About this file

This document contains the Technical Specifications for the decommissioning of an Oil Water Separator (OWS), Underground Storage Tank (UST), and Fuel Line at the Joseph Stewart County Park in Jackson County, Oregon. The work is being solicited by the Oregon Parks and Recreation Department (OPRD) through Invitation to Bid (ITB) Contract Number 9412. The work includes site preparation, deconstruction and removal of the OWS, 260-gallon waste oil UST, and fuel line, and site restoration. No specific quantities are provided. The work is to be completed by June 2023.

The Technical Specifications outline the requirements for the tank cleaning, removal, transportation, and disposal of the OWS and UST and associated piping and materials. Soil sampling is required to assess potential contamination. The contractor is responsible for all permitting, notifications, and fees. Payment will be made as a lump sum for the mobilization/overhead, site preparation, and tank/piping deconstruction and removal work.

View the file

Other files

File Type Posted
OregonBuys Sign-in Sheet Completed.docx DOCX document
S-63400-00007260 Intent to Award.docx DOCX document
Attachment 5. Sample Services Contract.pdf PDF
S-63400-00007260 ITB Trade Services.pdf PDF
5664-0 Sole Source Determination~1.pdf PDF
S-63400-00007260 BID TABULATION.docx DOCX document
ITB S-36400-00007260 Question and Answer .docx DOCX document
Meeting Agenda.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Oregon Parks and Recreation

Department

TECHNICAL SPECIFICATIONS

For

Oil Water Separator, Underground Storage Tank and Fuel Line Decommissioning at

Joseph Stewart County Park

Project Number: #009412 Contract Number: 9412

June 2023

Prepared by:

PBS Engineering and Environmental Inc.

4412 S Corbett Avenue Portland, OR 97239

Oregon Parks and Recreation Department

725 Summer St NW, Ste. C Salem, OR 97301

Oregon Parks and Recreation Department PBS Engineering and Environmental Inc.

Joseph Stewart County Park 74270.005

June 2023 Page i of i

TECHNICAL SPECIFICATIONS

for

Oil Water Separator, Underground Storage Tank and Fuel Line Decommissioning at Joseph Stewart County Park

Jackson County, Oregon

Oregon Parks and Recreation Department

TABLE OF CONTENTS

SECTION 011100 - SUMMARY OF WORK

SECTION 012000 - PRICE AND PAYMENT PROCEDURES

SECTION 017000 - EXECUTION AND CLOSEOUT REQUIREMENTS

SECTION 026500 – UNDERGROUND STORAGE TANK REMOVAL

SECTION 310513 - SOILS FOR EARTHWORK

SECTION 310516 - AGGREGATES FOR EARTHWORK

SECTION 311000 - SITE CLEARING

SECTION 312316 – EXCAVATION

SECTION 312323 – FILL

SECTION 312500 - EROSION AND SEDIMENTATION CONTROLS

SECTION 321123 - AGGREGATE BASE COURSES

SECTION 321216 - ASPHALT PAVING

June 2023 Section 011100 – Summary of Work Page 1 of 65 Specifications

SECTION 011100 - SUMMARY OF WORK

PART 1 – GENERAL

1.1 SUMMARY

A. These Specifications are subject to the administrative and procedural requirements specified in the Invitation to Bid (“ITB”) State of Oregon Terms and Conditions.

1.2 DESCRIPTION OF WORK

A. Decommission the Oil Water Separator (OWS), Underground Storage Tank (UST), and Fuel Line by removal and bring site back to safe and usable conditions.

B. The Work shall be as shown on the Plans and as specified herein at the following location(s):

1. Joseph Stewart County Park

C. Contractor shall furnish all permits, labor, equipment, tools, supervision, materials, and incidentals required to complete the Work in accordance with the Plans, Specifications and terms and conditions. Also refer to the Invitation to Bid (“ITB”) and the Attachments for additional requirements and information. Work includes, but is not limited to, the following:

1. Site preparation and protection.

2. Deconstruction of OWS, UST, and fuel line materials.

3. Removal of all deconstructed materials.

4. Refer to Plans and Specifications for other items.

D. Specific items furnished by Owner:

1. None.

E. Project is for the Oregon Parks and Recreation Department (“OPRD”), herein referred to as Owner.

June 2023 Section 011100 – Summary of Work Page 2 of 65

F. The Owner’s Authorized Representative, herein referred to as Project Manager is:

Nathan Seable, Rogue MU Manager 3792 North River Gold Hill, OR 97525

(541) 415-2654 Email: Nathan.SEABLE@oprd.oregon.gov

1.03 CONSTRUCTION STAKEOUT

A. The Contractor will be solely responsible for laying out the Work from the information shown on the Plans and the approved submittals, and no additional stakeout will be provided by the Project Manager.

1.04 SPECIFICATION LANGUAGE

A. Portions of the Specifications are written in imperative and streamlined form. This imperative language is directed to the Contractor, unless specifically noted otherwise.

The words “shall be” shall be included by inference where a colon (:) is used within sentences or phrases. Example: Aggregate: ASTM C33.

PART 2 – MATERIALS (not applicable)

PART 3 – EXECUTION (not applicable)

END OF SECTION

mailto:Nathan.SEABLE@oprd.oregon.gov

June 2023 Section 017000 – Execution and Closeout Requirements Page 3 of 65

SECTION 012000 - PRICE AND PAYMENT PROCEDURES

1.01 DESCRIPTION

A. All Payments shall be as provided according to the ITB’s Terms and Conditions.

B. If no item exists for a portion of the Work, include the costs in a related Item.

C. No separate payment will be made for any item that is not specifically set forth in the

ITB, and all costs therefore shall be included in the prices named in the ITB for the various appurtenant items of Work.

