Attachment_3C_Amended_Sewer_Specifications.pdf

PDF 1 MB Posted

Attached to
SLOAN CANYON CONTACT STATION CONSTRUCTION & DELEGA
Solicitation number
140L0624R0026
Issued by

About this file

This solicitation is for construction and delegated design services for the Sloan Canyon Contact Station project. Key details include that the Bureau of Land Management is seeking a contractor to construct the contact station and perform associated design work. Construction is to be completed within 365 calendar days of the notice to proceed. The solicitation includes requirements for site work, utilities, buildings, and other incidental construction items. Pricing is to be provided as firm fixed price with payment terms of net 30. The set-aside is for small businesses.

View the file

Other files

File Type Posted
Attachment_2C_Additive_Details_20240422_0003.pdf PDF
Sol_140L0624R0026_Amd_0003.pdf PDF
Attachment_14_Final_EA_July2021_0003.pdf PDF
Attachment_11A_Questions_and_Answers_2_0003.pdf PDF
SF30_Continuation_Pages_Amend_3_0003.pdf PDF
Sol_140L0624R0026_Amd_0002.pdf PDF
Attachment_13_Consulting_Firms_Tortoise_0001.pdf PDF
Attachment_11_Questions_Answers_1_26_20240402_0001.pdf PDF
Attachment_2C_Additives_Details_20240328_0001.pdf PDF
Attachment_1_SOW_Amendment_1_20240328_0001.pdf PDF
Attachment_12_Site_Visit_Sign_In_20240401_0001.pdf PDF
SF1442_Continuation_Pages_Amend_1_0001.pdf PDF
Sol_140L0624R0026_Amd_0001.pdf PDF
Attachment_10_SF1442_Completion_Instructions.pdf PDF
Attachment_6_Price_Breakout.pdf PDF
Attachment_3A_Construction_Specifications_1.pdf PDF
Attachment_2A_Contsruction_Drawings_Compressed.pdf PDF
Attachment_7_Drainage_Report.pdf PDF
Attachment_9_Lim_on_SubK_Breakout.xlsx XLSX spreadsheet
Attachment_8_Fire_supression.pdf PDF
Attachment_3B_Construction_Specifications_2.pdf PDF
Attachment_2B_Amended_Sewer_Drawings.pdf PDF
Attachment_5_Wage_Determination_NV20240038.pdf PDF
Attachment_4_Delegated_Water_Service_Design_Info.pdf PDF
Sol_140L0624R0026.pdf PDF
Attachment_1_SOW_240110.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. BUREAU OF LAND MANAGEMENT

SLOAN CANYON SEWER DESIGN

2998 NAWGHAW POA RD, HENDERSON, NV 89044

CONTRACT NO. 140L0621D0006

TASK ORDER NO. 140L0622F0302

FINAL

SPECIFICATIONS

U.S. DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

Daniel Gaynes Snapshot

Daniel Gaynes Snapshot

PAGE LEFT BLANK ON PURPOSE

TABLE OF CONTENTS

DIVISION SECTION TITLE

DIVISION 02 – EXISTING CONDITIONS

02 41 19 SELECTIVE DEMOLITION

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 31 – EARTHWORK

31 10 00 SITE CLEARING

31 20 00 EARTH MOVING

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 12 16 ASPHALT PAVING

DIVISION 33 – UTILITIES

33 08 00 COMMISSIONING OF SITE UTILITY SYSTEMS

33 30 00 SANITARY SEWER UTILITIES

SLOAN CANYON SEWER DESIGN SELECTIVE DEMOLITION

02 41 19 - 1

SECTION 02 41 19 - SELECTIVE DEMOLITION

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes: Selective demolition as designated or required to provide for new Work.

Refer to Drawings for additional demolition notes. Work includes, but is not necessarily limited to, the following:

1. Selective demolition of designated construction.

2. Removal of designated materials and finishes.

3. Disconnecting and capping identified utilities.

4. Removal of demolished materials from site.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or recycled.

B. Remove and Salvage: Detach items from existing construction and deliver them to Owner.

C. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or recycled.

