This document appears to be a pricing attachment for a federal contract opportunity related to barriers maintenance and repair at U.S. Army Garrison (USAG) installations in Italy. The attachment provides pricing templates for three base years and four option years, with labor hours and rates for various work categories such as electrical, mechanical, electronic, and general work, both within and outside of normal duty hours. It also includes estimated material costs and percentage discounts. The overall contract includes multiple Contract Line Item Numbers (CLINs) for repairs at the Vicenza and Livorno locations. The key details, such as estimated labor hours, labor rates, material costs, and discount percentages, are provided for each CLIN and option year. This pricing attachment appears to be part of a larger solicitation for barriers maintenance and repair services at USAG-Italy locations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Riparazione delle barriereD.F. DUE S.r.l.Barriers Repair - MA IMPIANTIBarriers Repair - L'APRIREBarriers Repair - Attachment 4 Pricing
NOTE: OFFERORS SHALL FILL-IN ONLY CELLS HIGHLIGHTED IN YELLOW AND REPORT THE TOTAL AMOUNTS FOR EACH CLIN ON THE SF1449 OF THE SOLICITATION
Anno Base : 30 Dec 2024 - 29 Dec 2025Base Year: 30 Dec 2024 - 29 Dec 2025Base Year: 30 Dec 2024 - 29 Dec 2025Base Year: 30 Jan 2025 - 29 Jan 2026
RIPARAZIONI USAG-Italy (Vicenza and Livorno) CLINs 0003-0006N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)REPAIRS USAG-Italy (Vicenza and Livorno) CLINs 0003-0006Est. # of HoursLabor RateTotal (Hours X Labor Rate)REPAIRS USAG-Italy (Vicenza and Livorno) CLINs 0003-0006Est. # of HoursLabor RateTotal (Hours X Labor Rate)REPAIRS USAG-Italy (Vicenza and Livorno) CLINs 0003-0006Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro114€ 55.00€ 6,270.00Electric work Within Duty Hours114€ 50.00€ 5,700.00Electric work Within Duty Hours114€ 58.00€ 6,612.00Electric work Within Duty Hours114€ - 0
Lavori elettrici oltre l'orario di lavoro40€ 64.00€ 2,560.00Electric Outside Duty Hours40€ 60.00€ 2,400.00Electric Outside Duty Hours40€ 67.00€ 2,680.00Electric Outside Duty Hours40€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro113€ 64.00€ 7,232.00Mechanical Work Within Duty Hours113€ 60.00€ 6,780.00Mechanical Work Within Duty Hours113€ 50.00€ 5,650.00Mechanical Work Within Duty Hours113€ - 0
Lavori meccanici oltre l'orario di lavoro23€ 69.00€ 1,587.00Mechanical Work Outside Duty Hours23€ 65.00€ 1,495.00Mechanical Work Outside Duty Hours23€ 65.00€ 1,495.00Mechanical Work Outside Duty Hours23€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro142€ 73.00€ 10,366.00Electronic Work Within duty hours142€ 70.00€ 9,940.00Electronic Work Within duty hours142€ 72.00€ 10,224.00Electronic Work Within duty hours142€ - 0
Lavori elettronici oltre l'orario di lavoro57€ 78.00€ 4,446.00Electronic Work Outside duty hours57€ 75.00€ 4,275.00Electronic Work Outside duty hours57€ 78.00€ 4,446.00Electronic Work Outside duty hours57€ - 0
Generale nell'ambito dell'orario di lavoro68€ 55.00€ 3,740.00General Within Duty Hours68€ 50.00€ 3,400.00General Within Duty Hours68€ 50.00€ 3,400.00General Within Duty Hours68€ - 0
Generale oltre l'orario di lavoro11€ 55.00€ 605.00General Outside Duty Hours11€ 50.00€ 550.00General Outside Duty Hours11€ 65.00€ 715.00General Outside Duty Hours11€ - 0
