Attachment_5__CA_-_Clean_Agent_and_CO2_Test_Form_(1).pdf
PDF 168 KB Posted
- Attached to
- AKRO STRCUTURAL FIRE SUPPRESSION & CONTROL EQUIP I Federal contract opportunity
- Solicitation number
- 140P9726Q0017
About this file
This is an Inspection and Test Report form used by the National Park Service Alaska Regional Office (AKRO) to document the inspection and testing of clean agent or CO2 fire suppression systems in park facilities.
The form requires completion of a comprehensive 27-point inspection checklist covering enclosure integrity, nozzles, piping, hose, cylinders, extinguishing agent quantity and pressure, detection and control devices, release mechanisms, abort devices, auxiliary functions, system monitoring, and personnel training. Technicians must verify compliance with NFPA 2001 and NFPA 12 standards and document specific measurements for up to five agent cylinders, including serial numbers, PSI, gross weight, agent weight, tare weight, liquid level, and hydrostatic test dates. The form includes sections for identifying deficiencies found during inspection, recommended resolutions with NFPA code references, and certification by a state-certified or NICET-certified technician with signature, company affiliation, and certification numbers. A dedicated deficiencies section on page four allows detailed documentation of any non-conformances, their locations, recommended corrective actions, and NFPA references, with space to indicate whether each deficiency has been resolved. The document is formatted to require a separate form completion for each system inspected.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_2_-_SOW.pdf | ||
| Attachment_1_Structural_Fire_Asset_Details.pdf | ||
| Attachment_4__BP_-_Backflow_Device_Test_Form.pdf | ||
| Attachment_7__FA_-_Fire_Alarm_Test_Form_(1).pdf | ||
| B03_DOL_WD_2015-5681_Rev_25.pdf | ||
| Sol_140P9726Q0017.pdf | ||
| Attachment_6__DC_-_Dry_Chemical_Test_Form_(1).pdf | ||
| B03_DOL_WD_2015-5683_Rev_25.pdf | ||
| B03_DOL_WD_2015-5685_Rev_27.pdf | ||
| B03_DOL_WD_2015-5687_Rev_27.pdf | ||
| Attachment_3__DENA_Coordination_Requirements_1-23-20_(1).pdf | ||
| Attachment_8__FP_-_Fire_Pump_Test_Form_(1).pdf | ||
| B08_Subcontracting___Worksheet.xlsx | XLSX spreadsheet | |
| Attachment_9__SP_-_Fire_Sprinkler_Test_Form_(1).pdf | ||
| Attachment_10__NPS_FILLABLE_INVENTORY_FORM_Vez_(1).xlsx | XLSX spreadsheet |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clean Agent or CO2 System Page 1 of 4 Revised 12/17/25
National Park Service / AKRO
Inspection and Test Report (complete a separate form for each system)
CLEAN AGENT OR CO2 SYSTEM – CLEAN AGENT CO2
Park Alpha Code: ______________________ FMSS Location No.:___________________
Location Description: ______________________
Date of Test:_________________________
Time:_________________
System Make: ______________________ System Model: _____________________
No of Cylinders ______________________ No. of Nozzles _____________________
Control Panel Make ______________________ Panel Model _____________________
DEFICIENCIES FOUND? Yes No List items that were not corrected. Use the Deficiencies section or attach itemized sheet
REPAIRS: All deficiencies have been corrected N/A Yes No
This certifies that the fire and life safety system has been inspected and tested for functional operation in accordance with applicable NFPA 2001 & 12 standards and has been properly tagged and/or labeled. Any discrepancies found are noted in this report with code references for corrective action by the Owner/Responsible Person.
Technician Name (printed): ______________________ Company: ______________________________
Signature: ___________________________________ Phone #: _______________________________
State Certification No.: _________________________
National/NICET No.: ___________________________
ENCLOSURE INTEGRITY
1. After visual inspection, there are no unsealed penetrations in walls, ceiling, and floors that would affect enclosure integrity.