1.3 REFERENCE STANDARDS

A. American National Standards Institute

1. ANSI A10.6 - American National Standard Safety Requirements for Demolition.

1.4 PERFORMANCE REQUIREMENTS

A. Salvage and recycle demolition waste in accordance with requirements of Section 01 74 19 -

Construction Waste Management and Disposal.

1.5 ADMINISTRATIVE REQUIREMENTS

A. Coordination:

1. Coordinate utility and building services interruptions with Owner.

2. Coordinate Work to ensure fire sprinklers, fire alarms, smoke detectors, emergency lighting, exit signs and other life safety systems remain in full operation in occupied areas.

B. Pre-Demolition Meeting: Conduct pre-demolition meeting. Convene pre-demolition meeting one week prior to commencing work of this Section

C. Sequencing:

1. Sequence operations to maintain safe working conditions and preserve existing work that is to remain.

2. Sequence demolition so as not to undermine or compromise vertical and lateral load carrying capacity of structures that are to remain.

D. Scheduling:

1. Schedule work at Owner’s convenience to cause minimal interference with Owner’s normal operations.

2. Schedule utility and building services interruptions with Owner.

02 41 19 - 2

a. Do not disable or disrupt building fire or life safety systems without 7 days prior written notice to Owner.

b. Schedule tie-ins to existing systems to minimize disruption.

3. Cooperate with Owner in scheduling noisy, dirty, or wet work.

4. Cooperate with Owner in scheduling waste removal that may impact Owner’s operations.

5. Obtain Owner’s approval of times scheduled for jack hammering.

1.6 SUBMITTALS

A. Program of methods and time schedule for accomplishing this Work.

B. Existing Building Documentation: Submit the following for existing buildings indicated to remain.

1. Report of inspections conducted with Owner both before and after performing work.

2. Survey indicating position and elevation of exterior building features.

3. Photographic survey indicating conditions before, during, and after demolition work.

1.7 QUALITY ASSURANCE

A. Requirements of Regulatory Agencies:

1. Perform Work in accordance with rules and regulations of state and local agencies having jurisdiction for demolition of structures, safety of adjacent structures, dust control, runoff control, and disposal of debris.

2. Conform to rules and regulations of state and local agencies having jurisdiction when hazardous or contaminated materials are discovered.

1.8 SITE CONDITIONS

A. Conduct demolition to minimize interference with adjacent [and occupied] building areas.

B. Owner assumes responsibility for actual condition of building to be partially demolished.

C. Conduct demolition and debris removal operations to minimize interference with adjacent roads, streets, walks, and other adjacent occupied and used facilities.

D. Conduct demolition and debris removal operations with minimum interference to public or private access. Maintain protected egress and access from adjacent structures at all times.

E. Cease demolition immediately if structures appear to be in danger. Notify Owner’s Representative. Do not resume operations until directed.

F. Where existing conditions conflict with representations of the Contract Documents, notify Owner’s Representative and obtain clarification. See also inspection requirements under Existing Building Documentation Article. Do not perform work affecting the conflicting conditions until clarification of the conflict is received.

G. Hazardous Materials:

1. It is not expected that hazardous materials will be encountered in the Work.

2. Hazardous materials are excluded from work of this Section. Immediately inform Owner’s

Representative if hazardous materials are encountered or suspected and stop work in suspect area. Do not proceed with work in suspected area until approved by Owner’s Representative.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

02 41 19 - 3

3.1 EXISTING BUILDING DOCUMENTATION

A. Before performance of work, make inspection and report defects and structural weaknesses of structures to be partially demolished, cut, or removed, of adjacent structures, and of improvements remaining.

B. After performance of work, make inspection and document conditions including defects and structural weaknesses of:

1. Adjacent structures indicated to remain.

2. Structures partially demolished, cut, or removed.

3. Improvements indicated to remain.

C. Owner will accompany Contractor before and after performance of Work to confirm physical condition of existing structures or improvements indicated to remain.

3.2 EXAMINATION

A. Review Project Record Documents of existing construction provided by Owner’s Representative does not guarantee that existing conditions are same as those indicated in Project Record Documents.

B. Determine where removals may result in structural deficiency or unplanned building collapse during demolition. Coordinate demolition sequence and procedures to prevent structures from becoming unstable.