TOTALE lavoro568€ 36,806.00TOTAL Labor568€ 34,540.00TOTAL Labor568€ 35,222.00TOTAL Labor568€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
13.50%€ 17,633.56€ 15,253.03Vicenza15.00%€ 17,633.56€ 14,988.53Vicenza10.00%€ 17,633.56€ 15,870.20Vicenza€ 17,633.56€ 17,633.56Vicenza
13.50%€ 13,691.11€ 11,842.81Livorno15.00%€ 13,691.11€ 11,637.44Livorno10.00%€ 13,691.11€ 12,322.00Livorno€ 13,691.11€ 13,691.11Livorno
TOTALCLIN 0003 (Vicenza)€ 41,017.23TOTALCLIN 0003 (Vicenza)€ 39,166.53TOTALCLIN 0003 (Vicenza)€ 40,525.60TOTALCLIN 0003 (Vicenza)€ 17,633.56
TOTAL CLIN 0006 (Livorno)€ 22,884.61TOTAL CLIN 0006 (Livorno)€ 21,999.44TOTAL CLIN 0006 (Livorno)€ 22,888.60TOTAL CLIN 0006 (Livorno)€ 13,691.11
CLIN 0009: Barriere Natsaka USAG - Italy (Vicenza and Livorno)N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)CLIN 0009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 0009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 0009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro48€ 55.00€ 2,640.00Electric work Within Duty Hours48€ 50.00€ 2,400.00Electric work Within Duty Hours48€ 58.00€ 2,784.00Electric work Within Duty Hours48€ - 0
Lavori elettrici oltre l'orario di lavoro12€ 64.00€ 768.00Electric Outside Duty Hours12€ 60.00€ 720.00Electric Outside Duty Hours12€ 67.00€ 804.00Electric Outside Duty Hours12€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro64€ 64.00€ 4,096.00Mechanical Work Within Duty Hours64€ 60.00€ 3,840.00Mechanical Work Within Duty Hours64€ 50.00€ 3,200.00Mechanical Work Within Duty Hours64€ - 0
Lavori meccanici oltre l'orario di lavoro12€ 69.00€ 828.00Mechanical Work Outside Duty Hours12€ 65.00€ 780.00Mechanical Work Outside Duty Hours12€ 65.00€ 780.00Mechanical Work Outside Duty Hours12€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro16€ 73.00€ 1,168.00Electronic Work Within duty hours16€ 70.00€ 1,120.00Electronic Work Within duty hours16€ 72.00€ 1,152.00Electronic Work Within duty hours16€ - 0
Lavori elettronici oltre l'orario di lavoro12€ 78.00€ 936.00Electronic Work Outside duty hours12€ 75.00€ 900.00Electronic Work Outside duty hours12€ 78.00€ 936.00Electronic Work Outside duty hours12€ - 0
Generale nell'ambito dell'orario di lavoro24€ 55.00€ 1,320.00General Within Duty Hours24€ 50.00€ 1,200.00General Within Duty Hours24€ 50.00€ 1,200.00General Within Duty Hours24€ - 0
Generale oltre l'orario di lavoro12€ 55.00€ 660.00General Outside Duty Hours12€ 50.00€ 600.00General Outside Duty Hours12€ 65.00€ 780.00General Outside Duty Hours12€ - 0
TOTALE lavoro200€ 12,416.00TOTAL Labor200€ 11,560.00TOTAL Labor200€ 11,636.00TOTAL Labor200€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
13.50%€ 19,522.71€ 16,887.1415%€ 19,522.71€ 16,594.3010%€ 19,522.71€ 17,570.44€ 19,522.71€ 19,522.71
TOTAL CLIN 0009 (Barriere Natsaka )€ 29,303.14TOTAL CLIN 0009 (Natsaka Barriers)€ 28,154.30TOTAL CLIN 0009 (Natsaka Barriers)€ 29,206.44TOTAL CLIN 0009 (Natsaka Barriers)€ 19,522.71
TOTAL BASE YEAR€ 93,204.98TOTAL BASE YEAR€ 89,320.27TOTAL BASE YEAR€ 92,620.64TOTAL BASE YEAR€ 50,847.38
Primo anno di opzione: 30 Dec 2025 - 29 Dec 2026First Option Year: 30 Dec 2025 - 29 Dec 2026First Option Year: 30 Dec 2025 - 29 Dec 2026First Option Year: 30 Jan 2026 - 29 Jan 2027
