ATTACHMENT 5 - DFSP Pt. Loma Accident Prevention Plan.pdf
PDF 19 MB Posted
- Attached to
- SPE603-22-R-0509 - DFSP Point Loma Environmental Restoration, Compliance, and Facility Management Services
- Solicitation number
- SPE60323D5002
- Issued by
-
Defense Logistics Agency Energy
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AACCCCIIDDEENNTT PPRREEVVEENNTTIIOONN PPLLAANN
SSiittee AAccttiivviittiieess aatt DDeeffeennssee FFuueell SSuuppppoorrtt PPooiinntt ((DDFFSSPP)) PPooiinntt LLoommaa NNaavvaall BBaassee PPooiinntt LLoommaa SSaann DDiieeggoo,, CCaalliiffoorrnniiaa
EEnnvviirroonnmmeennttaall RReessppoonnssee CCoonnttrraacctt
SSPPEE660033--1188--DD--55000077
Prepared for:
Defense Logistics Agency, Installation Support for Energy (DLA Energy) 8725 John J. Kingman Road, Suite 2828 Fort Belvoir, VA 22060-6222
Prepared by:
Bhate Federal Services JV LLC.
1608 13th Avenue South, Suite 300 Birmingham, AL 35205
DFSP Pt. Loma Environmental Services SPE60323D5002 ATTACHMENT #5
Accident Prevention Plan Disclaimer
This Accident Prevention Plan (APP) has been designed for the methods presently contemplated by BFS Federal Services LLC (BFS) for execution of proposed work. Therefore, the APP may not be appropriate if the work is not performed by or using the methods presently contemplated by BFS. In addition, as the work is performed, conditions different from those anticipated may be encountered, and the APP may have to be modified. Therefore, BFS only makes representations or warranties as to the adequacy of the APP for currently anticipated activities and conditions. This plan was originally prepared for the preceeding contract for Point Loma operation and maintenace. The contract awarded to BFS (SPE603-18-D-5007) required that BFS review and update the original HSP. This document is a result of that review and update.
Table of Contents ________________________________________________
List of Figures ................................................................................................................................................ v List of Tables ................................................................................................................................................. v List of Appendices ......................................................................................................................................... v Acronyms and Abbreviations ......................................................................................................................... vi
1.0 Signature Sheet .............................................................................................................................. 1-1
2.0 Background Information .................................................................................................................. 2-1
2.1 Contractor ............................................................................................................................. 2-1
2.2 Contract Number .................................................................................................................. 2-1
2.3 Project Name ........................................................................................................................ 2-1
2.4 Project Description ............................................................................................................... 2-2
2.4.1 Assessment ............................................................................................................. 2-2
2.4.2 Remediation ............................................................................................................ 2-3
2.4.3 Compliance ............................................................................................................. 2-3
2.4.4 Anticipated Activities Needing an Activity Hazard Analysis ..................................... 2-4
3.0 Statement of Safety and Health Policy ............................................................................................ 3-1
3.1 Corporate Safety Policy ........................................................................................................ 3-1
3.2 Safety Program Goals, Objectives, and Accident Experience Goals .................................... 3-2
4.0 Responsibilities and Lines of Authority ........................................................................................... 4-1
4.1 Employer Ultimate Responsibilities ...................................................................................... 4-1
4.2 Personnel Identification and Accountability .......................................................................... 4-1
4.2.1 On-Site Personnel ................................................................................................... 4-1
4.2.2 Project Manager ...................................................................................................... 4-2
4.2.3 Site Manager/Construction Manager ....................................................................... 4-2
4.2.4 Site Safety and Health Officer ................................................................................. 4-3
4.2.5 Program Health, Safety, and Environment Manager ............................................... 4-5
4.2.6 Contracting Officer’s Representative ....................................................................... 4-5
4.2.7 Visitors..................................................................................................................... 4-5
4.3 Competent and Qualified Person Qualifications ................................................................... 4-6
4.4 Competent and Qualified Person Requirements .................................................................. 4-7
4.5 Pre-Task Safety and Health Analysis ................................................................................... 4-8
4.5.1 Extra Hazardous and Repair Work .......................................................................... 4-8
4.5.2 Activity Hazard Analyses ....................................................................................... 4-10
4.5.3 Job Safety Analyses .............................................................................................. 4-10
4.5.4 Step Back for Safety Procedure ............................................................................ 4-11
4.6 Lines of Authority ................................................................................................................ 4-13
4.7 Noncompliance with Safety Requirements ......................................................................... 4-13
4.7.1 Management Accountability .................................................................................. 4-14
5.0 Subcontractors and Suppliers ......................................................................................................... 5-1