C. Determine where demolition may affect structural integrity or weather resistance of adjacent buildings indicated to remain.

1. Identify measures required to protect buildings from damage.

2. Identify remedial work including patching, repairing, bracing, and other work required to leave buildings indicated to remain in structurally sound and weathertight and watertight condition.

D. Verify hazardous material abatement is complete before beginning demolition.

E. Examine areas affected by work of this Section and verify following:

1. Disconnection of utilities as required.

2. Those utilities serving occupied portions of buildings will be disturbed – needs to be coordinated.

3. Removal by Owner of Owner’s personal property, movable furniture, and equipment items not designated for relocation.

F. Inventory and record the condition of items to be removed and salvaged.

G. When unanticipated mechanical, electrical, or structural elements are encountered, investigate and measure the nature and extent of the element. Promptly submit a written report to Owner.

3.3 PREPARATION

A. Consult with Owner prior to commencing demolition work and determine which existing items are to be salvaged and retained or can be reused in the work. These items shall be carefully removed to avoid damage and shall be delivered to Owner or stored as directed.

B. Lay out work to be demolished at job site and coordinate with related work for which cutting is required.

02 41 19 - 4

C. Review proposed layout with Owner’s Representative prior to performing demolition.

D. Erect and maintain weatherproof closures for exterior openings.

E. Erect and maintain temporary partitions to prevent spread of dust, odors, and noise to permit continued Owner occupancy.

F. Erect and maintain temporary enclosures at locations indicated, including, and security devices lighting, warning signs, and guards necessary to protect public and Owner’s employees, finishes, and existing improvements to remain and adjoining property from damage, all in accordance with applicable regulations.

G. Existing Utilities:

1. Notify affected utility companies before starting work and comply with their requirements.

2. Mark location and termination of utilities.

3. Refer to Divisions 21, 22, 23, 25, 26, 27, and 28 Sections for shutting off, disconnecting, removing, and sealing or capping mechanical or electrical utilities.

4. Do not start demolition work until utility disconnection and sealing have been completed and verified in writing.

5. Take care to ensure that utilities to remain and portions thereof which are not required to be demolished or removed.

6. Locate, identify, disconnect, and seal or cap off indicated utilities serving areas to be demolished.

7. Locate, identify, and protect known utilities indicated to remain from damage. Should damage occur, notify Owner’s Representative and repair at no additional cost to the Contract.

8. Verify that those utilities serving occupied portions of buildings will not be disturbed-unless coordinated with the Owner.

H. Prevent movement or settlement of adjacent structures. Provide bracing and shoring.

I. Protect existing improvements indicated to remain from damage during demolition.

J. Locate, identify, and protect known utilities indicated to remain from damage. Should damage occur, notify Owner’s Representative and repair at no additional cost to the Contract.

3.4 SALVAGE REQUIREMENTS

A. Coordinate with Owner to identify building components and equipment required to be removed and delivered to Owner.

B. Tag components and equipment Owner designates for salvage.

C. Protect designated salvage items from demolition operations until items can be removed.

D. Carefully remove building components and equipment indicated to be salvaged or reinstalled.

Remove materials to be reinstalled or retained in a manner to prevent damage.

E. Disassemble as required to permit removal from building.

F. Package small and loose parts to avoid loss.

G. Mark equipment and packaged parts to permit identification and consolidation of components of each salvaged item.

H. Prepare assembly instructions consistent with disassembled parts. Package assembly instructions in protective envelope and securely attach to each disassembled salvaged item.

02 41 19 - 5

I. Deliver salvaged items to Owner. Obtain signed receipt from Owner.

J. Carefully store building components and equipment indicated to be reinstalled.

3.5 DEMOLITION REQUIREMENTS

A. Disposition of Existing Improvements:

1. Materials forming portions of permanent structure designated for demolition shall become Contractor’s property, and Contractor shall be responsible for their removal unless otherwise noted.

2. Personal property and movable furniture remain Owner’s property. Contractor to store items in future storage area and protect from damage. Consider items not claimed by Owner as debris. Owner’s final verification is required before removal.