D. Payments to the Contractor will be made only for actual Work performed in accordance with Terms and Conditions and for Work actually performed under Change Orders.

E. Indirect costs, such as supervision and overhead, profit, and the Terms and Conditions, all shall be allocated to each item as applicable for Work defined in the item. No separate payment will be made to the Contractor for these items.

F. Bids will be made assuming there has been no release of petroleum hydrocarbons to the environment. This includes the OWS, UST, and fuel lines. Contractor is responsible for all Oregon Department of Environmental Quality or any other jurisdictional permits, notices, and fees.

1.02 ITEM MEASUREMENT AND PAYMENT

A. BID ITEMS:

1. Lump Sum:

a. Mobilization/Overhead: Payment for Mobilization shall be included in the lump sum.

b. Measurement for the work area preparation shall be included in the lump sum.

c. Work shall include full compensation for all labor, equipment and materials necessary to perform the specified Work, including:

1. Permitting (if required).

2. Execution and installation of protect site safety controls.

3. Regulatory notifications and reporting, along with applicable fees.

June 2023 Section 017000 – Execution and Closeout Requirements Page 4 of 65

d. Work shall also include full compensation for any and all other preparatory and other support work as needed to complete the specified work.

e. Deconstruction: Work shall include full compensation for all labor, equipment, and materials necessary to perform the specified Work, including:

1. Dismantling.

2. Removal of Oil Water Separator.

3. Removal of Underground Storage Tank.

4. Removal of Fuel Line.

5. Hauling and disposal of any/all waste materials and fluids.

6. Fill areas left open and unsafe to public.

PART 2 – MATERIALS (not applicable)

PART 3 – EXECUTION (not applicable)

June 2023 Section 017000 – Execution and Closeout Requirements Page 5 of 65

SECTION 017000 - EXECUTION AND CLOSEOUT REQUIREMENTS

1.1 SECTION INCLUDES

A. Examination.

B. Preparation.

C. Coordination of Owner's portion of the Work.

D. Execution.

E. Cutting and patching.

F. Protecting installed construction.

G. Testing, adjusting, and balancing.

H. Closeout procedures.

I. Project record documents.

J. Final cleaning.

1.2 EXAMINATION

A. Verify that existing Site conditions and substrate surfaces are acceptable for subsequent Work.

B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Verify that utility services are available with correct characteristics and in correct locations.

1.3 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance according to manufacturer's instructions.

B. Seal cracks or openings of substrate prior to applying next material or substance.

June 2023 Section 017000 – Execution and Closeout Requirements Page 6 of 65

C. Apply manufacturer-required or -recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.

1.4 COORDINATION OF OWNER'S PORTION OF THE WORK

A. Site Access: Provide access to Project site for Owner's construction personnel.

1. Provide temporary facilities required for Owner-furnished, Contractor-installed products.

B. Coordination: Coordinate construction and operations of the Work with Work performed by Owner's construction personnel.

1. Construction Schedule: Inform Owner of Contractor's preferred construction schedule for Owner's portion of the Work. Adjust construction schedule based on a mutually agreeable timetable. Notify Owner if changes to schedule are required due to differences in actual construction progress.

2. Preinstallation Conferences: Include Owner's construction personnel at preinstallation conferences covering portions of the Work that are to receive Owner's Work. Attend preinstallation conferences conducted by Owner's construction personnel if portions of the Work depend on Owner's construction.

1.5 EXECUTION

A. Comply with manufacturer's installation instructions, performing each step in sequence. Maintain one set of manufacturer's installation instructions at Project Site during installation and until completion of construction.

B. When manufacturer's installation instructions conflict with Contract Documents, request clarification from Owner before proceeding.

C. Verify that field measurements are as indicated on approved Shop Drawings or as instructed by manufacturer.

D. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

1. Secure Work true to line and level and within specified tolerances, or if not specified, industry-recognized tolerances.

June 2023 Section 017000 – Execution and Closeout Requirements Page 7 of 65

2. Physically separate products in place, provide electrical insulation, or provide protective coatings to prevent galvanic action or corrosion between dissimilar metals.

3. Exposed Joints: Provide uniform joint width and arrange to obtain best visual effect. Refer questionable visual effect choices to Owner for final decision.

1.6 CUTTING AND PATCHING

A. Employ skilled and experienced Installers to perform cutting and patching.

B. Submit written request in advance of cutting or altering elements affecting the following:

1. Structural integrity of element.

2. Integrity of weather-exposed or moisture-resistant elements.

3. Efficiency, maintenance, or safety of element.

4. Visual qualities of sight-exposed elements.

5. Work of Owner or separate Contractor.

C. Execute cutting, fitting, and patching including excavation and fill to complete Work and to accomplish the following:

1. Fit the several parts together, to integrate with other Work.

2. Uncover Work to install or correct ill-timed Work.

3. Remove and replace defective and nonconforming Work.

4. Remove samples of installed Work for testing.

5. Provide openings in elements of Work for penetrations of mechanical and electrical Work.

D. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit.

1.7 PROTECTING INSTALLED CONSTRUCTION

A. Protect installed Work and provide special protection where specified in individual Specification Sections.

June 2023 Section 017000 – Execution and Closeout Requirements Page 8 of 65

B. Provide temporary and removable protection for installed products. Control activity in immediate Work area to prevent damage.