CLIN 1003 and 1006: USAG-Italy (Vicenza and Livorno)N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)CLIN 1003 and 1006: USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 1003 and 1006: USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 1003 and 1006: USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro114€ 55.00€ 6,270.00Electric work Within Duty Hours114€ 50.00€ 5,700.00Electric work Within Duty Hours114€ 58.00€ 6,612.00Electric work Within Duty Hours114€ - 0
Lavori elettrici oltre l'orario di lavoro40€ 64.00€ 2,560.00Electric Outside Duty Hours40€ 60.00€ 2,400.00Electric Outside Duty Hours40€ 67.00€ 2,680.00Electric Outside Duty Hours40€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro113€ 64.00€ 7,232.00Mechanical Work Within Duty Hours113€ 60.00€ 6,780.00Mechanical Work Within Duty Hours113€ 50.00€ 5,650.00Mechanical Work Within Duty Hours113€ - 0
Lavori meccanici oltre l'orario di lavoro23€ 69.00€ 1,587.00Mechanical Work Outside Duty Hours23€ 65.00€ 1,495.00Mechanical Work Outside Duty Hours23€ 65.00€ 1,495.00Mechanical Work Outside Duty Hours23€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro142€ 73.00€ 10,366.00Electronic Work Within duty hours142€ 70.00€ 9,940.00Electronic Work Within duty hours142€ 72.00€ 10,224.00Electronic Work Within duty hours142€ - 0
Lavori elettronici oltre l'orario di lavoro57€ 78.00€ 4,446.00Electronic Work Outside duty hours57€ 75.00€ 4,275.00Electronic Work Outside duty hours57€ 78.00€ 4,446.00Electronic Work Outside duty hours57€ - 0
Generale nell'ambito dell'orario di lavoro68€ 55.00€ 3,740.00General Within Duty Hours68€ 50.00€ 3,400.00General Within Duty Hours68€ 50.00€ 3,400.00General Within Duty Hours68€ - 0
Generale oltre l'orario di lavoro11€ 55.00€ 605.00General Outside Duty Hours11€ 50.00€ 550.00General Outside Duty Hours11€ 65.00€ 715.00General Outside Duty Hours11€ - 0
TOTALE lavoro568€ 36,806.00TOTAL Labor568€ 34,540.00TOTAL Labor568€ 35,222.00TOTAL Labor568€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
13.50%€ 19,629.62€ 16,979.62Vicenza15.00%€ 19,629.62€ 16,685.18Vicenza10.00%€ 19,629.62€ 17,666.66Vicenza€ 19,629.62€ 19,629.62Vicenza
13.50%€ 14,019.70€ 12,127.04Livorno15.00%€ 14,019.70€ 11,916.75Livorno10.00%€ 14,019.70€ 12,617.73Livorno€ 14,019.70€ 14,019.70Livorno
TOTAL CLIN 1003 (Vicenza)€ 42,743.82TOTAL CLIN 1003 (Vicenza)€ 40,863.18TOTAL CLIN 1003 (Vicenza)€ 42,322.06TOTAL CLIN 1003 (Vicenza)€ 19,629.62
TOTAL CLIN 1006 (Livorno)€ 23,168.84TOTAL CLIN 1006 (Livorno)€ 22,278.75TOTAL CLIN 1006 (Livorno)€ 23,184.33TOTAL CLIN 1006 (Livorno)€ 14,019.70
CLIN 1009: Barriere Natsaka USAG - Italy (Vicenza and Livorno)N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)CLIN 1009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 1009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 1009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro48€ 55.00€ 2,640.00Electric work Within Duty Hours48€ 50.00€ 2,400.00Electric work Within Duty Hours48€ 58.00€ 2,784.00Electric work Within Duty Hours48€ - 0
Lavori elettrici oltre l'orario di lavoro12€ 64.00€ 768.00Electric Outside Duty Hours12€ 60.00€ 720.00Electric Outside Duty Hours12€ 67.00€ 804.00Electric Outside Duty Hours12€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro64€ 64.00€ 4,096.00Mechanical Work Within Duty Hours64€ 60.00€ 3,840.00Mechanical Work Within Duty Hours64€ 50.00€ 3,200.00Mechanical Work Within Duty Hours64€ - 0