B. Sprinkle or wet down Work and areas affected by this Work as required to prevent dust and dirt from rising. Provide hoses and water connections required for this purpose.

3.6 DEMOLITION

A. Perform work in accordance with ANSI A10.6 unless otherwise noted.

B. Conduct demolition to minimize interference with adjacent and occupied building areas.

C. Maintain protected egress from and access to adjacent existing buildings at all times.

D. Do not close or obstruct roadways or sidewalks without permits.

E. Cease operations immediately when structure appears to be in danger and notify Owner’s Representative

F. Disconnect, cap, and identify designated utilities within demolition areas.

G. Remove designated interior structures, parts, and finishes at beginning of work to minimize hazardous working conditions and to provide comparatively clean surfaces for installation of new work.

H. Perform demolitions as much as possible with small tools. Demolish in small sections. Remove loading before cutting or removing structural members.

I. Demolish in an orderly and careful manner. Protect existing supporting structural members.

J. Concrete:

1. Demolish by means of saw cutting, drilling, chipping, breaking, or a combination thereof, as indicated or required to satisfactory accomplish the Work without damage to existing improvements not being removed.

2. If jack hammering is permitted do not jack hammer within 2 inches of reinforcing or structural steel; remove final 2 inches of material with chipping gun.

3. Demolish concrete in small sections, less than 3 feet in any direction.

4. Cut concrete at nearest control joint to line shown on the Drawings, so that new concrete can be installed continuing the adjacent existing joint pattern.

K. At concrete and other materials where edges of cuts and holes will remain exposed in the completed work, make cuts using power sawing and coring equipment. Do not over cut at corners of cut openings.

02 41 19 - 6

L. Where existing resilient flooring, carpeting, carpet padding, tile and other similar adhesive or mortar applied finishes are required to be removed to permit application of new finishes, grind, stone, sand or otherwise remove all adhesives, mortar, fasteners, and similar materials to the extent that no ridges, lumps or other protrusions will telegraph through surface of new finish or be apparent when the substrate is left exposed.

M. Lower heavy structural framing members by hoist or crane.

3.7 CUTTING

A. Cutting of concrete and asphalt shall be made clean and neat.

B. At limits of demolition Work shown or specified, provide neat, orderly, and clean joints, lines, and edges of surfaces, whether for junctions with new materials or surfaces or whether to be left as existing. Where demolitions methods or controls may not permit the intended jointure, submit conditions and alternatives to Owner’s Representative, and obtain resolutions prior to commencing.

C. Cutting of concrete and asphalt shall be made clean and neat.

D. Do not cut or alter structural members unless indicated to do so on the Drawings or written approval is received from Owner’s Representative.

E. Take care not to damage reinforcing or structural steel scheduled to remain in place.

3.8 REMOVAL OF DEBRIS

A. Remove debris in accordance with requirements of Section 01 74 19 - Construction Waste Management.

B. Remove demolished materials from site except where specifically noted otherwise.

C. Remove materials as Work progresses. Upon completion of Work, leave areas in clean condition.

D. Remove salvage and debris as they accumulate. Do not permit presence of debris to delay progress of related work.

E. Remove materials in a manner to prevent spillage.

F. Nothing to be removed from site shall be stored, sold, burned, or buried on site.

3.9 REPAIRS

A. Promptly repair damage to adjacent construction caused by demolition operations.

B. Where repairs to existing surfaces are required, patch to restore surface to original or better condition.

C. Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.

3.10 CLEANING

A. Clean adjacent improvements scheduled to remain of dust, dirt, and debris caused by demolition operations. Return adjacent areas to condition existing before building demolition operations began.

3.11 SCHEDULES

02 41 19 - 7

A. Disconnect, carefully remove, and store at Owner-designated locations within the Contract Boundary all equipment items to be reused.

END OF SECTION 02 41 19

SLOAN CANYON SEWER DESIGN CAST-IN-PLACE CONCRETE

03 30 00 - 1

SECTION 03 30 00 - CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUSTAINABILITY REQUIREMENTS

A. Refer to Section 01 81 13.14 for general requirements and procedures for compliance with the LEED Version 4 BD+C: New Construction. The Contractor shall ensure that submittals required by this Section also comply with the requirements of Section 01 81 13.14 and the LEED Reference Guide for Building Design and Construction Version 4.