Yes No
2. Doors in the protected enclosure are self-closing and provided with sweeps/gaskets Yes No
3. HVAC penetrations in the protected enclosure that could affect agent hold time are provided with low-leakage dampers.
Yes No
NOZZLES, PIPING, AND HOSE
4. All nozzles, piping, and brackets are properly placed and are secured. Yes No
5. All hose was visually inspected and does not have visual defects. Yes No
6. All hose five years old and older have been tested in 5-year intervals in accordance with NFPA 2001 Section 11.7. N/A’ for CO2 systems . Yes No
• Date for Next Hose Test: ___________ • •
7. All hose five years old and older has been tested in 5-year intervals in accordance with NFPA 12, Section 4.8.2. Yes No
Clean Agent or CO2 System Page 2 of 4 Revised 12/17/25
CYLINDERS AND EXTINGUISHING AGENT
8. The quantity loss is <5% and the pressure loss is <10% in each cylinder from the required quantity and pressure of the extinguishing agent.
Yes No
9. There is an up-to-date log containing a record of semi-annual checks for the agent quantity and pressure on each cylinder
Yes No
10. All cylinders with an unacceptable quantity loss were refilled or replaced.
N/A Yes No
11. All cylinders are tested and inspected according to NFPA 2001, Section 11.6.1 and 11.6.2 at the proper intervals.
Yes No
Date for next cylinder test____________
12. System passed actuating test without discharging carbon dioxide agent. Yes No
DETECTION AND CONTROL
13. All detection/initiating devices respond properly when tested.
No. of Units Tested Manual Stations ________________ Smoke Detectors ________________ Heat Detectors ________________ Air Sampling Detectors ________________ Tamper Switches ________________ Other ________________
N/A Yes No
14. All alarm functions take place upon receipt of a signal from the detection devices.
N/A Yes No
15. All alerting / notification devices work properly.
No. of Units Tested Pre Discharge Devices ________________ Post Discharge Devices ________________
16. All supervised circuits send the proper signals to the control panel. N/A Yes No
17. All manual release stations are readily accessible, accurately identified, and properly protected to prevent damage.
Clean Agent or CO2 System Page 3 of 4 Revised 12/17/25
RELEASE DEVICES
18. The automatic release device(s) work properly, including pre-discharge time delays.
19. All manual release stations used to release agents work properly. N/A Yes No
ABORT DEVICES
20. The manual abort switch is a dead-man type switch and functions properly.
AUXILIARY FUNCTIONS
21. All auxiliary functions such as alarm-sounding or displaying devices, remote annunciators, air-handling shutdown, damper operation, and power shutdown operate properly in accordance with system requirements and design specifications.
N/A Yes No
22. The alarms can be silenced, when allowed, without affecting other system functions.
SYSTEM MONITORING
23. The suppression control panel sends the proper signals to the building FACP.
N/A Yes No
24. The suppression control panel operates on standby power N/A Yes No
25. Signals were received at the monitoring company. N/A Yes No
TRAINING
26. All personnel working in enclosures protected by a clean agent system have received up-to-date training regarding clean agent safety issues.
Type of Extinguishing Agent ___________________
Agent Cylinders #1 #2 #3 #4 #5
Serial No. __________ __________ __________ __________ __________
PSI __________ __________ __________ __________ __________
Gross Weight __________ __________ __________ __________ __________
Agent Weight __________ __________ __________ __________ __________
Tare Weight __________ __________ __________ __________ __________
Liquid Level __________ __________ __________ __________ __________
Hydro Date __________ __________ __________ __________ __________
27. Cylinders passed hydrostatic tests. N/A’ . Yes No
Clean Agent or CO2 System Page 4 of 4 Revised 12/17/25
Deficiencies
Resolved
Location:
Deficiency:
Recommended Resolution:
NFPA reference: