Attachment 4 - Specifications.pdf

PDF 148 KB Posted

Attached to
NRS Rhinelander Vinyl Flooring Replacement
Solicitation number
12445526Q0034
Issued by

About this file

This document contains the specifications for the Northern Research Station NRS Rhinelander 1st Floor Flooring Replacement project located at 5985 Hwy K, Rhinelander, WI 54501. The Owner is the USDA Forest Service – Northern Research Station, with Jeremy Kasprak serving as the Contracting Officer's Representative. The project involves demolition of existing flooring and installation of new resilient tile flooring with vinyl base and accessories. The contractor must submit a construction schedule within 14 days of the Notice to Proceed and provide a minimum two-week advance notice before beginning work. Work is restricted to normal business hours of 8:00 a.m. to 4:30 p.m., Monday through Friday, excluding Federal Holidays, and the facility requires all doors to remain locked 24 hours per day with COR escort for site access. The contractor is responsible for protecting or relocating all room furnishings and returning them to original locations upon completion, obtaining written COR approval for temporary storage locations.

The flooring specification requires installation of vinyl composition tile flooring with an example acceptable product of Karndean Designflooring Van Gogh Gluedown (interlocking, 20MIL wear course, 48 inches by 6 inches, waterproof luxury vinyl plank) in a light color complementing adjacent remaining flooring, with options submitted to the COR for selection. The vinyl base shall be ASTM F1861 Type TV (solid, homogeneous) with a minimum thickness of 0.125 inches and height of 5 inches, including cove-style base and vinyl molding accessories for smooth transitions. Both flooring products carry a 20-year commercial warranty. The contractor must provide product data, samples, and shop drawings as action submittals, with an initial review period of 15 days and resubmittal review period of 15 days. Extra materials equal to 2 percent of the amount installed must be delivered to the Owner from the same production run. Installation must comply with manufacturer's written instructions, including proper substrate preparation per ASTM F710, with materials acclimated at least 48 hours before installation. The site maintains full Owner occupancy during construction, and all construction waste must be removed and legally disposed of without burning.

View the file

Other files

File Type Posted
260316 Q and A.docx DOCX document
260302 SF 30.pdf PDF
Attachment 3 - SOW.pdf PDF
Attachment 5 - Wage Determination WI20260011 Oneida County.pdf PDF
Attachment 1 - Solicitation 12445526Q0034.pdf PDF
Attachment 2 - Schedule of Items.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Northern Research Station

NRS Rhinelander 1st Floor - Flooring Replacement

Specifications

011000 – Summary

013300 – Submittal Procedures

017419 – Construction Waste Management and Disposal

024119 – Selective Demolition

096513 – Resilient Base and Accessories

093519 – Resilient Tile Flooring

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Contractor's use of site and premises.

4. Coordination with occupants.

5. Work restrictions.

6. Specification and Drawing conventions.

1.2 PROJECT INFORMATION

A. Project Identification: Rhinelander WI Flooring Replacement

1. Project Location: 5985 Hwy K Rhinelander WI 54501

B. Owner: USDA Forest Service – Northern Research Station

1. Contracting Officer’s Representative: Jeremy Kasprak-

Jeremy.kasprak@usda.gov

2. Site Contact: Jeremy Kasprak

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. Please reference Statement of work and other Contract Documents.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.4 CONTRACTOR'S USE OF SITE AND PREMISES

A. Limits on Use of Site:

1. Limit use of Project site to areas immediately in the area of work, unless otherwise approved by COR. Do not disturb portions of Project site beyond areas in which are required to complete the contract work.

2. Driveways, Walkways, and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials unless approved by the COR.

B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.

Repair damage caused by construction operations.

C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.5 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy site and existing building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with

Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.

B. Within 14 Days of the Notice to Proceed a Schedule is to be submitted to COR and CO.

Notify COR a minimum of two weeks prior to beginning work.

C. All room furnishings and belongings will need to be protected or relocated by the contractor and returned to their original location upon completion of the work. Obtain written COR approval of the temporary storage location. Temporary storage will need to comply with safety ingress and egress regulations. Blocking access to areas of the building will not be permitted unless prior approval is received in writing from the COR.