Lavori meccanici oltre l'orario di lavoro12€ 69.00€ 828.00Mechanical Work Outside Duty Hours12€ 65.00€ 780.00Mechanical Work Outside Duty Hours12€ 65.00€ 780.00Mechanical Work Outside Duty Hours12€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro16€ 73.00€ 1,168.00Electronic Work Within duty hours16€ 70.00€ 1,120.00Electronic Work Within duty hours16€ 72.00€ 1,152.00Electronic Work Within duty hours16€ - 0
Lavori elettronici oltre l'orario di lavoro12€ 78.00€ 936.00Electronic Work Outside duty hours12€ 75.00€ 900.00Electronic Work Outside duty hours12€ 78.00€ 936.00Electronic Work Outside duty hours12€ - 0
Generale nell'ambito dell'orario di lavoro24€ 55.00€ 1,320.00General Within Duty Hours24€ 50.00€ 1,200.00General Within Duty Hours24€ 50.00€ 1,200.00General Within Duty Hours24€ - 0
Generale oltre l'orario di lavoro12€ 55.00€ 660.00General Outside Duty Hours12€ 50.00€ 600.00General Outside Duty Hours12€ 65.00€ 780.00General Outside Duty Hours12€ - 0
TOTALE lavoro200€ 12,416.00Total Labor200€ 11,560.00Total Labor200€ 11,636.00Total Labor200€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
12%€ 19,991.26€ 17,592.3115%€ 19,991.26€ 16,992.5710%€ 19,991.26€ 17,992.13€ 19,991.26€ 19,991.26
TOTAL CLIN 1009 (Barriere Natsaka )€ 30,008.31TOTAL CLIN 1009 (Natsaka Barriers)€ 28,552.57TOTAL CLIN 1009 (Natsaka Barriers)€ 29,628.13TOTAL CLIN 1009 (Natsaka Barriers)€ 19,991.26
TOTAL FIRST YEAR€ 95,920.97TOTAL FIRST YEAR€ 91,694.49TOTAL FIRST YEAR€ 95,134.52TOTAL FIRST YEAR€ 53,640.58
Secondo anno di opzione: 30 Dec 2026 - 29 Dec 2027Second Option Year: 30 Dec 2026 - 29 Dec 2027Second Option Year: 30 Dec 2026 - 29 Dec 2027Second Option Year: 30 Jan 2027 - 29 Jan 2028
CLIN 2003 and 2006 : USAG-Italy (Vicenza and Livorno)N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)CLIN 2003 and 2006 : USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 2003 and 2006 : USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 2003 and 2006 : USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro114€ 55.55€ 6,332.70Electric work Within Duty Hours114€ 50.00€ 5,700.00Electric work Within Duty Hours114€ 60.00€ 6,840.00Electric work Within Duty Hours114€ - 0
Lavori elettrici oltre l'orario di lavoro40€ 64.64€ 2,585.60Electric Outside Duty Hours40€ 60.00€ 2,400.00Electric Outside Duty Hours40€ 70.00€ 2,800.00Electric Outside Duty Hours40€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro113€ 64.64€ 7,304.32Mechanical Work Within Duty Hours113€ 60.00€ 6,780.00Mechanical Work Within Duty Hours113€ 52.00€ 5,876.00Mechanical Work Within Duty Hours113€ - 0
Lavori meccanici oltre l'orario di lavoro23€ 69.69€ 1,602.87Mechanical Work Outside Duty Hours23€ 65.00€ 1,495.00Mechanical Work Outside Duty Hours23€ 65.00€ 1,495.00Mechanical Work Outside Duty Hours23€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro142€ 73.73€ 10,469.66Electronic Work Within duty hours142€ 70.00€ 9,940.00Electronic Work Within duty hours142€ 72.00€ 10,224.00Electronic Work Within duty hours142€ - 0
Lavori elettronici oltre l'orario di lavoro57€ 78.78€ 4,490.46Electronic Work Outside duty hours57€ 75.00€ 4,275.00Electronic Work Outside duty hours57€ 80.00€ 4,560.00Electronic Work Outside duty hours57€ - 0
Generale nell'ambito dell'orario di lavoro68€ 55.55€ 3,777.40General Within Duty Hours68€ 50.00€ 3,400.00General Within Duty Hours68€ 52.00€ 3,536.00General Within Duty Hours68€ - 0
Generale oltre l'orario di lavoro11€ 55.55€ 611.05General Outside Duty Hours11€ 50.00€ 550.00General Outside Duty Hours11€ 65.00€ 715.00General Outside Duty Hours11€ - 0
TOTALE lavoro568€ 37,174.06TOTAL Labor568€ 34,540.00TOTAL Labor568€ 36,046.00TOTAL Labor568€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
11.50%€ 20,100.73€ 17,789.15Vicenza13.00%€ 20,100.73€ 17,487.64Vicenza8.00%€ 20,100.73€ 18,492.67Vicenza€ 20,100.73€ 20,100.73Vicenza
11.50%€ 14,356.17€ 12,705.21Livorno13.00%€ 14,356.17€ 12,489.87Livorno8.00%€ 14,356.17€ 13,207.68Livorno€ 14,356.17€ 14,356.17Livorno
TOTAL CLIN 2003 (Vicenza)€ 43,810.99TOTAL CLIN 2003 (Vicenza)€ 41,665.64TOTAL CLIN 2003 (Vicenza)€ 43,724.87TOTAL CLIN 2003 (Vicenza)€ 20,100.73
TOTAL CLIN 2006 (Livorno)€ 23,857.43TOTAL CLIN 2006 (Livorno)€ 22,851.87TOTAL CLIN 2006 (Livorno)€ 24,021.48TOTAL CLIN 2006 (Livorno)€ 14,356.17
CLIN 2009: Barriere Natsaka USAG - Italy (Vicenza and Livorno)N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)CLIN 2009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 2009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 2009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro48€ 55.55€ 2,666.40Electric work Within Duty Hours48€ 50.00€ 2,400.00Electric work Within Duty Hours48€ 60.00€ 2,880.00Electric work Within Duty Hours48€ - 0
Lavori elettrici oltre l'orario di lavoro12€ 64.64€ 775.68Electric Outside Duty Hours12€ 60.00€ 720.00Electric Outside Duty Hours12€ 70.00€ 840.00Electric Outside Duty Hours12€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro64€ 64.64€ 4,136.96Mechanical Work Within Duty Hours64€ 60.00€ 3,840.00Mechanical Work Within Duty Hours64€ 52.00€ 3,328.00Mechanical Work Within Duty Hours64€ - 0
Lavori meccanici oltre l'orario di lavoro12€ 69.69€ 836.28Mechanical Work Outside Duty Hours12€ 65.00€ 780.00Mechanical Work Outside Duty Hours12€ 65.00€ 780.00Mechanical Work Outside Duty Hours12€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro16€ 73.73€ 1,179.68Electronic Work Within duty hours16€ 70.00€ 1,120.00Electronic Work Within duty hours16€ 72.00€ 1,152.00Electronic Work Within duty hours16€ - 0
Lavori elettronici oltre l'orario di lavoro12€ 78.78€ 945.36Electronic Work Outside duty hours12€ 75.00€ 900.00Electronic Work Outside duty hours12€ 80.00€ 960.00Electronic Work Outside duty hours12€ - 0
Generale nell'ambito dell'orario di lavoro24€ 55.55€ 1,333.20General Within Duty Hours24€ 50.00€ 1,200.00General Within Duty Hours24€ 52.00€ 1,248.00General Within Duty Hours24€ - 0
Generale oltre l'orario di lavoro12€ 55.55€ 666.60General Outside Duty Hours12€ 50.00€ 600.00General Outside Duty Hours12€ 65.00€ 780.00General Outside Duty Hours12€ - 0
TOTALE lavoro200€ 12,540.16Total Labor200€ 11,560.00Total Labor200€ 11,968.00Total Labor200€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
11.5%€ 20,471.05€ 18,116.8813%€ 20,471.05€ 17,809.818%€ 20,471.05€ 18,833.37€ 20,471.05€ 20,471.05
TOTAL CLIN 2009 (Barriere Natsaka )€ 30,657.04TOTAL CLIN 2009 (Natsaka Barriers)€ 29,369.81TOTAL CLIN 2009 (Natsaka Barriers)€ 30,801.37TOTAL CLIN 2009 (Natsaka Barriers)€ 20,471.05
TOTAL SECOND YEAR€ 98,325.46TOTAL SECOND YEAR€ 93,887.32TOTAL SECOND YEAR€ 98,547.71TOTAL SECOND YEAR€ 54,927.95
Terzo anno di opzione: 30 Dec 2027- 29 Dec 2028Third Option Year: 30 Dec 2027- 29 Dec 2028Third Option Year: 30 Dec 2027- 29 Dec 2028Third Option Year: 30 Jan 2028 - 29 Jan 2029