C. Prohibit traffic from landscaped areas.

1.8 TESTING, ADJUSTING, AND BALANCING

A. Owner will appoint, employ, and pay for services of independent firm to perform testing, adjusting, and balancing.

B. Reports will be submitted by independent firm to Owner indicating observations, test results, and compliance or noncompliance with requirements of Contract Documents.

1.9 CLOSEOUT PROCEDURES

A. Prerequisites to Substantial Completion: Complete following items before requesting Certification of Substantial Completion, either for entire Work or for portions of Work:

1. Submit Project record documents, digital images of construction photographs, and other similar final record data in compliance with this Section.

2. Conduct inspection to establish basis for request that Work is substantially complete. Create comprehensive list (initial punch list) indicating items to be completed or corrected, value of incomplete or nonconforming Work, reason for being incomplete, and date of anticipated completion for each item. Include copy of list with request for Certificate of Substantial Completion.

3. Obtain and submit releases enabling Owner's full, unrestricted use of Project and access to services and utilities. Include certificate of occupancy, operating certificates, and similar releases from authorities having jurisdiction and utility companies.

4. Deliver tools, spare parts, extra stocks of material, and similar physical items to Owner.

5. Discontinue or change over and remove temporary facilities and services from Project Site, along with construction tools, mockups, and similar elements.

6. Perform final cleaning according to this Section.

June 2023 Section 017000 – Execution and Closeout Requirements Page 9 of 65

B. Substantial Completion Inspection:

1. When Contractor considers Work to be substantially complete, submit to Owner:

a) Written certificate that Work, or designated portion, is substantially complete.

b) List of items to be completed or corrected (initial punch list).

2. Within seven days after receipt of request for Substantial

Completion, Owner will make inspection to determine whether Work or designated portion is substantially complete.

3. Should Owner determine that Work is not substantially complete:

a) Owner will promptly notify Contractor in writing, stating reasons for its opinion.

b) Contractor shall remedy deficiencies in Work and send second written request for Substantial Completion to Owner.

c) Owner will reinspect Work.

4. When Owner finds that Work is substantially complete, Owner will:

a) Prepare Certificate of Substantial Completion on AIA G704 -

Certificate of Substantial Completion, accompanied by Contractor's list of items to be completed or corrected as verified and amended by Owner (final punch list).

b) Submit Certificate to Owner and Contractor for their written acceptance of responsibilities assigned to them in Certificate.

5. After Work is substantially complete, Contractor shall:

a) Allow Owner occupancy of Project under provisions stated in Certificate of Substantial Completion.

b) Complete Work listed for completion or correction within time period stipulated.

C. Prerequisites for Final Completion: Complete following items before requesting final acceptance and final payment.

June 2023 Section 017000 – Execution and Closeout Requirements Page 10 of 65

1. When Contractor considers Work to be complete, submit written certification that:

a) Contract Documents have been reviewed.

b) Work has been examined for compliance with Contract Documents.

c) Work has been completed according to Contract Documents.

d) Work is completed and ready for final inspection.

2. Submittals: Submit following:

a) Final punch list indicating all items have been completed or corrected.

b) Final payment request with final releases and supporting documentation not previously submitted and accepted.

c) Specified warranties, and other similar documents.

d) Accounting statement for final changes to Contract Sum.

e) If applicable, Contractor's affidavit of payment of debts and claims on AIA G706 - Contractor's Affidavit of Payment of Debts and Claims.

f) If applicable, Contractor affidavit of release of liens on AIA

G706A - Contractor's Affidavit of Release of Liens.

g) If applicable, Consent of surety to final payment on AIA G707 - Consent of Surety to Final Payment Form.

1.10 PROJECT RECORD DOCUMENTS

A. Maintain on Site one set of the following record documents; record actual revisions to the Work:

1. Drawings.

2. Specifications.

3. Contract

June 2023 Section 017000 – Execution and Closeout Requirements Page 11 of 65

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, and product data.

6. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Specifications: Legibly mark and record, at each product Section, description of actual products installed, including the following:

1. Manufacturer's name and product model and number.

2. Product substitutions or alternates used.

3. Changes made by Addenda and modifications.

D. Record Drawings: Legibly mark each item to record actual construction as follows:

1. Include Contract modifications such as Addenda, supplementary instructions, change directives, field orders, minor changes in the Work, and change orders.

2. Include locations of concealed elements of the Work.

3. Identify depth of buried utility lines and provide dimensions showing distances from permanent facility components that are parallel to utilities.

4. Dimension ends, corners, and junctions of buried utilities to permanent facility components using triangulation.

5. Identify and locate existing buried or concealed items encountered during Project.

6. Field changes of dimension and detail.

E. Submit marked-up paper copy documents to Owner’s Project Manager before

Substantial Completion.

F. Submit PDF electronic files of marked-up documents to Owner’s Project Manager before Substantial Completion.

1.11 FINAL CLEANING

June 2023 Section 017000 – Execution and Closeout Requirements Page 12 of 65

A. Execute final cleaning prior to final Project assessment.

1. Employ experienced personnel or professional cleaning firm.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 13 of 65

SECTION 026500 – UNDERGROUND STORAGE TANK REMOVAL

A. This Section includes the removal, decommissioning, and disposal of the 285-gallon waste oil underground storage tank (UST).

B. Related Sections:

1. Section 01 70 00 – Execution and Closeout Requirements

2. Section 31 05 13 – Soils for Earthworks

3. Section 31 05 16 - Aggregates for Earthwork

4. Section 31 10 00 - Site Clearing

5. Section 31 23 16 - Excavation

6. Section 31 23 23 - Fill

7. Section 31 25 00 - Erosion and Sedimentation Controls

8. Section 32 11 23 - Aggregate Base Courses

9. Section 32 12 16 - Asphalt Paving

1.2 REFERENCES

A. The current issue of each document shall govern. If there is a conflict between documents, or between a document and the Technical Specifications, the most stringent requirements shall apply.