1.6 WORK RESTRICTIONS

A. Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.

2. At the end of each working day, the work area must be accessible and safe.

Remove all loose construction debris, materials, and tools from walkways and access areas.

3. Contractor is responsible for moving and returning all furniture and contents to its original location as necessary for floor replacement.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 8:00 a.m. to 4:30 p.m., Monday through Friday (except Federal Holidays), unless otherwise indicated.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by

Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify COR not less than seven days in advance of proposed utility interruptions.

2. Obtain COR written or verbal permission before proceeding with utility interruptions.

D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.

1. Notify COR not less than seven days in advance of proposed disruptive operations.

2. Obtain COR written permission before proceeding with disruptive operations.

1.7 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the

Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.

3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the

Specifications. Unless otherwise indicated, linked information is not part of the

Contract Documents.

4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the

Work of all Sections in the Specifications.

1.8 SECURITY

A. This is a secure facility, and all doors are to remain locked 24 hours a day.

B. Coordinate with COR for building access.

C. COR will escort the contractor to worksite and manage daily sign-in and sign-out of all contractor and subcontractor’s staff. There is no anticipated unescorted work and if desired would require a federal background check.

PART 2 - PRODUCTS

A. Reference Sections:

1. 096513 – RESILIENT BASE AND ACCESSORIES

2. 096519 – RESILIENT TILE FLOORING

END OF SECTION 011000

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

1.2 DEFINITIONS

A. Approval: Equivalent to “No Exception Taken”.

B. Approved or Approved Equivalent: To possess the same performance qualities and characteristics and fulfill the utilitarian function without any decrease in quality, durability or longevity. For equipment/products defined by the Contractor as

"equivalent", substitution requests must be submitted to Contracting Officer’s

Representative for consideration and be approved by the COR in writing. Approval shall constitute “No Exception Taken” and shall not be otherwise construed.

C. "No Exception Taken" constitutes that review is for general conformance with the design concept expressed in the Contract Documents for the limited purpose of checking for conformance with information given. Any action is subject to the requirements of the Contract Documents. Contractor is responsible for the dimensions and quantity and will confirm and correlate at the job site, fabrication processes and techniques of construction, coordination of the work with that of all other trades, and the satisfactory performance of the work.

D. Action Submittals: Written and graphic information and physical samples that require

CO or COR’s responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

E. Informational Submittals: Written and graphic information and physical samples that do not require CO or COR’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.3 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Contract Name and Number.

2. Date.

3. Name of Contractor.

4. Name of firm or entity that prepared the submittal

5. Names of subcontractor, manufacturer, and supplier.

6. Category and type of submittal.

7. Submittal Purpose and description.

8. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

9. Drawing number and detail references, as appropriate.

10. Indication of full or partial completion.

11. Consecutive transmittal number.

12. Submittal and transmittal distribution record.

13. Other necessary identification.

14. Remarks.

1.4 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections as PDF electronic files and as indicated for samples and other physical submittals. Types of submittals are indicated in individual Specification Sections.

B. Submittals shall be transmitted via email to the COR & CO.

C. Identify and incorporate information in each electronic submittal file as follows:

1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form acceptable to Government with links enabling navigation to each item.

2. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by COR.

D. Coordination: Coordinate preparation and processing of submittals with performance of construction activities

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same

Specification Section as separate packages under separate transmittals.

4. Coordinate transmittal of different types of submittals for related parts of the

Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Contracting Officer or COR reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

E. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer's and COR’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals

1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

Contracting Officer or COR will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process intermediate review in same manner as initial submittal.

3. Resubmittal Review: Allow 15 days for review of each resubmittal.

4. Sequential Review: Where sequential review of submittals by Contracting

Officer's consultants, Government, or other parties is indicated, allow 21 days for initial review of each submittal.

F. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Indicate date and content of previous submittal.

2. Indicate date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are approved in writing by the CO or COR (in a method acceptable to the specifications or as otherwise described by the CO).

G. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

H. Use for Construction: Retain complete copies of submittals on Project site. Use only final action or material submittals that are approved in writing by the Contracting Officer or

COR.

1.5 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product

Data.