CLIN 3003 and 3006 : USAG-Italy (Vicenza and Livorno)N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)CLIN 3003 and 3006 : USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 3003 and 3006 : USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 3003 and 3006 : USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro114€ 56.10€ 6,395.40Electric work Within Duty Hours114€ 50.00€ 5,700.00Electric work Within Duty Hours114€ 60.00€ 6,840.00Electric work Within Duty Hours114€ - 0
Lavori elettrici oltre l'orario di lavoro40€ 65.28€ 2,611.20Electric Outside Duty Hours40€ 60.00€ 2,400.00Electric Outside Duty Hours40€ 70.00€ 2,800.00Electric Outside Duty Hours40€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro113€ 65.28€ 7,376.64Mechanical Work Within Duty Hours113€ 60.00€ 6,780.00Mechanical Work Within Duty Hours113€ 52.00€ 5,876.00Mechanical Work Within Duty Hours113€ - 0
Lavori meccanici oltre l'orario di lavoro23€ 70.38€ 1,618.74Mechanical Work Outside Duty Hours23€ 65.00€ 1,495.00Mechanical Work Outside Duty Hours23€ 65.00€ 1,495.00Mechanical Work Outside Duty Hours23€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro142€ 74.46€ 10,573.32Electronic Work Within duty hours142€ 70.00€ 9,940.00Electronic Work Within duty hours142€ 72.00€ 10,224.00Electronic Work Within duty hours142€ - 0
Lavori elettronici oltre l'orario di lavoro57€ 79.56€ 4,534.92Electronic Work Outside duty hours57€ 75.00€ 4,275.00Electronic Work Outside duty hours57€ 80.00€ 4,560.00Electronic Work Outside duty hours57€ - 0
Generale nell'ambito dell'orario di lavoro68€ 56.10€ 3,814.80General Within Duty Hours68€ 50.00€ 3,400.00General Within Duty Hours68€ 52.00€ 3,536.00General Within Duty Hours68€ - 0
Generale oltre l'orario di lavoro11€ 56.10€ 617.10General Outside Duty Hours11€ 50.00€ 550.00General Outside Duty Hours11€ 65.00€ 715.00General Outside Duty Hours11€ - 0
TOTALE lavoro568€ 37,542.12TOTAL Labor568€ 34,540.00TOTAL Labor568€ 36,046.00TOTAL Labor568€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
11.00%€ 20,100.73€ 17,889.65Vicenza12.00%€ 20,100.73€ 17,688.64Vicenza8.00%€ 20,100.73€ 18,492.67Vicenza€ 20,100.73€ 20,100.73Vicenza
11.00%€ 14,356.17€ 12,776.99Livorno12.00%€ 14,356.17€ 12,633.43Livorno8.00%€ 14,356.17€ 13,207.68Livorno€ 14,356.17€ 14,356.17Livorno
TOTAL CLIN 3003 (Vicenza)€ 44,169.13TOTAL CLIN 3003 (Vicenza)€ 41,866.64TOTAL CLIN 3003 (Vicenza)€ 43,724.87TOTAL CLIN 3003 (Vicenza)€ 20,100.73
TOTAL CLIN 3006 (Livorno)€ 24,039.63TOTAL CLIN 3006 (Livorno)€ 22,995.43TOTAL CLIN 3006 (Livorno)€ 24,021.48TOTAL CLIN 3006 (Livorno)€ 14,356.17
CLIN 3009: Barriere Natsaka USAG - Italy (Vicenza and Livorno)N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)CLIN 3009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 3009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 3009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro48€ 56.10€ 2,692.80Electric work Within Duty Hours48€ 50.00€ 2,400.00Electric work Within Duty Hours48€ 60.00€ 2,880.00Electric work Within Duty Hours48€ - 0
Lavori elettrici oltre l'orario di lavoro12€ 65.28€ 783.36Electric Outside Duty Hours12€ 55.00€ 660.00Electric Outside Duty Hours12€ 70.00€ 840.00Electric Outside Duty Hours12€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro64€ 65.28€ 4,177.92Mechanical Work Within Duty Hours64€ 60.00€ 3,840.00Mechanical Work Within Duty Hours64€ 52.00€ 3,328.00Mechanical Work Within Duty Hours64€ - 0