1. Current Oregon State Fire Code

2. Oregon Administrative Rules for Underground Storage Tanks: OAR 340-122, 340-

150, 340-160

3. Federal Underground Storage Tank Rules: 40 CFR Part 280

4. Oregon Safety and Health Standards: OAR 437, Division 2

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 14 of 65

5. API 1604: Closure of underground Petroleum storage tanks. Published by the American Petroleum Institute, 1220 L. Street, NW, Washington, DC 20005.

7. API 1628: A Guide to the Assessment and Remediation of Underground

Petroleum Releases

8. "Test Methods for Evaluating Solid Waste: Physical/Chemical Methods

Compendium SW-846”, (U.S. Environmental Protection Agency EPA)

1.3 DEFINITIONS

A. The following terms are used in this specification. Additional terms and definitions may be found in the DEQ UST Regulations (OAR 340-150-0001 through 0620; OAR 340-160-0005 through 0150; and OAR 340-122-0205 through 0360), incorporated into this contract by reference.

1. "Above-Ground Release" means any release to the land surface or to surface water.

This includes, but is not limited to, releases from the above ground portion of a petroleum UST system and releases associated with overfills and transfer operations during petroleum deliveries to or dispensing from a petroleum UST system.

2. "Acceptable Risk Level" has the meanings set forth in OAR 340-122-0115(1) through

(6).

3. "Ancillary equipment" means any devices including, but not limited to, such devices as piping, fittings, flanges, valves and pumps used to distribute, meter or control the flow of regulated substances to and from an UST.

4. "Aquatic Sediments" means any collection of fine-, medium-, and coarse-grained minerals and organic particles that are found within aquatic habitats.

(a) "As built drawing" or "as built" means a line drawing to-scale that accurately illustrates the location of USTs, underground piping, and all related equipment in relation to buildings or other structures at an UST facility and that provides thorough construction documentation.

(b) Other terms used in lieu of "as built" are "record drawing" or "measured drawing," which indicate that the drawing is for an existing structure or UST system.

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 15 of 65

5. “Belowground release” means any release to the subsurface of the land and to groundwater. This includes, but is not limited to, releases from the belowground portions of an underground storage tank system and belowground releases associated with overfills and transfer operations as the regulated substance moves to or from an underground storage tank.

6. “Beneath the surface of the ground” means beneath the ground surface or otherwise covered with earthen materials.

7. "Buildings" means any structure occupied by residents, workers or visitors, including convenience stores for retailing of food. For purposes of these rules, "buildings" does not include service station kiosks less than 45 square feet in size if the kiosk is exclusively dedicated to services for motor vehicles.

8. "CERCLA" means the Comprehensive Environmental Response, Compensation and

Liability Act of 1980, as amended (42 U.S.C. § 1906 et seq.).

9. "Closure" means to permanently decommission an UST, by removal, filling in-place with an inert material or change-in-service, or to temporarily remove an UST from operation.

10. "Compatible" means the ability of two or more substances to maintain their respective physical and chemical properties upon contact with one another for the design life of the UST system under conditions likely to be encountered in the UST.

11. "Confirmed release" means:

(a) For petroleum. Contamination observed in soil or groundwater as a sheen, stain or petroleum odor or petroleum contamination detected in soil by the Northwest Total Petroleum Hydrocarbon Identification Analytical Method (NWTPH-HCID, DEQ, December 1996) or detected in groundwater by any appropriate analytical method specified in OAR 340-122-0218,or

(b) For hazardous substances other than petroleum. Contamination observed in soil or groundwater as a sheen, stain or identifiable odor or as detected in soil, surface water or groundwater by any appropriate analytical method specified in "Test Methods for Evaluating Solid Waste: Physical/Chemical Methods Compendium SW-846”, (U.S. Environmental Protection Agency EPA).

12. "Connected piping" means all piping including valves, elbows, joints, flanges and flexible connectors, attached to an UST system through which regulated substances flow and that are located beneath the ground surface or otherwise covered by

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 16 of 65 earthen materials. For the purpose of determining how much piping is connected to any individual UST system, the piping that joins two UST systems should be allocated equally between them.

13. "Contaminant of Concern" means a hazardous constituent contained in petroleum present at a concentration posing a potentially unacceptable risk to public health, safety or welfare or the environment.

14. "Corrective action" means remedial action taken to protect the present or future public health, safety, welfare or the environment from a release of a regulated substance. "Corrective action" includes but is not limited to:

(a) Preventing, eliminating, removing, abating, controlling, investigating, assessing, evaluating or monitoring a hazard or potential hazard or threat, including migration of a regulated substance; or

(b) Transporting, storing, treating or disposing of a regulated substance or contaminated material from a site.

15. "Decommission" means permanent removal from operation including filling in-place, removal from the ground or change-in-service to a nonregulated status of any UST system component.

16. "De minimis" means an insignificant amount of regulated substance (e.g., meets the definition of "empty") or is less than a reportable quantity as defined under CERCLA.

17. "DEQ” means the Oregon Department of Environmental Quality.

18. "Earthen Materials" means materials originating from the earth, including, but not limited to, dirt, sand, gravel and rocks, or any other materials, including, but not limited to, wood, that have the potential to cause corrosion when placed in contact with a tank.

