ATTACHMENT 12 - DFSP Pt. Loma CPSMR.pdf

PDF 574 KB Posted

Attached to
SPE603-22-R-0509 - DFSP Point Loma Environmental Restoration, Compliance, and Facility Management Services
Solicitation number
SPE60323D5002
Issued by

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

Page 1 of 2 Point Loma CPSMR

Date: 01 July 2022

Contractor’s Progress, Status and Management Report:

June 2022

CLIN 0001 – On-site Work (DLA Contract SPE603-18-D-5007)

Professional Services and Remedial Systems O&M

• The remediation systems remained operational during the reporting period. No loss of hydraulic control in the groundwater occurred.

• Coordination with NBPL Environmental Office continued through the reporting period.

o Provided total extracted NAPL numbers for their use in reports to the base commander.

o Renewing base passes for groundwater sampling personnel.

• Performed weekly and monthly well gauging (water level and NAPL level measurements) for selected wells through the period.

• Provided Bhate contact information and links to the State of California Geotracker website to the NAVFAC SW planning team for any questions they may have regarding their designs for a new construction project.

• NAPL measurements and system readings at the sumps were performed through the period.

• Received the State of California RWQCB “Annual Estimation Letter for Site Cleanup Cost Recovery - NBPL Fuel Farm”. The RWQCB was notified of the receipt of the estimate.

• Provided the DLA with estimates for groundwater modeling and a facility monitoring plan update.

• Provided the DLA contract specialist with information regarding the base EMS and contact information.

• Arranging for a subcontractor to change out the carbon filter media. Sampled the carbon for the sub to determine proper disposal of the carbon as part of the estimate.

• Treated water from RO units sent to Connection 220 (5/22/2022 through 6/22/2022):

- RO Unit 1: 307,184 gallons

- RO Unit 2: 180,013 gallons

Total treated water discharged to Connection 220 (5/22/2022 through 6/22/2022) was 787,397 gallons.

During the month of June, NAPL was recovered at an average daily rate of approximately 33 gallons per day.

DFSP PT. LOMA ENVIRONMENTAL SERVICES SPE60323D5002 ATTACHMENT # 12

DFSP PT. LOMA ENVIRONMENTAL SERVICES SPE60323D5002 ATTACHMENT # 12

Page 1 of 2 Point Loma CPSMR

Date: 01 August 2022

Contractor’s Progress, Status and Management Report:

July 2022

CLIN 0001 – On-site Work (DLA Contract SPE603-18-D-5007)

Professional Services and Remedial Systems O&M

• The remediation systems remained operational during the reporting period. No loss of hydraulic control in the groundwater occurred.

• Coordination with NBPL Environmental Office continued through the reporting period.

o Provided total extracted NAPL numbers for their use in reports to the base commander.

o Renewing base passes for groundwater sampling personnel.

• Performed weekly and monthly well gauging (water level and NAPL level measurements) for selected wells through the period.

• Provided the DLA with the Q3 self-evaluation for Point Loma

• Conducted sampling for the 2022 annual groundwater monitoring event.

• NAPL measurements and system readings at the sumps were performed through the period.

• Arranging for a subcontractor to change out the carbon filter media. Sampled the carbon for the sub to determine proper disposal of the carbon as part of the estimate.

• Arranging for a subcontractor to service the three site compressors.

• Treated water from RO units sent to Connection 220 (6/22/2022 through 7/22/2022):

o RO Unit 1: 256,053 gallons o RO Unit 2: 168,994 gallons

• Total treated water discharged to Connection 220 (6/22/2022 through 7/22/2022) was 746,415 gallons.

• During the month of July, NAPL was recovered at an average daily rate of approximately 30 gallons per day. The reduced average daily rate for the month is due to a slowdown in recovery during and following the July 4th holiday. At that rime the HW pumps were slowed by a programing issue. The issue has been addressed. During the last week in July the average daily recovery rate was restored to 50 gpd.

• On 7/19/22, two trucks from World Oil collected 13,070 gallons for off-site recycling. The total volume of recovered oil purchased and/or transported offsite by World Oil since the beginning of the contract is 73,179 gallons. At the current production rate, the next off-site shipment should occur in 2023.

Page 2 of 2 Point Loma CPSMR

Anticipated activities for the upcoming reporting period.

• Continue coordination with, and reporting to, the NBPL Environmental Office.

• Ongoing O&M of the remedial systems (well gauging, NAPL measurements, system readings).

• Complete the change out of the carbon and clay filter media.

• Complete servicing the three site compressors.

CLIN 0002 – On-site Work (DLA Contract SPE603-18-D-5007)

• The first portable extraction system is pumping at well 10MW-31 near Rosecrans Street.

• The second portable extraction system is pumping at well PZ-19 on the west side of the site.

Anticipated activities for the upcoming reporting period.

• Continue pumping at well PZ-19

• Continue pumping at well 10MW-31.

Financial Status and POP Summary (All Delivery Orders)