2. Clearly mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. Submit Product Data before Shop Drawings, and before or concurrent with

Samples.

5. Submit Product Data in PDF electronic file.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated

2. Submit Shop Drawings in PDF Electronic Format.

C. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.

D. Design Data/Product Data/Materials Submittals: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.

E. Certificates:

1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide original paper copy where a notarized signature is required.

2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the

Contract Documents. Include evidence of manufacturing experience where required.

4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents

F. Test and Research Reports:

1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract

Documents.

3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract

Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:

7. Name of evaluation organization.

8. Date of evaluation.

9. Time period when report is in effect.

10. Product and manufacturers' names.

11. Description of product.

12. Test procedures and results.

13. Limitations of use.

1.6 CONTRACTOR'S REVIEW

A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with contractor approval before submitting to

Contracting Officer and COR.

B. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform written approval method. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents

1.7 GOVERNMENT REVIEW

A. Contracting Officer’s Representative (COR) may approve technical submittals, unless otherwise indicated by the contract documents or determined in writing by the

Contracting Officer (CO). COR may review each submittal instead of the CO.

B. Action Submittals: Will be reviewed and their approval status will be documented in a project submittal review XLS spreadsheet returned to the contractor. The specific material items will be included in this review document and notes for approval, disapproval, and resubmittal and any questions on items.

C. All submittals reviewed will be approved in the material review spreadsheet only. This will be returned to contactor with each submittal group reviewed.

D. No marked up copies of material cut sheets will be returned to the contractor.

E. Informational Submittals: Contracting Officer or COR will review each submittal and will not return it, or may return it if it does not comply with requirements. Contracting

Officer or COR may forward each submittal to appropriate party. Contractor is responsible for compliance with contract requirements and all applicable laws and regulations regardless of whether mistakes were discovered by CO or COR review of informational submittals.

F. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from COR or Contracting Officer.

G. Incomplete submittals are unacceptable, will be considered nonresponsive, and may be returned for resubmittal without review.

H. Submittals not required by the Contract Documents may be returned by Contracting

Officer or COR without action.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013300

SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for the following:

1. Disposing of nonhazardous construction waste.

1.2 DEFINITIONS

A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations.

Construction waste includes packaging.

B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations.

C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction, or designated spoil areas on Owner’s property.

1.3 PERFORMANCE GOAL

A. Salvage/Recycle Goals: Government’s goal is to salvage and recycle as much non-hazardous demolition and construction waste as possible.

PART 2 - EXECUTION

2.1 DISPOSAL OF WASTE

A. General: Remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.

1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn waste materials.

END OF SECTION 017419

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. The Work of this Section Includes:

1. Demolition and removal of selected portions of exterior or interior of building or structure and site elements.

1.2 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1. Carefully salvage in a manner to prevent damage and promptly return to

Owner.

1.3 FIELD CONDITIONS

A. Owner will occupy the building and areas immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by

Owner as far as practical.

C. Notify COR of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. On-site sale of removed items or materials is not permitted.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction. Comply with OSHA Safety regulations during demolition.

B. Standards: Comply with ANSI/ASSP A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations, as necessary.

B. Photograph any existing building damage prior to beginning selective demolition operations. Notify the CO and COR of any discovered damage.

3.2 PREPARATION

A. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

B. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain. This includes any regulation required blocking or modification of the HVAC system to protect building occupants.

C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by COR, items may be removed to a suitable, protected storage location and reinstalled in their original locations after selective demolition operations are complete. All room furnishings and belongings will need to be protected or relocated by the contractor and returned to their original location upon completion of the work.

3.3 UTILITY SERVICES AND BUILDING SYSTEMS

A. Existing Services/Systems to Remain: Maintain utilities and building systems and equipment to remain and protect against damage during selective demolition operations.

3.4 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

B. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

C. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

D. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

E. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

F. Any damage caused during the selective damage must be repaired by the contractor.

G. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

3.5 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site and recycle or dispose of them in accordance with Section 017419 "Construction Waste Management and Disposal."

B. Do not allow demolished materials to accumulate on-site.

C. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

D. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

E. Comply with requirements specified in Section 017419 "Construction Waste

Management and Disposal."