19. "Electrical equipment" means equipment that is located beneath the ground surface or otherwise covered by earthen materials and that contains dielectric fluid that is necessary for equipment to operate, such as transformers and buried electrical cable.

20. "Empty" means the tank contains no more than one inch of a liquid containing a regulated substance or 0.3 percent by volume of the total capacity of the tank.

21. "Engineering Control" means a remedial method used to prevent or minimize exposure to petroleum and hazardous substances, including technologies that

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 17 of 65 reduce the mobility or migration of petroleum and hazardous substances.

Engineering controls may include, but are not limited to, capping, horizontal or vertical barriers, hydraulic controls and alternative water supplies.

22. "Excavation zone" means the volume containing the UST system and backfill material bounded by the ground surface, walls and floor of the pit and trenches into which the UST system is placed at the time of installation.

23. "Free product" means a regulated substance that is present as a nonaqueous phase liquid (e.g., liquid not dissolved in water).

24. "Gasoline" means any petroleum distillate used primarily for motor fuel of which more than 50 percent of its components have hydrocarbon numbers of C10 or less.

For purposes of OAR 340-122-0205 through 340-122-0360, the concentration of gasoline in soil or groundwater is the level determined by the Northwest Total Petroleum Hydrocarbon Method NWTPH-Gx.

25. "Gathering lines" means any pipeline, equipment, facility, or building used in transporting oil or gas during oil or gas production or gathering operations.

26. "Groundwater" means any water, except capillary moisture, beneath the land surface or beneath the bed of any stream, lake, reservoir, or other body of surface water within the boundaries of the state, whatever may be the geological formation or structure in which such water stands, flows, percolates or otherwise moves.

27. "Hazardous Substance" has the meaning set forth in OAR 340-122-0115(30).

28. "Institutional Control" means a remedial method such as a legal or administrative tool or action used to reduce the potential for exposure to petroleum and hazardous substances. Institutional controls may include, but are not limited to, use restrictions and site access and security measures.

29. "Investigation" means monitoring, surveying, testing, sampling, analyzing or other information gathering techniques.

30. "Leak" has the same meaning as "release" as defined by OAR 340-150-0010(70).

31. “Motor Fuel” means a complex blend of hydrocarbons typically used in operating a motor engine, such as motor gasoline, aviation gasoline, No. 1 or No. 2 diesel fuel, or any blend containing one or more of these substances (for example: motor gasoline blended with alcohol).

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 18 of 65

32. "Native soil" means the soil outside of the immediate boundaries of the pit that was originally excavated for the purpose of installing an UST.

33. "Non Gasoline Fraction" means diesel and any other petroleum distillate used for motor fuel or heating oil, of which more than 50 percent of its components have hydrocarbon numbers of C11 or greater. For purposes of OAR 340-122-0205 through 340-122-0360, the concentration of non gasoline fraction in soil or groundwater is the level determined by the Northwest Total Petroleum Hydrocarbon Method NWTPH-Dx.

34. "OAR" means Oregon Administrative Rules.

35. "Operate" or "operation" means depositing a regulated substance into an UST, storing a regulated substance in, or dispensing a regulated substance from an UST.

36. "ORS" means Oregon Revised Statutes.

37. "Owner" means a person who currently owns an UST or who owned an UST.

38. "Permittee" means the owner or person who is in control of or has responsibility for daily UST system operation and maintenance, financial responsibility, and UST operator training requirements set forth in OAR chapter 340, division 150.

39. "Person" means an individual, trust, firm, joint stock company, federal agency, corporation, partnership, joint venture, consortium, association, state, municipality, commission, political subdivision of a state or any interstate body, any commercial entity, and the United States Government.

40. "Petroleum" or "oil" means gasoline, crude oil, fuel oil, diesel oil, lubricating oil, oil sludge, oil refuse and crude oil fractions and refined petroleum fractions, including gasoline, kerosene, heating oils, diesel fuels, and any other petroleum-related product, or waste or fraction thereof, that is liquid at a temperature of 60 degrees Fahrenheit and a pressure of 14.7 pounds per square inch absolute. For the purposes of chapter 340, divisions 150 and 160, blends of gasoline with ethanol and diesel fuels with biodiesel are “petroleum.” "Petroleum" does not include any substance identified as a hazardous waste under 40 C.F.R. Part 261 (October 13, 2015).

41. "Petroleum UST system" means an UST system that contains petroleum or a mixture of petroleum with de minimis quantities of other regulated substances. Such systems include those containing motor fuels, jet fuels, distillate fuel oils, residual fuel oils, lubricants, petroleum solvents and used oils.

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 19 of 65

42. "Pipe" or "piping" means a hollow cylinder or tubular conduit that is constructed of nonearthen materials.

43. "Pipeline facilities," including gathering lines, means new and existing pipe rights-of-way and any associated equipment, facilities or buildings.

44. "Probability of detection" means the likelihood, expressed as a percentage, that a test method will correctly identify a release from an UST system.

45. "Property owner" means the legal owner of the real property on which an UST is located.

46. "Regulated substance" means:

(a) Any substance defined in section 101(14) of CERCLA. This does not include any substance regulated as a hazardous waste under subtitle C; and

(b) Petroleum, including crude oil or any fraction thereof that is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute).

(c) The term regulated substance includes but is not limited to petroleum and petroleum-based substances comprised of a complex blend of hydrocarbons, such as motor fuels, jet fuels, distillate fuel oils, residual fuel oils, lubricants, petroleum solvents, and used oils.

