About this file
This document appears to be a detailed user story for a federal system called the Technical Information Management System (TIMS) that is used to submit decommissioning expenditures reports to the Bureau of Safety and Environmental Enforcement (BSEE).
The key details are:
- External users can use TIMS Web to create and submit decommissioning expenditure reports, including details on permanently plugged wells, temporarily abandoned wells, platform/facility removals, site clearances, and pipeline segment decommissioning.
- Required metadata includes lease number, area code, block number, complex ID, well API number, and segment number.
- Submittal details required include date, initial/revision indicator, company name and number, decommissioning activity type, duration, associated assets, and various flags (e.g. multi-asset, turnkey, casing cut).
- Cost details are required, broken out by transportation, location, contract services, and other decommissioning costs.
- Internal users can review the submittals, update certain data, and view associated end-of-operations reports.
- The document describes functional requirements for the TIMS system to support these decommissioning expenditure reporting capabilities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_3_User_Stories_for_Idle_Iron_1.docx | DOCX document | |
| Attachment_6_User_Stories_for_Cost_Report_Tracker_1.docx | DOCX document | |
| Decommissioning_Project_Request_for_Information_1.docx | DOCX document | |
| Attachment_4_User_Stories_for_Terminated_Lease_1.docx | DOCX document | |
| Attachment_2_Flowchart_Decision_Descriptions_1.docx | DOCX document | |
| Attachment_1_Cost_Estimating_Flowcharts_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BSEE Decommissioning User Stories Expenditures As an External User, I would like to submit Decommissioning Expenditures, in accordance with NTL No. 2017-N02, so that I am in compliance with the NTL and 30 CFR 250.1704(i).
· Using TIMS Web, Create and Submit the submittal Decom Expenditure Reports Required by Regulation/NTL (DECOM_EXP_REP_REQ).
· The submittal uses the following metadata: LEASE_NUM, AREA_CODE, BLOCK_NUMBER, COMPLEX_ID_NUM (Structure Number), WELL_API_NUMBER, SEGMENT_NUM
· Enters the required/optional data for the submittal.
· Enters the decommissioning expenditures summary, as described in the Decommissioning Expenditures Summary user story. This will be an extended application of TW Submittals.
As an External User, I would like to enter the decommissioning expenditures summary to submit to BSEE for each permanently plugged well (PA), temporary abandoned wells with a SCP in place, platform or facility removed, site cleared, and pipeline segment decommissioned, so that I am in compliance with 30 CFR 250.1704(i).
· All data submitted is proprietary data.
· Assign Date of Submission to BSEE the date of submission (submitted date).
· Auto-populate when the external user submits the request.
· This will be read only.
· Indicate whether this is the Initial submission or a Revision.
· Initial would be indicated with an “I”.
· Revision will include an “R” followed by a number.
· The number can be 2 digits
· Enters Submittal Id Number
· Assign Company Name and Number based on the company the user is representing.
· Display Company Name
· Display Company Number
· Select Decommissioning Activity Type (PR, PA, SCV, PL)
· PR: Platform and Facility removal (including PLETS (pipeline end terminations), PLEMS (pipeline end manifolds), subsea templates, etc., per 30 CFR 250.1700(c)
· PA: Well abandonment
· SCV: Site clearance and verification
· PL: Pipeline segment decommissioning
· Indicate whether the decommissioning activity is part of a multiple asset decommissioning project.
· Multi-Asset Activity Flag (Y/N)
· Indicate whether a majority of the decommissioning expenditures for the reported asset decommissioning were incurred under a “turnkey” type contract(s).
· Turnkey Contracting Flag (Y/N)
· If the Decommissioning Activity Type is PA, indicate whether casing cutting and removal remains to be performed.
· Permanently Plugged Well – Casing Cut (Y/N)
· If the decommissioning activity type is PR, SCV, PL, a response is not required – indicating this value can be nulled.
· Do not request this information.
· Indicate whether an asset has been partially decommissioned.
· Partially Decommissioned Assets (Y/N)
· If the Decommissioning Activity Type is PR, indicate whether the structure removal operations were conducted as part of a Rigs to Reefs program.
· Rigs to Reefs Flag (Y/N)
· If Decommissioning activity type is PA, SCV or PL, a response is not required, indicating this value can be nulled.
· Do not request this information.
· If the Decommissioning Activity Type is PL, indicate whether the pipeline segment was removed as opposed to being decommissioned in place.
· Pipeline Segment Removal Flag (Y/N)
· If Decommissioning activity type is PA, PR, SCV, a response is not required, indicating this value can be nulled.
· Do not request this information.
