | ||||||||||||||||||||
| Technical Specifications | X | NTP+45 | PE STAMP REQ'D, NO HARD COPY | |||||||||||||||||||
| DEMOLITION/ASBESTOS | ||||||||||||||||||||||
| Demolition Plan | X | X | X | NTP+45 | ||||||||||||||||||
| Asbestoes Plan | X | X | X | NTP+45 | ||||||||||||||||||
| CIVIL | ||||||||||||||||||||||
| Soil Gradations for each type of soil used | X | X | Install -7 | |||||||||||||||||||
| Moisture-Density curve for each type of soil used | X | Install -7 | ||||||||||||||||||||
| Nuclear Densometer Calibration | X | Install -7 | ||||||||||||||||||||
| Soil Compaction Test Results for Utilities, Facilities & Pavement | X | X | Install+7 | |||||||||||||||||||
| Storm Pipe | X | Design+14 | ||||||||||||||||||||
| ARCHITECTURAL | ||||||||||||||||||||||
| Blast Resistant Doors and Frames | X | X | X | NTP+45 | ||||||||||||||||||
| Door Hardware | X | X | NTP+45 | Hardware Schedule | ||||||||||||||||||
| Gypsum Board-Type X | X | X | NTP+45 | |||||||||||||||||||
| Gypsum Board-Type X-Mold Resistant | X | X | NTP+45 | |||||||||||||||||||
| Wood Paneling | X | X | X | NTP+45 | ||||||||||||||||||
| Wood Chair Rails | X | X | X | NTP+45 | ||||||||||||||||||
| Wood Ceiling Cloud | X | X | X | NTP+45 | ||||||||||||||||||
| Sheet Vinyl Flooring | X | X | X | NTP+45 | ||||||||||||||||||
| Rubber Base | X | X | X | NTP+45 | ||||||||||||||||||
| Ceiling Tiles | X | X | X | NTP+45 | ||||||||||||||||||
| Blast Resistant Window | X | X | X | X | X | X | X | NTP+45 | ||||||||||||||
| Glazing | X | X | X | NTP+45 | ||||||||||||||||||
| Solid Surface Countertops | X | X | X | X | NTP+45 | |||||||||||||||||
| Kitchen Cabinets | X | X | X | X | X | NTP+45 | ||||||||||||||||
| Garbage Disposal | X | X | NTP+45 | |||||||||||||||||||
| Interior Paint | X | X | X | NTP+45 | ||||||||||||||||||
| Exterior Paint | X | X | X | NTP+45 | ||||||||||||||||||
| Roofing System | X | X | X | X | X | NTP+45 | ||||||||||||||||
| Roofing Insulation | X | X | X | X | X | X | NTP+45 | |||||||||||||||
| Roof Drains | X | X | X | X | X | NTP+45 | ||||||||||||||||
| Scuppers | X | X | NTP+45 | |||||||||||||||||||
| Coping | X | X | NTP+45 | |||||||||||||||||||
| Flashing | X | X | NTP+45 | |||||||||||||||||||
| STRUCTURAL | ||||||||||||||||||||||
| Reinforcing Steel Drawings | X | NTP+45 | ||||||||||||||||||||
| Concrete Mix Design | X | X | NTP+45 | |||||||||||||||||||
| Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints | X | X | X | X | X | NTP+45 | ||||||||||||||||
| Concrete Field Test Results | X | NTP+45 | ||||||||||||||||||||
| Reinforcing Steel Mill Certifications | X | X | NTP+45 | |||||||||||||||||||
| Slump Test results & Concrete Truck Tickets (per truck) | X | Test + 3 | ||||||||||||||||||||
| 7-Day Concrete Compressive Strength Test | X | X | Test + 3 | |||||||||||||||||||
| 28-Day Concrete Compressive Strength Test | X | X | Test + 3 | |||||||||||||||||||
| Blast Resistant Window Attachment | X | X | Design + 14 | |||||||||||||||||||
| MECHANICAL | ||||||||||||||||||||||
| HVAC Balancing | X | Design+14 | ||||||||||||||||||||
| Registers | X | X | Design+14 | |||||||||||||||||||
| Dampers | X | X | Design+14 | |||||||||||||||||||
| Ductwork | X | Design+14 | ||||||||||||||||||||