47. "Release" means the discharge, deposit, injection, dumping, spilling, emitting, leaking or placing of a regulated substance from an UST into the air or into or on land or the waters of the state, other than as authorized by a permit issued under state or federal law.

48. "Release detection" or "leak detection" means determining whether a release of a regulated substance has occurred from the UST system into the environment or a leak has occurred into the interstitial space between the UST system and its secondary barrier, or into a secondary containment unit or sump around the UST.

49. "Remediation" or "Remedial Measures" include "remedial action" as defined in ORS

465.200(22), "removal" as defined in 465.200(24) and "corrective action" as defined in 466.706(3).

50. "Remediation Level" means a concentration of petroleum or petroleum constituents in environmental media such as soil and groundwater that alone, or in combination

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 20 of 65 with institutional controls or engineering controls, is determined to be protective of public health, safety and welfare and the environment in accordance with this division.

51. "Responsible Person" includes "owner" as defined in OAR 340-150-0010(51), "permittee" as defined in 340-150-0010(52), "owner or operator" as defined in ORS 465.200(19) and any other person liable for or voluntarily undertaking remediation under 465.200, et seq. or 466.706, et seq.

52. "Risk-Based Concentration" means a concentration of petroleum or petroleum constituents in environmental media such as soil and groundwater that is determined to be protective of public health, safety and welfare and the environment in accordance with these rules without requiring institutional controls or engineering controls.

53. "Service provider" means a person licensed by DEQ to perform UST services on USTs.

54. "Soil" means any unconsolidated geologic materials including, but not limited to, clay, loam, loess, silt, sand, gravel and tills or any combination of these materials.

55. "Storm water" or "wastewater collection system" means piping, pumps, conduits, and any other equipment necessary to collect and transport the flow of surface water runoff resulting from precipitation or domestic, commercial or industrial wastewater to and from retention areas or any areas where treatment is designated to occur.

Collecting storm water and wastewater does not include treatment except where incidental to conveyance.

56. "Supervisor" means an individual licensed by DEQ to direct and oversee specific UST services.

57. "Surface impoundment" means a natural topographic depression, human-made excavation, or diked area formed primarily of earthen materials, although it may be lined with human-made materials, that is not an injection well.

58. "Surface Water" means lakes, bays, ponds, impounding reservoirs, springs, wells, rivers, streams, creeks, estuaries, wetlands, inlets, canals, the Pacific Ocean within the territorial limits of the State of Oregon and all other bodies, natural or artificial, inland or coastal, fresh or salt, public or private (except those private waters which do not combine or effect a junction with natural surface waters), which are wholly or partially within or bordering the state or within its jurisdiction.

59. "Suspected release" has the same meaning as described in OAR 340-150-0500(1).

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 21 of 65

60. "Tank" means a stationary device designed to contain an accumulation of regulated substances that is constructed of nonearthen materials (e.g. concrete, steel, plastic) that provide structural support.

61. "Underground area" means an underground room, such as a basement, cellar, shaft or vault, that provides enough space for physical inspection of the exterior of the tank situated on or above the surface of the floor.

62. "Underground piping" means connected piping that is located beneath the ground surface.

63. "Underground storage tank" or "UST" means any one, or a combination of tanks, including connected underground piping that contains or used to contain a regulated substance and the volume of which, including the volume of connected underground piping is 10 percent or more beneath the ground surface.

64. "UST facility" means the real property on which an UST is installed or will be installed.

A UST facility encompasses all contiguous real property owned by the same property owner associated with the operation of the UST system.

65. "UST services" includes, without limitation, installing, decommissioning, modifying, testing (e.g., cathodic protection and tank tightness) and inspecting UST systems.

66. "UST system" or “Tank System” means an underground storage tank, connected underground piping, underground ancillary equipment and containment system, if any.

1.4 MATERIAL OWNERSHIP

A. Removed and decommissioned materials shall become Contractor's property and shall be removed from the Project site.

1.5 SAFETY

A. Proper removal procedures must be followed, especially for tanks containing volatile liquids, vapors, or hazardous regulated substances. The Contractor shall submit a site specific health and safety plan to use during construction activities at least ten (10) days prior to commencing work. All persons doing tank decommissioning work shall

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 22 of 65 be under continuous direct supervision of Contractor’s licensed UST Service Provider and shall be trained and knowledgeable of:

1. All applicable environmental, fire, health and safety rules, regulations and site specific health and safety plan and emergency response plan required in the Technical Specifications.

2. The proper operation of equipment and methods for freeing tanks of vapors and testing for combustible vapors.

3. The proper handling and disposal of all wastes encountered during completion of the Work.

4. Permit-Required Confined Space entry procedures, including current training, written entry program, and equipment necessary for meeting OSHA Confined Space Entry requirements.

B. Care must be exercised to minimize exposure to petroleum products and soil contaminated with petroleum products. Contractor shall be responsible for informing its workers and subcontractors of all chemical and physical hazards potentially present at the Work Sites and safe working procedures. The Contractor must comply with all applicable OSHA training requirements.

C. In the event that the Contractor engages in Cleanup Activities, all provisions of OAR

340-122-0205 through OAR 340-122-360 (UST Cleanup Manual) must be met.

1.6 PROJECT CONDITIONS

A. Care must be exercised to prevent spilling of petroleum or chemical products onto the surface or into the pit during tank decommissioning. Spills into the ground or groundwater must be reported immediately to the Owner and shall be cleaned up at Contractor’s expense. Contractor shall complete additional reporting depending upon the type and quantity of the spill as required by federal and state regulations.