F. Burning: Do not burn demolished materials.

3.6 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 024119

SECTION 096513 - RESILIENT BASE AND ACCESSORIES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Vinyl base.

2. Vinyl molding accessories

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Samples: For each exposed product and for each color and texture specified.

1.3 CLOSEOUT SUBMITTALS

A. Maintenance data.

B. Warranty information.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are competent in techniques required by manufacturer for floor installation.

1.5 WARRANTY

A. Warranty Period: Manufacturer's standard warranty against manufacturing defects and wearing for flooring are as follows

1. 20-year commercial warranty.

1.6 EXTRA MATERIALS

A. Deliver to Owner extra materials from same production run as products installed. Package products with protective covering and identify with descriptive labels.

1. Quantity: Furnish quantity of flooring units equal to 2 percent of amount installed. Delivery, Storage and Protection: Comply with Owner's requirements for delivery, storage, and protection of extra materials.

PART 2 - PRODUCTS

2.1 VINYL BASE

A. Product Standard: ASTM F1861, Type TV (vinyl, thermoplastic).

B. Group: I (solid, homogeneous)

C. Style and Location:

1. Cove: Provide in areas with resilient floor coverings.

D. Minimum Thickness: 0.125 inch (3.2 mm)

E. Height: 5 inches (102 mm)

F. Lengths: Coils in manufacturer's standard length

G. Outside Corners: Job formed or preformed.

H. Inside Corners: Job formed or preformed.

I. Colors and Patterns: For each exposed product and for each color and texture specified.

2.2 VINYL MOLDING ACCESSORY

A. Description: Vinyl cap for cove resilient floor covering, nosing for resilient floor covering, reducer strip for resilient floor covering, transition strips.

B. Locations: Provide vinyl molding accessories as needed for smooth and professional transitions to existing.

C. Colors and Patterns: For each exposed product and for each color and texture specified.

2.3 INSTALLATION MATERIALS

A. Trowelable Leveling and Patching Compounds: Latex-modified, portland-cement-based or blended hydraulic-cement-based formulation provided or approved by resilient-product manufacturer for applications indicated.

B. Adhesives: Water-resistant type recommended by resilient-product manufacturer for resilient products and substrate conditions indicated.

PART 3 - EXECUTION

3.1 PREPARATION

A. Prepare substrates according to manufacturer's written instructions to ensure adhesion of resilient products.

B. Remove all previous adhesives.

C. Fill cracks, holes, and depressions in substrates with trowelable leveling and patching compound; remove bumps and ridges to produce a uniform and smooth substrate.

D. Do not install resilient products until materials are the same temperature as space where they are to be installed.

3.2 RESILIENT BASE INSTALLATION

A. Comply with manufacturer's written instructions for installing resilient base.

B. Apply resilient base to walls, columns, pilasters, casework and cabinets in toe spaces, and other permanent fixtures in rooms and areas where base is required.

C. Install resilient base in lengths as long as practical without gaps at seams and with tops of adjacent pieces aligned.

D. Tightly adhere resilient base to substrate throughout length of each piece, with base in continuous contact with horizontal and vertical substrates.

E. Do not stretch resilient base during installation.

F. Preformed Corners: Install preformed corners before installing straight pieces.

G. Job-Formed Corners:

1. Outside Corners: Use straight pieces of maximum lengths possible and form with returns not less than 3 inches (76 mm) in length.

a. Form without producing discoloration (whitening) at bends.

2. Inside Corners: Use straight pieces of maximum lengths possible and form with returns not less than 3 inches (76 mm) in length.

3.3 RESILIENT ACCESSORY INSTALLATION

A. Comply with manufacturer's written instructions for installing resilient accessories.

B. Resilient Molding Accessories: Butt to adjacent materials and tightly adhere to substrates throughout length of each piece. Install reducer strips at edges of floor covering that would otherwise be exposed.

3.4 CLEANING AND PROTECTION

A. Comply with manufacturer's written instructions for cleaning and protecting resilient products.

END OF SECTION 096513

SECTION 096519 - RESILIENT TILE FLOORING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Vinyl composition floor.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Samples: For each exposed product and for each color and pattern specified.