1.3 SUMMARY

A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes.

1.4 DEFINITIONS

A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash, slag cement, other pozzolans, and silica fume;

materials subject to compliance with requirements.

B. W/C Ratio: The ratio by weight of water to cementitious materials.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Sustainable Design Submittals:

1. Product Data: For recycled content, indicating postconsumer and preconsumer recycled content and cost.

C. Design Mixtures: For each concrete mixture. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.

D. Aggregate: multi-color aggregate (tans and grays), to ensure the colors from the quarry are acceptable to the Architect and Government.

E. Steel Reinforcement Shop Drawings: Placing Drawings that detail fabrication, bending, and placement. Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and supports for concrete reinforcement.

F. Construction Joint Layout: Indicate proposed construction joints required to construct the structure.

1. Location of construction joints is subject to approval of the Architect.

G. Samples: For vapor retarder.

03 30 00 - 2

H. Mockups: Before casting architectural concrete, build mockups to verify selections made under Sample submittals and to demonstrate typical joints, surface finish, texture, tolerances, and standard of workmanship. Build mockups to comply with the following requirements, using materials indicated for the completed Work:

1.6 INFORMATIONAL SUBMITTALS

A. Material Test Reports: For the following, from a qualified testing agency:

1. Aggregates: Include service record data indicating absence of deleterious expansion of concrete due to alkali aggregate reactivity.

B. Formwork Shop Drawings: Prepared by or under the supervision of a qualified professional engineer, detailing fabrication, assembly, and support of formwork.

1. Shoring and Reshoring: Indicate proposed schedule and sequence of stripping formwork, shoring removal, and reshoring installation and removal.

C. Field quality-control reports.

D. Floor surface flatness and levelness measurements indicating compliance with specified tolerances.

1.7 QUALITY ASSURANCE

A. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C94 requirements for production facilities and equipment.

B. Testing Agency Qualifications: An independent agency, qualified according to ASTM C1077 and ASTM E329 for testing indicated

1.8 PRECONSTRUCTION TESTING

A. Preconstruction Testing Service: Engage a qualified testing agency to perform preconstruction testing on concrete mixtures.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage. Avoid damaging coatings on steel reinforcement.

B. Waterstops: Store waterstops under cover to protect from moisture, sunlight, dirt, oil, and other contaminants.

1.10 FIELD CONDITIONS

A. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.

1. When average high and low temperature is expected to fall below 40 deg F for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301.

2. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials.

03 30 00 - 3

3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.

B. Hot-Weather Placement: Comply with ACI 301 and as follows:

1. Maintain concrete temperature below 90 deg F at time of placement. Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option.

2. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete. Keep subgrade uniformly moist without standing water, soft spots, or dry areas.

PART 2 - PRODUCTS

2.1 CONCRETE, GENERAL

A. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:

1. ACI 301.

2. ACI 117.

2.2 FORM-FACING MATERIALS

A. Smooth-Formed Finished Concrete: Form-facing panels that provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints.

1. Plywood, metal, or other approved panel materials.

B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material.

Provide lumber dressed on at least two edges and one side for tight fit.

C. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4-inch, minimum.

D. Rustication Strips: Wood, metal, PVC, or rubber strips, kerfed for ease of form removal.

E. Form-Release Agent: Commercially formulated form-release agent that does not bond with, stain, or adversely affect concrete surfaces and does not impair subsequent treatments of concrete surfaces.

1. Formulate form-release agent with rust inhibitor for steel form-facing materials.

F. Form Ties: Factory-fabricated, removable or snap-off glass-fiber-reinforced plastic or metal form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal.

1. Furnish units that leave no corrodible metal closer than 1 inch to the plane of exposed concrete surface.

2. Furnish ties that, when removed, leave holes no larger than 1 inch in diameter in concrete surface.

3. Furnish ties with integral water-barrier plates to walls indicated to receive dampproofing or waterproofing.

2.3 STEEL REINFORCEMENT

03 30 00 - 4

A. Recycled Content of Steel Products: Postconsumer recycled content plus one-half of preconsumer recycled content not less than 25 percent or higher as required to meet overall LEED goals.