B. The Contractor shall post adequate warning signs at all potential entrances to work sites. The Contractor shall install security fencing in the immediate area surrounding the Excavation Zone.

C. The Contractor is responsible for having all existing utilities accurately located in the construction area. No work shall commence until all existing utilities have been field

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 23 of 65 located and marked. Repair of damages resulting from the Contractor activities to any utility, including those underground, shall be paid for solely by the Contractor.

PART 2 – PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 PERMANENT DECOMMISSIONING

A. Tank Cleaning

1. Drain and flush all piping into the tank, being careful to avoid spilling.

2. Contractor should plan for the tank to be empty, but tank may contain residual sludge and solids; they will arrange for removal, management, and disposal/recycling of this material. Remove any solids or sludge. Any material which cannot be recycled must be disposed of in accordance with applicable federal and state laws. The Contractor is responsible for determining appropriate disposal options for all tank contents.

3. Carefully dig down to the top of the tank.

4. Remove any Ancillary Equipment, e.g., tank gauge pipe, fill pipe, and other tank fixtures.

5. Cap or remove any non-product Ancillary Equipment, leaving the vent line open until the tank is purged of all flammable or explosive vapors. This is referred to as inerting the tank.

6. Temporarily close off all other openings in the tank so that all vapors can be vented through the vent line during the inerting process.

7. All tanks containing combustible and flammable liquids shall be inerted and rendered gas free, using one of the following methods:

a. Inert the tank with dry ice (1.5 pounds per 100 gallons of tank capacity). The dry ice shall be evenly distributed over the whole area of the tank bottom.

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 24 of 65

During the inerting process, precautions shall be taken to prevent ignitions throughout the Excavation Zone that might be affected by the vapors.

b. Ventilate the tank with air using an eductor-type air mover. Such a device usually uses compressed air to cause the vapors to be drawn out of the tank.

For this method, leave the drop tube in place to ventilate the bottom of the tank. Discharge the vapors a minimum of 12 feet above the ground surface using an eductor extension.

c. Ventilate the tank with air, using a diffused air blower. The air pressure must not exceed 5 pounds per square inch gauge.

d. Inert the tank with a non-reactive gas, such as carbon dioxide or nitrogen.

Again, the internal gas tank pressure shall not exceed 5 pounds per square inch gauge.

8. Monitor the vapor concentration levels in the tank and in the Excavation Zone using a combustible gas meter that has been maintained and calibrated according to the manufacturer's instructions. Once the meter shows levels below 10% of the lower explosive limit (LEL), the tank is considered inerted and safe for removal.

B. Tank Removal

1. In addition to 3.1(A), complete the following:

2. Plug or cap all holes leaving a 1/8-inch vent hole to prevent differential pressures from building up due to temperature differences.

3. Remove all existing concrete and asphalt paving necessary to allow removal of the tank.

4. Excavate soils around and above tank to allow removal.

5. Complete the excavation and remove the tank. As a safety precaution the tank shall be blocked with wood blocks when staged on the ground to prevent the tank from moving.

6. Remove vent line. Cut at cap at one end at edge of excavation. Cut and cap other end at ground surface. Remove all aboveground vent piping. Buried vent line between edge of excavation and ground surface can be left in ground and abandoned in place.

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 25 of 65

7. If transported, the tank shall be secured on the truck so that the 1/8-inch vent hole is located on the top of the tank.

8. If groundwater is encountered, work will stop immediately, and the Owner will be notified. In accordance with Oregon law, any identified release from the removed tanks will be reported to the Oregon DEQ Tanks Program.

9. If excavated soil exhibits signs of contamination, stockpile the contaminated soil and debris onto a plastic-lined and bermed area. A layer of plastic sheeting (6 mils or greater) shall be placed beneath the stockpile and a layer shall also be placed over the top of the stockpile upon completion of the excavation phase.

Contractor shall perform a visual inspection and test any excavated soil evidencing apparent contamination. Test methods shall include initial hydrocarbon identification by Northwest Method Total Petroleum Hydrocarbons (NWTPH-HCID), and quantification of total petroleum hydrocarbon (TPH) detections in the gasoline range (NWTPH-Gx) and TPH in the diesel range (NWTPH-Dx), as appropriate. Additional follow-up analyses, as specified in OAR 340-122-0218 and 340-122-0340, and any additional analysis for disposal options, are the responsibility of the Contractor.

10. Remove and dismantle, or have the ends cut off the existing tank and piping. The tank shall be punctured, drilled, or cut appropriately to prevent its future use.

11. Contractor must provide the Owner with written verification that tank, Ancillary

Equipment, and any contents have been disposed of in accordance with state and federal regulations. Vehicles used for the transporting of the above-mentioned items from the site shall comply with all local, state, and federal regulations, and all applicable codes and standards.

12. Contractor shall obtain appropriate dismantling/disposal documentation. The

Contractor shall provide copies of completed waste/recycling manifests of the tank removal, which show the ultimate destination of the tank, its lines, and contents. It shall be rendered unsuitable for future use as an UST by puncturing, cutting, or drilling holes in all sections of the tank.

13. The UST and Ancillary Equipment included in the Work to be excavated and disposed of by the Contractor becomes the property of the Contractor, unless otherwise specified by the Owner to be salvaged.

C. Soil Sampling

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 26 of 65

1. Two soil samples will be collected, one from below each end of the tank and beneath the waste oil and former gasoline AST piping runs as follows:

a. For piping runs between 5 and 20 feet, a minimum of two soil samples must be collected from the native soils directly beneath the areas where contamination is most likely to be found, unless otherwise approved by

DEQ;

b. For piping runs of more than 20 feet in length, beginning at the floor drain, at least one additional soil sample must be collected at each 20-foot interval.