Lavori meccanici oltre l'orario di lavoro12€ 70.38€ 844.56Mechanical Work Outside Duty Hours12€ 65.00€ 780.00Mechanical Work Outside Duty Hours12€ 65.00€ 780.00Mechanical Work Outside Duty Hours12€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro16€ 74.46€ 1,191.36Electronic Work Within duty hours16€ 60.00€ 960.00Electronic Work Within duty hours16€ 72.00€ 1,152.00Electronic Work Within duty hours16€ - 0
Lavori elettronici oltre l'orario di lavoro12€ 79.56€ 954.72Electronic Work Outside duty hours12€ 65.00€ 780.00Electronic Work Outside duty hours12€ 80.00€ 960.00Electronic Work Outside duty hours12€ - 0
Generale nell'ambito dell'orario di lavoro24€ 56.10€ 1,346.40General Within Duty Hours24€ 50.00€ 1,200.00General Within Duty Hours24€ 52.00€ 1,248.00General Within Duty Hours24€ - 0
Generale oltre l'orario di lavoro12€ 56.10€ 673.20General Outside Duty Hours12€ 50.00€ 600.00General Outside Duty Hours12€ 65.00€ 780.00General Outside Duty Hours12€ - 0
TOTALE lavoro200€ 12,664.32Total Labor200€ 11,220.00Total Labor200€ 11,968.00Total Labor200€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
11%€ 20,471.05€ 18,219.2312%€ 20,471.05€ 18,014.528%€ 20,471.05€ 18,833.37€ 20,471.05€ 20,471.05
TOTAL CLIN 3009 (Barriere Natsaka)€ 30,883.55TOTAL CLIN 3009 (Natsaka Barriers)€ 29,234.52TOTAL CLIN 3009 (Natsaka Barriers)€ 30,801.37TOTAL CLIN 3009 (Natsaka Barriers)€ 20,471.05
TOTAL THIRD YEAR€ 99,092.32TOTAL THIRD YEAR€ 94,096.60TOTAL THIRD YEAR€ 98,547.71TOTAL THIRD YEAR€ 54,927.95
Quarto anno di opzione: 30 Dec 2028- 29 Dec 2029Fourth Option Year: 30 Dec 2028- 29 Dec 2029Fourth Option Year: 30 Dec 2028- 29 Dec 2029Fourth Option Year: 30 Jan 2029 - 29 Jan 2030
CLIN 4003 and 4006 : USAG-Italy (Vicenza and Livorno)N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)CLIN 4003 and 4006 : USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 4003 and 4006 : USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 4003 and 4006 : USAG-Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro114€ 56.65€ 6,458.10Electric work Within Duty Hours114€ 50.00€ 5,700.00Electric work Within Duty Hours114€ 62.00€ 7,068.00Electric work Within Duty Hours114€ - 0
Lavori elettrici oltre l'orario di lavoro40€ 65.92€ 2,636.80Electric Outside Duty Hours40€ 60.00€ 2,400.00Electric Outside Duty Hours40€ 73.00€ 2,920.00Electric Outside Duty Hours40€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro113€ 65.92€ 7,448.96Mechanical Work Within Duty Hours113€ 60.00€ 6,780.00Mechanical Work Within Duty Hours113€ 55.00€ 6,215.00Mechanical Work Within Duty Hours113€ - 0
Lavori meccanici oltre l'orario di lavoro23€ 71.07€ 1,634.61Mechanical Work Outside Duty Hours23€ 65.00€ 1,495.00Mechanical Work Outside Duty Hours23€ 68.00€ 1,564.00Mechanical Work Outside Duty Hours23€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro142€ 75.19€ 10,676.98Electronic Work Within duty hours142€ 70.00€ 9,940.00Electronic Work Within duty hours142€ 75.00€ 10,650.00Electronic Work Within duty hours142€ - 0
Lavori elettronici oltre l'orario di lavoro57€ 80.34€ 4,579.38Electronic Work Outside duty hours57€ 75.00€ 4,275.00Electronic Work Outside duty hours57€ 83.00€ 4,731.00Electronic Work Outside duty hours57€ - 0
Generale nell'ambito dell'orario di lavoro68€ 56.65€ 3,852.20General Within Duty Hours68€ 50.00€ 3,400.00General Within Duty Hours68€ 55.00€ 3,740.00General Within Duty Hours68€ - 0
Generale oltre l'orario di lavoro11€ 56.65€ 623.15General Outside Duty Hours11€ 50.00€ 550.00General Outside Duty Hours11€ 68.00€ 748.00General Outside Duty Hours11€ - 0