B. Reinforcing Bars: ASTM A615, Grade 60, deformed.

C. Epoxy-Coated Reinforcing Bars: ASTM A615, Grade 60 ASTM A706, deformed bars, ASTM A775 or ASTM A934, epoxy coated, with less than 2 percent damaged coating in each 12-inch bar length.

D. Plain-Steel Welded-Wire Reinforcement: ASTM A1064, plain, fabricated from as-drawn steel wire into flat sheets.

2.4 REINFORCEMENT ACCESSORIES

A. Joint Dowel Bars: ASTM A615, Grade 60, plain-steel bars, cut true to length with ends square and free of burrs.

B. Epoxy-Coated Joint Dowel Bars: ASTM A615, Grade 60, plain-steel bars, ASTM A775 epoxy coated.

C. Epoxy Repair Coating: Liquid, two-part, epoxy repair coating; compatible with epoxy coating on reinforcement and complying with ASTM A775.

D. Zinc Repair Material: ASTM A780.

E. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded-wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows:

1. For concrete surfaces exposed to view, where legs of wire bar support contact forms, use CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports.

2. For epoxy-coated reinforcement, use epoxy-coated or other dielectric-polymer-coated wire bar supports.

3. For zinc-coated reinforcement, use galvanized wire or dielectric-polymer-coated wire bar supports.

2.5 CONCRETE MATERIALS

A. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant, obtain aggregate from single source, and obtain admixtures from single source from single manufacturer.

B. Cementitious Materials:

1. Portland Cement: ASTM C 150, Type V, gray.

2. Fly Ash: ASTM C618, Class F.

3. Slag Cement: ASTM C989, Grade 100 or 120.

4. Silica Fume: ASTM C1240, amorphous silica.

C. Normal-Weight Aggregates: ASTM C 33, Class 5S coarse aggregate or better, graded.

Provide aggregates from a single source.

1. Maximum Coarse-Aggregate Size: 3/4-inch nominal.

2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

http://www.arcomnet.com/sustainable_design.aspx?topic=110

03 30 00 - 5

3. Multi-colored aggregate: tans and grays.

D. Air-Entraining Admixture: ASTM C260.

E. Chemical Admixtures: Certified by manufacturer to be compatible with other admixtures and that do not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.

1. Water-Reducing Admixture: ASTM C494, Type A.

2. Retarding Admixture: ASTM C494, Type B.

3. Water-Reducing and Retarding Admixture: ASTM C494, Type D.

4. High-Range, Water-Reducing Admixture: ASTM C494, Type F.

5. High-Range, Water-Reducing and Retarding Admixture: ASTM C494, Type G.

6. Plasticizing and Retarding Admixture: ASTM C1017, Type II.

F. Water: ASTM C94 and potable.

2.6 REINFORCED-POLYETHYLENE VAPOR RETARDERS

A. Reinforced-Polyethylene Vapor Retarders: Sheet with outer layers of polyethylene film laminated to an inner reinforcing layer consisting of either nylon cord or polyester scrim and weighing not less than 20 lb/1000 sq. ft., with maximum permeance rating of 0.1 perm.

B. Thickness: 15 mil

C. Class A, ASTM E-1745-11 Standard Specification for Water Vapor Retarders Use in Contact with Soil or Granular Fill under Concrete Slabs.

D. Approved Products:

1. Reef Industries, Inc: Griffolyn 65G.

2. ISI Building Products: Viper II.

3. Engineer Approved equal.

2.7 CURING MATERIALS

A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete, manufactured by the following companies, or approved equal:

1. BASF Corporation

2. Euclid Chemical Company

3. Sika Corporation

B. Absorptive Cover: AASHTO M182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. when dry.

C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

D. Water: Potable.

2.8 RELATED MATERIALS

A. Expansion- and Isolation-Joint-Filler Strips: ASTM D1751, asphalt-saturated cellulosic fiber or ASTM D1752, cork or self-expanding cork.