5.1 Identification of Subcontractors and Suppliers...................................................................... 5-1
5.2 Subcontractor/Supplier Safety Responsibilities .................................................................... 5-2
6.0 Training ........................................................................................................................................... 6-1
6.1 Safety and Occupational Health Orientation ......................................................................... 6-1
6.2 Mandatory Training and Certifications .................................................................................. 6-3
6.3 Periodic Supervisory and Employee Safety and Health Training .......................................... 6-5
6.4 Emergency Response Training ............................................................................................ 6-6
7.0 Safety and Health Inspections ........................................................................................................ 7-1
7.1 Site Safety Inspections ......................................................................................................... 7-1
7.2 Equipment Safety Inspections .............................................................................................. 7-2
7.2.1 Portable Fire Extinguisher Inspections .................................................................... 7-2
7.2.2 First-Aid Kits ............................................................................................................ 7-2
7.2.3 Emergency Eyewash / Safety Shower ..................................................................... 7-2
7.2.4 Mechanical Equipment Inspections ......................................................................... 7-3
7.3 Safety Supervisor Meetings .................................................................................................. 7-3
7.4 HSE Corrective Action Tracking Register ............................................................................. 7-4
7.5 External Inspections ............................................................................................................. 7-4
8.0 Accident Reporting .......................................................................................................................... 8-1
8.1 Exposure Data (Man-Hours Worked) ................................................................................... 8-1
8.2 Accident Investigations, Reports, and Logs .......................................................................... 8-1
8.3 Immediate Notification of Major Incidents ............................................................................. 8-2
9.0 Plans (Programs, Procedures) Required by the Safety Manual ...................................................... 9-1
9.1 Layout Plans ......................................................................................................................... 9-1
9.2 Emergency Response Plan .................................................................................................. 9-1
9.2.1 Personnel Roles/Lines of Authority.......................................................................... 9-2
9.2.1.1 Site Manager/Construction Manager/Site Safety and Health Officer ......... 9-2
9.2.1.2 Project Manager Emergency Support ....................................................... 9-2
9.2.2 Medical Emergency Response ................................................................................ 9-2
9.2.2.1 Serious Exposures or Injuries Requiring Transport by Ambulance ........... 9-3
9.2.3 Site Evacuation Procedures .................................................................................... 9-4
9.2.4 Emergency Equipment ............................................................................................ 9-5
9.2.5 Spill Prevention and Control .................................................................................... 9-6
9.2.5.1 Pre-emptive Measures .............................................................................. 9-6
9.2.5.2 Spill Response Procedure ......................................................................... 9-7
9.2.5.3 Spill Response Drill Procedure ................................................................. 9-9
9.2.5.4 Critique and Follow-Up of Emergency Procedures ................................... 9-9
9.2.6 Fire Control Response Procedure ......................................................................... 9-10
9.2.6.1 Fire Control Drill Procedure ..................................................................... 9-10
9.2.7 List of Emergency Contacts and Notification ......................................................... 9-10
9.2.8 Man Overboard/Abandon Ship .............................................................................. 9-11
9.2.9 On-Site Medical Support ....................................................................................... 9-11
9.2.9.1 Off-Site Medical Support ......................................................................... 9-12
9.3 Plan for Prevention of Alcohol and Drug Abuse.................................................................. 9-12
9.4 Site Sanitation Plan ............................................................................................................ 9-13
9.5 Access and Haul Road Plan ............................................................................................... 9-13
9.6 Respiratory Protection Plan ................................................................................................ 9-14
9.6.1 General Respiratory Protection Requirements ...................................................... 9-14
9.6.2 Training Requirements .......................................................................................... 9-14
9.6.3 Respirator Inspection and Cleaning....................................................................... 9-14
9.6.4 Respirator Fit Testing ............................................................................................ 9-14
9.6.5 Facial Hair ............................................................................................................. 9-15
9.6.6 Medical Certification .............................................................................................. 9-15
9.6.7 Respiratory Protection for Crystalline Silica ........................................................... 9-15
9.7 Health Hazard Control Plan ................................................................................................ 9-15
9.8 Hazard Communication Program ....................................................................................... 9-15