| Sprinkler Heads | X | X | NTP+14 | |||||||||||||||||||
| Ductwork Pressure Drops Before Removal | X | X | NTP+14 | |||||||||||||||||||
| Ductwork Pressure Drops After Installation | X | X | NTP+14 | |||||||||||||||||||
| Ductwork | X | X | NTP+14 | |||||||||||||||||||
| Controls | X | X | Design+14 | |||||||||||||||||||
| Piping | X | Design+14 | ||||||||||||||||||||
| Heaters | X | X | Design+14 | |||||||||||||||||||
| Valves | X | X | Design+14 | |||||||||||||||||||
| Pumps | X | X | Design+14 | |||||||||||||||||||
| Thermal Insulation | X | X | Design+14 | |||||||||||||||||||
| Instrumentation | X | X | Design+14 | |||||||||||||||||||
| PLUMBING | ||||||||||||||||||||||
| Plumbing Fixtures | X | X | X | X | X | NTP+45 | ||||||||||||||||
| Piping for Water | X | X | NTP+45 | |||||||||||||||||||
| Garbage Disposal | X | X | NTP+45 | |||||||||||||||||||
| Waste and Vent | X | X | X | X | NTP+45 | |||||||||||||||||
| INTERIOR ELECTRICAL | ||||||||||||||||||||||
| Cables(electrical,comm,fire alarm) | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||||
| Switches | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||||
| Receptacles | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||||
| Panels | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||||
| Breakers | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||||
| Conduits | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||||
| Lighting Fixtures | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||||
| Lighting UPS units (if req'd) | X | X | X | X | X | X | X | NTP+45 | ||||||||||||||
| Communication System Outlets(incl jacks) | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||||
| Communications patch panels | X | X | X | X | X | X | X | NTP+45 | ||||||||||||||
| PA Speakers | X | X | X | X | X | X | X | NTP+45 | ||||||||||||||
| Fire Alarm Devices (All) | X | X | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||
| Occupancy Sensors | X | X | X | X | X | X | X | X | NTP+45 | |||||||||||||
| Power Packs | X | X | X | X | X | X | X | NTP+45 | ||||||||||||||
| EXTERIOR ELECTRICAL | ||||||||||||||||||||||
| Conduits | X | X | NTP+14 | |||||||||||||||||||
| Transformer | X | X | X | X | X | X | NTP+14 | |||||||||||||||
| Meter | X | X | X | X | X | NTP+14 | ||||||||||||||||
| Cables(med & low voltage) | X | X | X | X | NTP+14 | |||||||||||||||||
| Switches | X | X | NTP+14 | |||||||||||||||||||
| Contactors | X | X | X | NTP+14 | ||||||||||||||||||
| Panels | X | X | NTP+14 | |||||||||||||||||||
| Breakers | X | X | NTP+14 | |||||||||||||||||||
| Controller | X | X | X | NTP+14 | ||||||||||||||||||
| Junction Cabinet | X | X | X | X | X | NTP+14 | ||||||||||||||||
| Heating Mat | X | X | X | X | X | X | X | X | NTP+14 | |||||||||||||
| CLOSEOUT | ||||||||||||||||||||||
| O&M maint data and maint manuals & Manufacturer's Warranty for Communications Equipment | X | X | X | Install + 4 | ||||||||||||||||||
| Factory and Field Test Certificates, Logs and Test Results | X | Before Acceptance | ||||||||||||||||||||
| Inspection Logbook | X | Before Acceptance | ||||||||||||||||||||
| As Builts (electronic in AutoCAD and hard copies on Mylar) | X | Final + 7 |