Attachment 5_FXSB 23-1040S LIQDG.pdf

PDF 187 KB Posted

Attached to
AMENDED 2_ HAZMAT Survey for B10435 Federal contract opportunity
Solicitation number
FA500023Q0073
Issued by
Department of the Air Force Pacific Air Forces

About this file

This document contains a determination to incorporate liquidated damages into a federal solicitation for a hazardous materials survey at Joint Base Elmendorf-Richardson in Alaska. Liquidated damages for the first and last day of unexcusable delay are established at $692.84 per day, while liquidated damages for each additional day of delay are set at $450.71 per day. These rates were calculated based on hourly rates derived from military and civilian pay tables, as well as engineering rates provided by the 673rd Civil Engineering Squadron project engineer. The liquidated damages are considered fair and reasonable forecasts of probable damages to compensate the government for untimely performance.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rate Hour(s) Daily Rate $63.29 2 $126.58

Project Engineer $80.07 2 $160.14 Chief of Engineering $106.37 1 $106.37

Total $393.09

Rate Hour(s) Daily Rate $63.29 2 $126.58

Project Engineer $80.07 2 $160.14 Total $286.72

Rate Hour(s) Daily Rate Contract Administrator $51.46 2 $102.92 Contracting Officer $61.07 2 $122.14

$74.69 1 $74.69 Total $299.75

Rate Hour(s) Daily Rate Contract Administrator $51.46 2 $102.92 Contracting Officer $61.07 1 $61.07

Total $163.99

E. Total CONS & CES Rates for First and Last Day of Delay: $692.84 F. Total CONS & CES Rates for Other than the First and Last Day: $450.71

Inspector

Legal

D. Contracting Costs for Each Day of Delay Other Than First and Last Day:

B. Civil Engineering Cost per Day of Delay Other Than First and Last:

C. Contracting Costs for First and Last Day of Delay:

Determination to Incorporate Liquidated Damages

This Determination and Findings is based upon the requirements of FAR 11.501(a) & (b), 11.503(b) and 52.211-12.

The Findings are as follows:

DEPARTMENT OF THE AIR FORCE

673d Contracting Squadron/PKA

Joint Base Elmendorf-Richardson, Alaska 99506

FINDINGS

Inspector

A. Civil Engineering Cost for First and Last Day of Delay:

2. IAW FAR 11.503(b), the contract includes the liquidated damages clause 52.211-12. Liquidated damages are to be specified on each order.

4. IAW FAR 11.501(b), Liquidated damages are not punitive and are not negative performance incentives. Liquidated damages are used to compensate the Government for probable damages. Therefore, the liquidated damage rates used are a reasonable forecast of just compensation for the harm that is caused by untimely performance. The liquidated damage rates are determined as follows:

3. IAW FAR 11.501(a), the Contracting Officer has considered the potential impact on pricing, competition, and contract administration before using a liquidated damages clause. Timely performance is so important that the Government may reasonably expect to suffer damage if performance is delinquent, and the extent or amount of the damage would be difficult to estimate accurately or prove.

1. The 673 Civil Engineering Squadron has a requirement for FXSB 23-1040S Replace HAZMAT Survey B10435

DETERMINATION AND FINDINGS

The 673 Civil Engineering Squadron has a requirement for FXSB 23-1040S Replace HAZMAT Survey B10435

D&F for Liquidated Damges Page 1 of 2

E. Additional Damages (If necessary): $0.00

5. Hourly rates were derived from the pay tables for each relevant position affected by the delay.

A. Military Rates were derived from AFI 65-503, TABLE A20-2. FY21 Military Rates last updated March 2021.

Capt (O-3) $78.07 MSgt (E-7) $59.73 SrA (E-4) $36.42 1Lt (O-2) $65.91 TSgt (E-6) $52.00 A1C (E-3) $28.93 2Lt (O-1) $52.55 SSgt (E-5) $44.09

B. Civilian Rates were derived from AFI 65-503, TABLE A26-1. FY22 Civilian Rates last updated December 2021.

GS-13 $74.69 GS-11 $51.46 GS-07 $36.42

GS-12 $61.07 GS-09 $42.42

Liquidated damages for the first and last day of unexcusable delay are established at the per day rate of $692.84 .

Liquidated damages for each additional day of unexcusable delay are established at the per day rate of $450.71 .

The liquidated damages computed above are considered fair and reasonable based on our forecast of probable damages.

TERRELL A. SINGLETON, TSgt, USAF Contracting Officer

C. Engineering rates were provided by the 673 CES Project Engineer and are filed with the requirements package.

On the basis of the above findings and in accordance with FAR 11.501, I hereby determine that it is in the best interest of the Government to include liquidated damages in the subject solicitation and later award.

DETERMINATION

D&F for Liquidated Damges Page 2 of 2

2023-07-14T09:22:16-0800
SINGLETON.TERRELL.ARRON.1366954283

File details come from the government source that posted it. Updated .