9.9 Process Safety Management Plan ..................................................................................... 9-16
9.10 Lead Abatement Plan ......................................................................................................... 9-16
9.11 Asbestos Abatement Plan .................................................................................................. 9-16
9.12 Radiation Safety Program .................................................................................................. 9-16
9.13 Abrasive Blasting Plan ........................................................................................................ 9-17
9.14 Heat and Cold Stress Monitoring Plan ................................................................................ 9-17
9.14.1 Heat Stress ............................................................................................................ 9-18
9.14.1.1 Heat Stress - Signs and Symptoms ........................................................ 9-19
9.14.1.2 Heat Stress Prevention ........................................................................... 9-20
9.14.1.3 Heat Stress Treatment ............................................................................ 9-21
9.14.1.4 Heat Stroke Treatment ............................................................................ 9-22
9.14.1.5 Heat Stress Control – Flagging System .................................................. 9-22
9.14.1.6 Heat Stress Control - Physiological Monitoring ....................................... 9-25
9.14.1.7 Heat Stress - Training ............................................................................. 9-25
9.14.2 Cold Stress ............................................................................................................ 9-26
9.14.2.1 Cold Stress Prevention Requirements .................................................... 9-27
9.14.2.2 Cold Stress Treatment ............................................................................ 9-30
9.14.2.3 Cold Stress Control – Wind Chill Index Monitoring .................................. 9-31
9.14.2.4 Cold Stress - Training ............................................................................. 9-31
9.15 Crystalline Silica Monitoring Plan ....................................................................................... 9-32
9.16 Night Operations Lighting Plan ........................................................................................... 9-32
9.17 Fire Prevention and Protection Plan ................................................................................... 9-32
9.17.1 Workplace Fire Hazards ........................................................................................ 9-33
9.17.2 Potential Ignition Sources ...................................................................................... 9-33
9.17.3 Fire-Control Systems, Equipment, and Procedures............................................... 9-33
9.17.4 Fire-Control Equipment Maintenance Responsibilities .......................................... 9-34
9.17.5 Fuel Source Hazards Control Responsibilities ...................................................... 9-34
9.17.6 Fire Control Housekeeping Procedures ................................................................. 9-34
9.18 Wild Fire Prevention Plan ................................................................................................... 9-35
9.19 Hazardous Energy Control Plan – Lockout/Tagout/Tryout ................................................. 9-35
9.20 Critical Lift Procedures ....................................................................................................... 9-36
9.21 Contingency Plan for Severe Weather ............................................................................... 9-36
9.21.1 Adverse Weather Conditions/Natural Disasters .................................................... 9-36
9.21.2 Lightning Safety ..................................................................................................... 9-37
9.21.3 Storm Procedures ................................................................................................. 9-38
9.21.4 Earthquakes .......................................................................................................... 9-38
9.21.5 Tsunamis ............................................................................................................... 9-39
9.21.6 Hurricanes and Tornadoes .................................................................................... 9-39
9.21.7 Mudslides .............................................................................................................. 9-39
9.21.8 Wildfire .................................................................................................................. 9-40
9.22 Float Plan ........................................................................................................................... 9-40
9.23 Site-Specific Fall Protection and Prevention Plan ............................................................... 9-40
9.23.1 Required Fall Protection/Fall Protection Systems.................................................. 9-40
9.23.2 Training Requirements .......................................................................................... 9-41
9.24 Demolition Plan .................................................................................................................. 9-41
9.25 Excavation/Trenching Plan ................................................................................................. 9-41
9.25.1 Intrusive Activities .................................................................................................. 9-42
9.25.2 Utilities Clearance Procedure ................................................................................ 9-42
9.25.3 Preliminary Manual Clearance .............................................................................. 9-43
9.25.4 Excavation and Trenching Operations ................................................................... 9-43
9.26 Emergency Rescue (Tunneling) ......................................................................................... 9-44
9.27 Underground Construction Fire Prevention and Protection Plan ........................................ 9-44
9.28 Compressed Air Plan .......................................................................................................... 9-45
9.29 Form Work and Shoring Erection and Removal Plans ....................................................... 9-45
9.30 Precast Concrete Plan ........................................................................................................ 9-45
9.31 Lift Slab Plan ...................................................................................................................... 9-45