TOTALE lavoro568€ 37,910.18TOTAL Labor568€ 34,540.00TOTAL Labor568€ 37,636.00TOTAL Labor568€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
9.00%€ 20,100.73€ 18,291.66Vicenza10.00%€ 20,100.73€ 18,090.66Vicenza7.00%€ 20,100.73€ 18,693.68Vicenza€ 20,100.73€ 20,100.73Vicenza
9.00%€ 14,356.17€ 13,064.11Livorno10.00%€ 14,356.17€ 12,920.55Livorno7.00%€ 14,356.17€ 13,351.24Livorno€ 14,356.17€ 14,356.17Livorno
TOTAL CLIN 4003 (Vicenza)€ 44,828.79TOTAL CLIN 4003 (Vicenza)€ 42,268.66TOTAL CLIN 4003 (Vicenza)€ 45,038.88TOTAL CLIN 4003 (Vicenza)€ 20,100.73
TOTAL CLIN 4006 (Livorno)€ 24,437.17TOTAL CLIN 4006 (Livorno)€ 23,282.55TOTAL CLIN 4006 (Livorno)€ 24,642.04TOTAL CLIN 4006 (Livorno)€ 14,356.17
CLIN 4009: Barriere Natsaka USAG - Italy (Vicenza and Livorno)N. stimato di oreTariffa di lavoro orariaTotale (ore X tariffa di lavoro oraria)CLIN 4009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 4009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)CLIN 4009: Natsaka Barriers USAG - Italy (Vicenza and Livorno)Est. # of HoursLabor RateTotal (Hours X Labor Rate)
Lavori elettrici nell'ambito dell'orario di lavoro48€ 56.65€ 2,719.20Electric work Within Duty Hours48€ 50.00€ 2,400.00Electric work Within Duty Hours48€ 62.00€ 2,976.00Electric work Within Duty Hours48€ - 0
Lavori elettrici oltre l'orario di lavoro12€ 65.92€ 791.04Electric Outside Duty Hours12€ 55.00€ 660.00Electric Outside Duty Hours12€ 73.00€ 876.00Electric Outside Duty Hours12€ - 0
Lavori meccanici nell'ambito dell'orario di lavoro64€ 65.92€ 4,218.88Mechanical Work Within Duty Hours64€ 60.00€ 3,840.00Mechanical Work Within Duty Hours64€ 55.00€ 3,520.00Mechanical Work Within Duty Hours64€ - 0
Lavori meccanici oltre l'orario di lavoro12€ 71.07€ 852.84Mechanical Work Outside Duty Hours12€ 65.00€ 780.00Mechanical Work Outside Duty Hours12€ 68.00€ 816.00Mechanical Work Outside Duty Hours12€ - 0
Lavori elettronici nell'ambito dell'orario di lavoro16€ 75.19€ 1,203.04Electronic Work Within duty hours16€ 60.00€ 960.00Electronic Work Within duty hours16€ 75.00€ 1,200.00Electronic Work Within duty hours16€ - 0
Lavori elettronici oltre l'orario di lavoro12€ 80.34€ 964.08Electronic Work Outside duty hours12€ 65.00€ 780.00Electronic Work Outside duty hours12€ 83.00€ 996.00Electronic Work Outside duty hours12€ - 0
Generale nell'ambito dell'orario di lavoro24€ 56.65€ 1,359.60General Within Duty Hours24€ 50.00€ 1,200.00General Within Duty Hours24€ 55.00€ 1,320.00General Within Duty Hours24€ - 0
Generale oltre l'orario di lavoro12€ 56.65€ 679.80General Outside Duty Hours12€ 50.00€ 600.00General Outside Duty Hours12€ 68.00€ 816.00General Outside Duty Hours12€ - 0
TOTALE lavoro200€ 12,788.48Total Labor200€ 11,220.00Total Labor200€ 12,520.00Total Labor200€ - 0
Sconto percentuale sui materiali:Importo stimato per i materialiTotale (importo scontato materiali)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)Percentage Discount for Materials:Estimated Amount for MaterialsTotal (Discount X Est. Amt)
9%€ 20,471.05€ 18,628.6610%€ 20,471.05€ 18,423.957%€ 20,471.05€ 19,038.08€ 20,471.05€ 20,471.05
TOTAL CLIN 4009 (Barriere Natsaka)€ 31,417.14TOTAL CLIN 4009 (Natsaka Barriers)€ 29,643.95TOTAL CLIN 4009 (Natsaka Barriers)€ 31,558.08TOTAL CLIN 4009 (Natsaka Barriers)€ 20,471.05
TOTAL FOURTH YEAR€ 100,683.09TOTAL FOURTH YEAR€ 95,195.16TOTAL FOURTH YEAR€ 101,238.99TOTAL FOURTH YEAR€ 54,927.95