· If the Decommissioning Activity Type is PL, indicate whether material flushed from a pipeline segment was disposed onshore or not.
· Onshore Disposal of Material Flushed from Pipeline Flag (Y/N)
· If Decommissioning activity type is PA, PR, SCV, a response is not required, indicating this value can be nulled.
· Do not request this information.
· Enter the approximate duration of the decommissioning activity
· Activity Duration (number of days) – 3 digits
· Enter the Asset that is being decommissioned based on the Decommissioning Activity Type
· PR: Platform and Facility removal
· Enter Complex Id Number and
· Enter Structure Number
· Complex Id Number and Structure Number are required.
· Verify the Complex Id Number entered
· If the Complex Id Number and Structure Number do not exist, display a message “Complex id Number and Structure Number are not found.”
· Display Surface Area Code, Surface Block Number, and Platform Name based on the Complex Id Number entered.
· Note: There are cases where the Complex Id Number and Structure Number are optional. This would include PLETS (pipeline end terminations), PLEMS (pipeline end manifolds), subsea templates.
· PA: Well abandonment
· Enter API Number (12 digits)
· API Number must be 12 digits
· Verify the API Number entered
· If the API Number does not exist, display a message “API Number is not found.”
· Display the following data for the API Number entered:
· Display Well Name, Surface Area Code, and Surface Block Number
· Display Well Name, Bottom Area Code and Bottom Block Number
· SCV: Site clearance and verification
· Enter Complex Id Number
· Enter Structure Number
· If Complex Id Number is entered, Structure Number is required.
· Verify the data entered
· If the Complex Id Number and Structure Number do not exist, display a message “Complex id Number and Structure Number are not found.”
· Display Surface Area Code, Surface Block Number and Platform Name based on the Complex Id Number entered.
· Enter API Number (12 digits)
· Tool Tip: If Well is not structurally associated with a platform.
· If API Number is entered, it must have 12 digits.
· Verify the data entered
· If the API Number does not exist, display a message “API Number is not found.”
· Display the following data for the API Number entered:
· Display Well Name, Surface Area Code and Surface Block Number
· Display Bottom Area Code and Bottom Block Number
· PL: Pipeline segment decommissioning
· Enter Pipeline Segment Number
· Verify the Pipeline Segment Number entered
· If the Pipeline Segment Number does not exist, display a message “Pipeline Segment Number is not found.”
· Display the Origination Area Code and Origination Block Number associated with the Pipeline Segment entered.
· Enter Transportation and Staging Costs
· Enter Location Costs
· Enter Contract Services, Diving and Service Unit Costs
· Enter Other Decommissioning Related Costs
· Calculate Decommissioning Cost Total
· Add the following values
· Transportation and Staging Costs
· Location Costs
· Contract Services, Diving and Service Unit Costs
· Other Decommissioning Related Costs
· Indicate whether conductor cutting and removal costs are included as part of PA activity or a PR activity.
· Enter Conductor Removal Cost Activity Association (PA, PR, NULL)
· Only display if decommissioning type is PA, PR
· Enter Number of Conductors Removed
· Value can be null
· Enter Conductor Removal Cost
· Value can be null
· Enter Contact Information of Individual Certifying Reported Costs
· Name
· Title
· Phone Number
· Email Address
· Note: This will be captured outside of Submittal Contact
· Enter Remarks
· Optional As an Internal User, I would like to capture Review information associated with the decommission expenditures submittal, so that I can capture the comments associated with the submittal.
· Reviewed By
· Auto-populate based on the user logged in
· Review Date
· Auto-populate with SysDate
· Select Review Status
· Accepted, Excluded, Returned, Superseded, Tentative Acceptance, Under Review, Calculated, Shared Trench, Combined Segs, Synthetic Segment, Other
· Remarks As an Internal User, I would like to modify certain data submitted by the operator within the Expenditure application.
· The data to be modified includes the following:
· Multi-Asset Activity Flag
· Turnkey Contracting Flag
· Casing Cut
· Partially Decommissioned Assets
· Rigs to Reef Flag
· Pipeline Segment Removal Flag
· Onshore Disposal of Material Flushed from Pipeline Flag As an Internal User, I would like to view the End of Operations Report (EOR) associated with the well, so that I can view which EORs has been submitted. This information can be retrieved from eWell.
· Display the following data form the permit:
· Permit type
· Submitted Date
· Current Status
· Current Status Date
· Plug Top MD
· Plug Top TVD
· Plug Type Migration:
· Attachments into EDMS from G Drive
· Historical data prior to TW Submittals currently stored in the Access Database need to be migrated into Submittals and documents from G Drive into EDMS