9.32 Steel Erection Plan ............................................................................................................. 9-45
9.33 Site Safety and Health Plan ................................................................................................ 9-45
9.34 Blasting Plan ...................................................................................................................... 9-45
9.35 Diving Plan ......................................................................................................................... 9-45
9.36 Confined Space Program ................................................................................................... 9-45
9.36.1 Confined Space Entry Competent Person ............................................................. 9-46
9.36.2 Elements of the Confined Space Entry Program ................................................... 9-46
9.36.3 Confined Space Entry Equipment ......................................................................... 9-47
9.36.4 Atmospheric Testing and Air Monitoring Action Levels .......................................... 9-47
10.0 Risk Management Processes ....................................................................................................... 10-1
11.0 References ................................................................................................................................... 11-1
List of Figures __________________________________________________
Figure 1 Site Vicinity Map Figure 2 Site Map Figure 3 Lines of Authority Figure 4 Site Evacuation Map Figure 5 Route Map to Hospital Figure 6 Route Map to Occupational Health Clinic
List of Tables ___________________________________________________
Table 1 Key Management Personnel Table 2 CPR and First Aid Training Completion Dates Table 3 Emergency Contact List Table 4 Heat Stress Index Table 5 CB&I Heat Stress Guideline – Heat Stress Index Flagging Levels Table 6 Wind Chill Table 7 Threshold Limit Values Work/Warm-up Schedule for 4-Hour Shift
List of Appendices _______________________________________________
Appendix A Accident Prevention Plan Acknowledgement Appendix B Site Safety and Health Plan Appendix C Activity Hazard Analyses Appendix D Site-Specific Accident Prevention Plan Amendments Appendix E Safety Personnel Resumes and Proof of Training and Competency Appendix F Referenced HSE Forms Appendix G Referenced HSE Procedures and Work Instructions Appendix H Competent Persons and Qualified Persons Designation Forms Appendix I Project HSE Information Pamphlet Appendix J Incident Notification, Reporting, and Management Procedure Appendix K Written Hazard Communication Plan Appendix L Severe Weather Preparedness Appendix M Infectious Disease Preparedness/Response Plan for the Novel Coronavirus, SARS-COV-2
Acronyms and Abbreviations ______________________________________ 29 CFR Code of Federal Regulations-Title 29 8 CCR California Code of Regulations – Title 8 ° degree °C degree Celsius °F degree Fahrenheit % percent ACGIH American Conference of Governmental Industrial Hygienists AHA Activity Hazard Analysis ANSI American National Standards Institute APP Accident Prevention Plan ASTM ASTM International bgs below ground surface Cal/OSHA California Division of Occupational Safety and Health
Administration BFS BFS Federal Services LLC CCR California Code of Regulations CFR Code of Federal Regulations CHMM Certified Hazardous Materials Manager CIH Certified Industrial Hygienist CMS CB&I Management System CO carbon monoxide COR Contracting Officer’s Representative CPR cardiopulmonary resuscitation CS confined space CSP Certified Safety Professional DFM diesel fuel, marine DFSP Defense Fuel Support Point DLA Energy Defense Logistics Agency, Installation Support for Energy DOT Department of Transportation EMS emergency medical services F44 NATO designation for jet propellant, grade 5 F76 NATO designation for diesel fuel, marine GDA government designated authority GPR ground penetrating radar HAZWOPER Hazardous Waste Operations and Emergency Response H2S hydrogen sulfide HSE Health, Safety, and Environmental HSEM Health, Safety, and Environmental Manager IDLH immediately dangerous to life health JP-4 / JP-5 jet propellant, grade 4 or grade 5 JSA Job Safety Analysis LEL lower explosive limit
Acronyms and Abbreviations (continued) ____________________________
LFL lower flammable limit mg/m3 milligram(s) per cubic meter mR/hr millirem per hour MSDS Material Safety Data Sheet MSHA Mine Safety and Health Administration NAPL non-aqueous phase liquid NATO North Atlantic Treaty Organization NAVFAC Naval Facilities Engineering Command NBPL Naval Base Point Loma NIOSH National Institute of Occupational Safety and Health NFPA National Fire Protection Association O&M operation and maintenance O2 oxygen OSHA Occupational Safety and Health Administration oz ounce PE Professional Engineer PEL permissible exposure limit PG Professional Geologist PID photoionization detector PIP Project HSE Information Pamphlet PM Project Manager PMP Project Management Professional POC point of contact PPE personal protective equipment ppm parts per million PWC Public Works Center (for NAVFAC Utilities) SDS Safety Data Sheet SOW scope of work SSHO Site Safety and Health Officer SSHP Site Safety and Health Plan TLV Threshold Limit Value USACE U.S. Army Corps of Engineers VOCs volatile organic compounds XRD X-ray powder diffraction
1.0 Signature Sheet
2.0 Background Information
This section provides a brief description of the project and activities for which this APP was prepared. This APP is prepared in accordance with the standards established by the United States Occupational Safety and Health Administration (OSHA) for regulated sites. Specifically, this APP complies with the appropriate standards contained in Code of Federal Regulations (CFR) –Title 29 (29CFR) 1940.120, 29CFR 1962.65, Safety and Health Requirements Manual – EM 385-1-1 (U.S. Army Corps of Engineers [USACE], 2008 and updates); Unified Facilities Guide Specifications, Health, Safety, and Emergency Response Procedures for Contaminated Sites, Section 01 35 29.13 (USACE et al., 2008); and Unified Facilities Guide Specifications, Governmental Safety Requirements, Section 01 35 26 (USACE et al., 2012). This plan was originally prepared for the preceeding contract for Point Loma operation and maintenace. The contract awarded to BFS (SPE603-18-D-5007) required that BFS review and update the original HSP. This document is a result of that review and update.
All new project personnel shall be provided a site orientation, which will convey the project-specific safety and health information provided in this APP. The training will be documented on the Accident Prevention Plan Acknowledgement Form (Appendix A, Accident Prevention Plan Acknowledgement).