2. Sampling is to be conducted by the Contractor. Contractor is responsible for costs associated with collecting and analyzing samples as described in this section.

3. The samples will be collected using a backhoe bucket, placed into sterile containers provided by an Oregon-accredited laboratory, labeled, and stored on ice for delivery to the laboratory with chain-of-custody documentation.

4. Soil samples will be submitted to the laboratory under a rush turnaround time of

24-48 hours.

5. Following the removal of the tank and collection of soil samples, the tank pit will be left open, and the excavation secured with fencing and/or covered with steel plates.

6. The Contractor is responsible for collecting soil samples from around the excavation to determine proper compaction requirements.

7. The tank pit will be backfilled per Section 31 23 23 “Fill”, once acceptable environmental soil sample analytical results have been received. Backfill material will consist of native material and imported gravel fill as needed. In wet weather conditions, imported gravel fill is expected to be necessary.

D. Site Restoration

1. Backfill Excavation Zone to the original grades that existed prior to construction.

Stockpiled soil which has been determined by laboratory testing required in the Technical Specifications to be uncontaminated may be used if suitable as structural backfill material. Additional structural fill to bring the excavation to grade shall be clean and free of debris or contamination.

June 2023 Section 02 65 00 – Underground Storage Tank Removal Page 27 of 65

2. Backfilling of the Excavation Zone shall not be performed until the soil sample results are made available and the Owner approves filling. Replace asphalt, concrete sidewalks, concrete curbs, and concrete pavements per the Technical Specifications.

E. Decommissioning Reporting

1. Reporting Suspected Releases

a. An owner and permittee of an UST system must notify DEQ within 24 hours, or another reasonable period allowed by DEQ, and follow the procedures in OAR 340-150-0510.

2. Contractor will follow requirements as specified in OAR 340-150-0168(8). Within 30 days after completing the field work or other period approved by DEQ, the permittee must complete and submit to DEQ an underground storage tank decommissioning checklist and site assessment report (OAR 340-150-0180) signed by the owner, permittee and service provider. A release does not relieve the Service Provider of reporting decommissioning within 30 days.

June 2023 Section 310513 – Soils for Earthwork Page 28 of 65

SECTION 310513 - SOILS FOR EARTHWORK

PART 1 - GENERAL

A. Section Includes:

1. Subsoil.

2. Topsoil.

1.2 UNIT PRICES

A. Subsoil:

1. Basis of Measurement: By cubic foot.

2. Basis of Payment: Includes supplying subsoil materials, and stockpiling.

B. Topsoil:

2. Basis of Payment: Includes supplying topsoil materials, and stockpiling.

1.3 SUBMITTALS

A. Product Data:

1. Subsoil.

2. Topsoil.

B. Samples: Submit, in airtight containers, 10-lb. sample of each type of fill to testing laboratory.

C. Source Quality-Control Reports: For subsoil and topsoil materials.

1.4 QUALITY ASSURANCE

A. Furnish each subsoil and topsoil material from single source throughout Work.

B. Perform Work according to Jackson County standards.

June 2023 Section 310513 – Soils for Earthwork Page 29 of 65

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Perform Work according to:

1. The State of Oregon Department of Transportation standards.

2. Jackson County standards.

2.2 SUSTAINABILITY CHARACTERISTICS

A. Regional Materials: Furnish materials extracted, processed, and manufactured within 500 miles of Project Site.

2.3 SUBSOIL

A. Type S1: Comply with Jackson County standard.

B. Type S2 Ordinary Borrow:

1. Ordinary borrow consists of well-graded mineral soil substantially free of organic materials, loam, wood, trash, and other objectionable material which may be compressible or which cannot be compacted properly.

2. Ordinary borrow consist of a material satisfactory to the Owner and not specified as gravel borrow, sand borrow, special borrow material, or other particular kind of borrow.

3. This material conforms to the physical characteristics of soils designated as group A-1, A-2-4, or A-3 under AASHTO M 145.

4. Must be readily spread and compacted for the formation of foundations, embankments, and other subgrade improvements.

5. Liquid Limit: A-1 and A-3 = none or not measured, A-2-4 = 40 max.

6. Plasticity Index: A-1 = 6 max, A-3 = Non-Plastic (NP), A-2-4 = 10 max.

C. Type S2-d Structural Fill:

1. Structural fill consists of processed fill material that is hard durable stone and coarse sand, free from loam and clay, surface coatings, and deleterious materials. Gradation requirements as determined by AASHTO T11 and T27 conforms to the following gradation requirements:

June 2023 Section 310513 – Soils for Earthwork Page 30 of 65

a) Percent Passing According to Sieve Size:

1) 3 Inches (75 mm): 100.

2) 1/2 Inch (12 mm): 50 to 85.

3) No. 4 (4.75 mm): 40 to 75.

4) No. 50 (300 micro m): 8 to 28.

5) No. 200 (75 micro m): 0 to 8.

D. Type S2-e Reclaimed Pavement Borrow Material:

1. Reclaimed pavement borrow material consists of crushed asphalt pavement or crushed cement concrete, and gravel borrow.

2. Provide material free of loam, clay, and deleterious materials such as brick, reinforcing steel, wood, paper, plaster, lathing, and building rubble.

3. Provide coarse aggregate with a percentage of wear not greater than 50 percent as measured by the Los Angeles Abrasion Test.

4. Determine gradation requirements in accordance with AASHTO T 311, except the material cannot be oven…