1.3 CLOSEOUT SUBMITTALS

A. Maintenance data.

B. Warranty information.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are competent in techniques required by manufacturer for floor installation.

1.5 WARRANTY

A. Warranty Period: Manufacturer's standard warranty against manufacturing defects and wearing for flooring are as follows

1. 20-year commercial warranty.

1.6 EXTRA MATERIALS

A. Deliver to Owner extra materials from same production run as products installed. Package products with protective covering and identify with descriptive labels.

1. Quantity: Furnish quantity of flooring units equal to 2 percent of amount installed. Delivery, Storage and Protection: Comply with Owner's requirements for delivery, storage, and protection of extra materials.

PART 2 - PRODUCTS

2.1 VINYL COMPOSITION FLOOR

A. Example Acceptable Manufacturer and Product, provide options meeting the requirements of this section to COR for approval.

1. Karndean Deasignflooring, Van Gogh Gluedown, interlocking; 20MIL

Wearcourse, 48 in. X 6 in. Waterproof Luxury Vinyl Plank Flooring

B. Wearing Surface: Smooth

C. Wearing Surface Thickness: 20mm or greater.

D. Size: 12 by 12 inches (305 by 305 mm) or greater for Tile or 6 inches wide x 48 inches long for Plank.

E. Colors and Patterns: Light Color that complements adjacent remaining flooring. Provide options to COR for selection.

2.2 INSTALLATION MATERIALS

A. Trowelable Leveling and Patching Compounds: Latex-modified, portland-cement-based or blended hydraulic-cement-based formulation provided or approved by floor tile manufacturer for applications indicated.

B. Adhesives: Water-resistant type recommended by floor tile and adhesive manufacturers to suit floor tile and substrate conditions indicated.

PART 3 - EXECUTION

3.1 PREPARATION

A. Prepare substrates according to floor tile manufacturer's written instructions to ensure adhesion of resilient products.

B. Concrete Substrates: Prepare according to ASTM F710.

1. Verify that substrates are dry and free of curing compounds, sealers, and hardeners.

2. Remove substrate coatings and other substances that are incompatible with adhesives and that contain soap, wax, oil, or silicone, using methods recommended by floor tile manufacturer.

3. Alkalinity and Adhesion Testing: Perform tests recommended by floor tile manufacturer. Proceed with installation only after substrate alkalinity falls within range on pH scale recommended by manufacturer in writing.

C. Fill cracks, holes, and depressions in substrates with trowelable leveling and patching compound; remove bumps and ridges to produce a uniform and smooth substrate.

D. Do not install floor tiles until materials are the same temperature as space where they are to be installed.

1. At least 48 hours in advance of installation, move resilient floor tile and installation materials into spaces where they will be installed.

E. Immediately before installation, sweep and vacuum clean substrates to be covered by resilient floor tile.

3.2 FLOOR TILE INSTALLATION

A. Comply with manufacturer's written instructions for installing floor tile.

B. Lay out floor tiles from center marks established with principal walls, discounting minor offsets, so tiles at opposite edges of room are of equal width. Adjust as necessary to avoid using cut widths that equal less than one-half tile at perimeter.

C. Match floor tiles for color and pattern by selecting tiles from cartons in the same sequence as manufactured and packaged, if so numbered. Discard broken, cracked, chipped, or deformed tiles.

D. If built-in items are required to be set on top of floor tile, indicate on Drawings and revise first paragraph below.

E. Scribe, cut, and fit floor tiles to butt neatly and tightly to vertical surfaces and permanent fixtures including built-in furniture, cabinets, pipes, outlets, and door frames.

F. Extend floor tiles into toe spaces, door reveals, closets, and similar openings. Extend floor tiles to center of door openings.

G. Maintain reference markers, holes, and openings that are in place or marked for future cutting by repeating on floor tiles as marked on substrates. Use chalk or other nonpermanent marking device.

H. Adhere floor tiles to substrates using a full spread of adhesive applied to substrate to produce a completed installation without open cracks, voids, raising and puckering at joints, telegraphing of adhesive spreader marks, and other surface imperfections. If required by manufacturer.

I. Clean products according to manufacturer’s maintenance instructions.

END OF SECTION 096519