Additionally, this APP contains the required Site Safety and Health Plan (SSHP) as Appendix B and Activity Hazard Analyses (AHAs) as Appendix C for the anticipated phases of work and specific work activities described herein. Additional AHAs may be attached to this APP through the amendment process. Any amendments to this APP shall be provided in Appendix D, Accident Prevention Plan Amendments. Amendments to this APP will be made in consultation and coordination with the BFS Project Manager (PM), BFS Site Manager/Construction Manager, BFS Site Safety and Health Officer (SSHO), and the BFS Program Health, Safety, and Environmental (HSE) Manager (HSEM).
2.1 Contractor
The prime contractor is BFS Federal Services LLC (BFS).
2.2 Contract Number
Defense Logistics Agency, Installation Support for Energy (DLA Energy) has contracted BFS under Environmental Response Contract No. SPE603-18-D-5007.
2.3 Project Name
The project name is “Environmental Assessment, Operation and Maintenance of Remediation
Systems, and Environmental Emergency Response Pt. Loma, CA (DFSP) Point Loma, Naval Base Point Loma (NBPL), San Diego, California” in accordance with the Statement of Work of the same name.
2.4 Project Description
The site of the work is the DFSP Point Loma Fuel Depot, located near 199 Rosecrans Street, Naval Base Point Loma, San Diego, California. DFSP Point Loma is one of several tenant facilities located on Naval Base Point Loma in the San Diego Area (Figures 1 and 2).
The DFSP Point Loma Fuel Depot includes aboveground storage tanks and appurtenances to receive, store, and dispense diesel fuel, marine (DFM or North Atlantic Treaty Organization [NATO] F76); jet propellant grade 5 (JP-5 or NATO F44); lubricating oils; managing reclaimed fuel oil; and processing ballast/bilge water. The topography is hilly; the soil is a mixture of fine-grained materials (silts, clays, and sands); the vegetation is dominated by non-native and native plant species; and the developed areas are paved.
In accordance with contractual scope of work (SOW), BFS provides Environmental Assessment, Operation and Maintenance of Remediation Systems, and Environmental Emergency Response services at DFSP Pt. Loma, CA. Primary work classifications consist of operation and maintenance, remediation, and compliance services.
2.4.1 Assessment
Assessment includes the following:
• Evaluation of the lateral and vertical extent of fuel hydrocarbon contaminants in the subsurface.
• Assessment of the nature and extent of free product (non-aqueous phase liquid [NAPL]), if present, and the initiation of NAPL recovery.
• Assessment of the nature and lateral extent of groundwater and soil contamination.
• Evaluation of the geologic and hydrogeologic characteristics of the subsurface.
• Initiation of a risk assessment.
Typical activities to take place under assessment of the site include the following:
• Conduct soil and groundwater sampling utilizing conventional boring or direct push technology, classification, and analysis.
• Install observation and monitoring wells.
• Perform soil, soil vapor, and groundwater analyses.
• Perform NAPL sampling and analyses, including forensic testing.
• Determine NAPL plume size and mass.
• Perform pump test and analyze data.
• Estimate the hydraulic conductivity.
• Initiate interim NAPL recovery.
• Prepare summary reports of activities.
• Present findings to DLA, regulatory agencies, and the public.
• Conduct risk assessment.
• Conduct treatability testing.
• Develop a Remedial Action Plan, as needed.
2.4.2 Remediation
Remediation includes removing contaminants from affected media, either through natural processes or by mechanical or chemical means, to reduce risks to receptors to acceptable levels.
Typical remediation activities include the following:
• Determine preferred remedial method.
• Implement the remedial action plan.
• For an active remediation system:
• Develop system drawings.
• Obtain stakeholder and regulatory concurrence.
• Procure system components.
• Install the remediation system.
• Prepare the Operation and Maintenance (O&M) manual.
• Operate and maintain the system.
2.4.3 Compliance
Compliance includes providing support in the form of studies, permit applications, disposal of petroleum waste products, and similar services to ensure the site remains in compliance with applicable Federal, State, and local environmental regulations.
2.4.4 Anticipated Activities Needing an Activity Hazard Analysis The phases of work and activities which are anticipated to require an Activity Hazard Analysis (AHA) consist of the following:
• Vehicle operations.
• Fueling operations.
• Equipment and materials handling.
• Groundwater sampling.
• Intrusive surface and subsurface work (drilling, soil sampling, and grading).
• Installation of groundwater monitoring, injection, and extraction wells including development/redevelopment and replacement.
• Treatment system operation and maintenance.
• Treatment system installation/expansion.
• Pressure washing and decontamination.
• Confined-space entry work (portable tank cleaning)
• Mobile crane operations.
• Concrete work.
• Site restoration.
• Hydroseeding.
• Radiographic testing of welds.
• Operating manlifts.
• Pump Lifting.
The AHAs for the anticipated phases of work are provided in Appendix C, Activity Hazard Analyses. Addendums, which may require the preparation of new AHAs, will be prepared as an APP Amendment prior to implementing work, as they are identified. Any amendments to this APP will be provided in Appendix D, Accident Prevention Plan Amendments.
3.0 Statement of Safety and Health Policy
This section presents the corporate safety policy, as well as safety program and accident experience goals.
3.1 Corporate Safety Policy
It is the policy of BFS, and a key component of our culture, to execute all of our activities in such a manner that will ensure the Health, Safety, and Environmental (HSE) protection of all our employees, clients, subcontractors, suppliers and the communities in which we live and work.
BFS will manage and apply our HSE Management System in such a manner that every employee shall be involved and ensure the effective implementation of our HSE Principles to assist the company in achieving our established goal of zero incidents.
All managers and supervisors of BFS have the responsibility to continuously improve HSE awareness among all employees, to manage proper usage of the environment, tools and equipment, and to create a culture in which everyone shares responsibility for the well-being of their fellow workers and the community.
All employees of BFS have the responsibility to execute their personal and work activities in such a manner as to prevent all circumstances which could lead to incidents that may cause personal injury or illnesses, security incidents, or environmental damage.
BFS will measure HSE performance and, by setting challenging objectives and targets, strive for continuous improvement.
BFS will implement this policy in combination with the HSE laws, regulations, standards, and codes of practice of our clients and all applicable governmental agencies.
3.2 Safety Program Goals, Objectives, and Accident Experience Goals BFS considers safety the highest priority and has established a goal of zero incidents for all projects. All projects will be conducted in a manner that minimizes the probability of near misses, equipment/property damage, or injury. BFS has established programs to recognize people and projects that demonstrate excellence in safety performance. BFS uses safety observation programs to identify and correct unsafe acts and conditions. Safety awareness programs are used to provide continuous training and development of good safety practices.
BFS site supervision will investigate all incidents to determine root causes and institute corrective actions to prevent recurrence. BFS provides and enforces safety rules to protect employees, subcontractors, clients, and the public.
The goals for safety performance and incident prevention for BFS projects are zero injuries and illnesses.
4.0 Responsibilities and Lines of Authority
This section presents BFS personnel with the overall health and safety responsibilities, competent persons, and lines of authority for implementing the health and safety program.
4.1 Employer Ultimate Responsibilities
BFS is ultimately responsible for the implementation of an effective safety and occupational health program. Managers must conduct business in compliance with governmental safety regulations and company procedures. The “rules of construction” for subcontractors apply as specified in 29 CFR 1926.16.
4.2 Personnel Identification and Accountability
The BFS has granted all employees stop work authorization, without fear of reprimand or retaliation to immediately stop work activity that presents a danger to employees, coworkers, our clients, partners, or the public. The PM, Site Manager/Construction Manager/SSHO, and HSEM are responsible for implementing this APP and enforcing the health and safety requirements.
Table 1 - Key Management Personnel, identifies the individuals that share the responsibility of implementing the health and safety program at the project site.
4.2.1 On-Site Personnel
All on-site personnel are responsible for continuous adherence to the requirements of the site HSE management system and this APP to prevent incidents, injuries/illnesses, and to ensure BFS achieves its objectives and target. All on-site personnel are:
• Authorized to stop any unsafe work activity or intervene with any unsafe work behaviors.
• Required to report any safety related work stoppages to their direct supervisor.
• Authorized to participate in activities to audit and ensure compliance with the site HSE management system.
• Required to adhere to the standards of the site HSE management system to ensure BFS achieves its objectives and target.
In no case may work be performed in a manner that conflicts with the inherent HSE precautions outlined in this APP. After due warning, personnel violating safety procedures will be dismissed from the site and possibly terminated from further work.
4.2.2 Project Manager
The PM, Mr. Mark Unruh, Professional Geologist (PG), has the overall responsibility for this project and overall accountability for the implementation of the HSE management system. The PM will provide allocated resources (people, financial) for implementation of the site HSE-management system. The PM will verify the requirements of the contract are fulfilled in a manner consistent with this APP, and the PM will issue communications to DLA Energy on the project status.
4.2.3 Site Manager/Construction Manager
The Site Manager/Construction Manager, Alonz Beehler, is the alternate on-site safety official and is the emergency response coordinator for all activities. The Site Manager/Construction Manager is responsible for the field implementation and enforcement of this APP for all activities. The Site Manager/Construction Manager will provide visible support for the site HSE management system and the objectives and targets identified. The Site Manager/Construction Manager is also responsible for the following:
• Inspecting site activities to identify safety and occupational health deficiencies, and coordinating the correction of potential deficiencies.
• Ensuring that tasks are performed by competent employees.
• Developing appropriate operational controls.
• Monitoring operational control activities, and ensuring that responsible people are maintaining the appropriate records in accordance with the HSE management system.
• Conducting safety meetings, and maintaining attendance records.
• Investigating accidents and illnesses, and implementing corrective actions as needed.
• Observing workers for symptoms of on-site exposure or stress.
• Arranging for on-site emergency medical care and first aid, as necessary.
• Determining evacuation routes and verifying that an effective means of emergency communication is always available while workers are on site.
• Establishing work zones.
• Reviewing this APP and providing input into the processes.
• Maintaining contact with the DLA representatives, the HSEM, and the PM.
• Explain the safety procedures involved with each task to employees, and check frequently to see that they understand and work as instructed.
• Prevent new employees from performing any tasks until required training is completed.
• Provide a safe work environment for employees and subcontractors. Immediately correct unsafe conditions.
• Ensure that employees are outfitted with appropriate PPE.
• Set a good safety example.
• Confirm subcontractor safety performance records have been verified prior to contract award and monitor subcontractor performance during operations.
• Report all incidents in accordance with Incident Notification procedure, CMS-710-05-
PR-02200.
Daily safety inspections will be used to determine if operations are being conducted in accordance with this APP and applicable regulatory guidelines. The Site Manager/Construction Manager reports to the PM. The Site Manager/Construction Manager will also serve as the alternate SSHO. A resume for the Site Manager/Construction Manager is included in Appendix E.
4.2.4 Site Safety and Health Officer
The primary SSHO, Alonzo Beehler, verifies that operations are being conducted in accordance with this APP and applicable regulatory guidelines. The primary and alternate SSHOs have the authority to suspend operations at the project due to noncompliance and is responsible for the following:
• Being present during operations to implement this APP.
• Inspecting site activities to identify safety and occupational health deficiencies, and coordinating the correction of potential deficiencies.
• Coordinating changes/modifications to this APP with the HSEM and the PM.
• Conducting exposure monitoring and/or air sampling.
• Selecting and/or adjusting personal protective equipment (PPE) use.
• Communicating the HSE policies and procedures.
• Obtaining and maintaining site HSE documentation including but not limited to training records, MSDSs, inspection logs, permits, clearances and monitoring records
• Identifying and reviewing the environmental aspects of the project and providing recommendations for continuous improvement.
• Identifying and routinely monitoring applicable legal and other requirements as they relate to the project.
• Notifying personnel, and providing training, if necessary, to meet regulations/requirements.
• Reviewing action items and identifying milestones/resources necessary to achieve the objectives of the HSE management system.
• Communicating the HSE management system structure and responsibilities.
• Providing periodic reviews of the HSE management system to ensure continued applicability and adherence to corporate HSE management system expectations.
• Ensuring approved resources are allocated appropriately for the effective implementation of the HSE management system.
• Reporting on the performance of the HSE management system to the HSEM for review and as a basis for improvement.
• Monitoring the practical implementation of the site HSE management system.
• Maintaining records for project activities.
• Identifying and documenting HSE training needs/plans for employees considering their roles, responsibilities, and other requirements.
• Scheduling and conducting the training of the site HSE management system.
• Ensuring that tasks are performed by competent employees.
• Managing the processes by which HSE performance is communicated internally at the site.
• Ensuring that relevant work instructions/requirements are communicated to affected employees, suppliers, and contractors.
• Establishing, reviewing, revising, and testing the site emergency preparedness plan/procedures.
• Documenting the results of environmental performance.
• Reviewing and approving this APP by signature.
• Being the on-site contacts for regulatory agencies on matters of HSE.
• Establishing employee exposure monitoring notification programs.
• Maintaining the project health and safety bulletin board.
• Verifying that decontamination procedures meet established criteria when necessary.
• Monitoring employee work hours and limiting excessive work hours.
The SSHOs are the Site Health, Safety, and Environmental Managers in regards to the BFS Management System. The SSHOs report to the HSEM. Resumes for the SSHOs are included in Appendix E, Safety Personnel Resumes and Proof of Training and Competency.
4.2.5 Program Health, Safety, and Environment Manager
The HSEM, Sally Smith Sally S. Smith, CIH, CSP, CHMM, CPEA is responsible for the following actions:
• Developing, maintaining, and overseeing the implementation of this APP.
• Visiting the project as needed to assess the effectiveness of this APP and compliance with the HSE management system.
• Remaining available for project emergencies.
• Developing modifications to this APP as needed.
• Evaluating occupational exposure monitoring/air sampling data and adjusting requirements of this APP, as necessary.
• Approving this APP by signature.
Resumes for the HSEMs are included in Appendix E, Safety Personnel Resumes and Proof of Training and Competency.
4.2.6 Contracting Officer’s Representative
The Contracting Officer’s Representative (COR), Mr. William Potter, is the DLA individual designated and authorized in writing by the contracting officer, Ms. Heather Adams, Contracting Officer, to perform specific technical or administrative functions.
4.2.7 Visitors
Visitors to Point Loma shall check in with the Site Manager/Construction Manager/SSHO in order to verify that all appropriate entry requirements are met. All visitors will be provided an abbreviated site safety orientation by the Site Manager/Construction Manager/SSHO which includes a discussion of their stop work authority, the hazards to be expected on the site, the safety and health controls required, and emergency procedures with emergency contact information. Visitors shall be provided information on the hazardous chemicals to which they may be exposed, the precautions they may take to lessen the possibility of exposure, the location of the material safety data sheets (MSDSs) and safety data sheets (SDSs), and an explanation of the labeling system used at the project.
The Site Manager/Construction Manager/SSHO will verify that all visitors entering the sites are properly protected and provided with the appropriate PPE. A stock of common PPE (e.g., hard hats, eye protection, hearing protection, reflective vests, etc.) will be maintained at the project for use by visitors. Visitors are responsible for providing their own respiratory protection, if required, as BFS cannot provide respiratory protection to visitors.
4.3 Competent and Qualified Person Qualifications
A designated competent person is one who is capable of identifying existing and predictable hazards (unsanitary, hazardous, or dangerous to employees) in the surrounding/working conditions and has authorization to take prompt corrective measures to eliminate the hazard. A designated qualified person is one who must have a recognized degree, certificate, or extensive experience and ability to solve the subject problems at the worksite. BFS policy requires a competent person or qualified person be designated in writing at the project location to address certain specific hazards and safety responsibilities.
As required by Safety and Health Requirements Manual, EM 385-1-1, Section 01.A.17 (USACE, 2008), the primary and alternate SSHO are BFS’s competent person(s) for this project as defined by 29 CFR 1926.32(f). At a minimum, the primary and alternate SSHO must have completed the 30-hour OSHA construction safety class or 30 hours of formal construction safety and health training covering the subjects of the OSHA 30-hour course, applicable to the work to be performed, and given by qualified instructors. Alonzo Beehler is the primary SSHOs.
Sally Smith Sally S. Smith, CIH, CSP, CHMM, CPEA, a qualified persons as required by Safety and Health Requirements Manual, EM 385-1-1, Section 01.A.17 (USACE, 2008), is the site HSEMs. The HSEM fulfills the requirements for providing a qualified industrial hygienist and qualified safety professional.
Qualified personnel are provided to administer first aid and cardiopulmonary resuscitation (CPR) with training certified by the American Red Cross. The identification of designated qualified personnel is provided in Table 2, CPR and First Aid Training Completion Dates. Proof of qualifications and competency (certificates of completed training) for personnel designated to administer first aid and CPR are included in Appendix E.
There are additional requirements for site-specific competent and qualified persons. These additional requirements and the procedure used to identify and document the competent and qualified persons are detailed in the following section, Competent and Qualified Person Requirements.
4.4 Competent and Qualified Person Requirements
No work will be performed unless the required competent/qualified person or the designated alternate competent/qualified person is present on the job site. The CMS-710-02-PR-04200, Competent/Qualified Person Procedure (Appendix G, Referenced HSE Procedures) is used to identify and document the site-specific competent and qualified persons. The Site Manager/Construction Manager/SSHO is responsible for implementing and enforcing the procedure, monitoring compliance with the procedure, and verifying that all competent persons have the necessary knowledge in their specific area(s). The choice of competent or qualified person is made according to supervisory responsibility, qualifications, experiences, and is designated by BFS management to perform duties required by BFS policy and applicable regulatory standards. The following outlines the procedure for designating the appropriate competent and/or qualified persons:
• The Site Manager/Construction Manager/SSHO shall review the list of standards contained in CMS-710-02-FM-04201, Competent Person Designation Form (Appendix H) that require a competent person, determine which apply to the SOW, and then designate the required competent person by name or job title on the form.
This shall be completed prior to the necessity for the use of that competent person.
• The Site Manager/Construction Manager/SSHO shall review the list of standards contained in CMS-710-02-FM-04202, Qualified Person Designation Form (Appendix H) that require a qualified person, determine which apply to the SOW, and then designate the required qualified person by name or job title on the form. This shall be completed prior to the necessity for the use of that competent person.
• The Site Manager/Construction Manager/SSHO shall maintain and update the CMS- 710-02-FM-04201, Competent Person Designation Form (Appendix H) and CMS- 710-02-FM-04202, Qualified Person Designation Form (Appendix H) on an annual basis, when personnel or requirements change, and when additional or different competent and/or qualified persons become necessary.
• The CMS-710-02-FM-04201,…