B. Bonding Agent: ASTM C1059, Type II, nonredispersible, acrylic emulsion or styrene butadiene.

03 30 00 - 6

C. Epoxy Bonding Adhesive: ASTM C881, two-component epoxy resin, capable of humid curing and bonding to damp surfaces, of class suitable for application temperature and of grade to suit requirements, and as follows:

1. Types I and II, nonload bearing, or Types IV and V, load bearing, for bonding hardened or freshly mixed concrete to hardened concrete.

2.9 REPAIR MATERIALS

A. Repair Underlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/8 inch and that can be feathered at edges to match adjacent floor elevations.

1. Cement Binder: ASTM C150, portland cement or hydraulic or blended hydraulic cement as defined in ASTM C219.

2. Primer: Product of underlayment manufacturer recommended for substrate, conditions, and application.

3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch or coarse sand as recommended by underlayment manufacturer.

4. Compressive Strength: Not less than 4100 psi at 28 days when tested according to ASTM C109.

B. Repair Overlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/4 inch and that can be filled in over a scarified surface to match adjacent floor elevations.

1. Cement Binder: ASTM C150, portland cement or hydraulic or blended hydraulic cement as defined in ASTM C219.

2. Primer: Product of topping manufacturer recommended for substrate, conditions, and application.

3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch or coarse sand as recommended by topping manufacturer.

4. Compressive Strength: Not less than 5000 psi at 28 days when tested according to ASTM C109.

2.10 CONCRETE MIXTURES, GENERAL

A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301.

1. Use a qualified independent testing agency for preparing and reporting proposed mixture designs based on laboratory trial mixtures.

B. Cementitious Materials: Limit materials to replace portland cement in concrete exposed to deicing chemicals per ACI 301 and ACI 318. For concrete not exposed to deicing chemicals limit percentage, by weight, of cementitious materials other than portland cement in concrete as follows:

1. Fly Ash: 25 percent.

2. Combined Fly Ash and Pozzolan: 25 percent.

3. Slag Cement: 50 percent.

4. Combined Fly Ash or Pozzolan and Slag Cement: 50 percent portland cement minimum, with fly ash or pozzolan not exceeding 25 percent.

03 30 00 - 7

5. Silica Fume: 10 percent.

6. Combined Fly Ash, Pozzolans, and Silica Fume: 35 percent with fly ash or pozzolans not exceeding 25 percent and silica fume not exceeding 10 percent.

7. Combined Fly Ash or Pozzolans, Slag Cement, and Silica Fume: 50 percent with fly ash or pozzolans not exceeding 25 percent and silica fume not exceeding 10 percent.

C. Admixtures: Use approved admixtures according to manufacturer's written instructions.

1. Use water-reducing, high-range water-reducing, or plasticizing admixture in concrete, as required, for placement and workability.

2. Use water-reducing and -retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions.

3. Use water-reducing admixture in pumped concrete, concrete for heavy-use industrial slabs and parking structure slabs, concrete required to be watertight, and concrete with a w/c ratio below 0.50.

4. Use corrosion-inhibiting admixture in concrete mixtures where indicated.

D. Color Pigment: Add color pigment to concrete mixture according to manufacturer's written instructions and to result in hardened concrete color consistent with approved mockup.

2.11 CONCRETE MIXTURES FOR BUILDING ELEMENTS

A. Footings: Normal-weight concrete.

1. Minimum Compressive Strength: 4500 psi at 28 days.

2. Maximum W/C Ratio: 0.40.

3. Slump Limit: 4 inches, plus or minus 1 inch.

4. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery for 3/4-inch nominal maximum aggregate size.

B. Foundation Walls: Normal-weight concrete.

1. Minimum Compressive Strength: 4500 psi at 28 days.

2. Maximum W/C Ratio: 0.40.

3. Slump Limit: 4 inches, plus or minus 1 inch.

4. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery for 3/4-inch nominal maximum aggregate size.

C. Slabs-on-Grade: Normal-weight concrete.

1. Minimum Compressive Strength: 4500 psi at 28 days.

2. Maximum W/C Ratio: 0.40.

3. Minimum Cementitious Materials Content: 540 lb/cu. yd.

4. Slump Limit: 4 inches, plus or minus 1 inch.

D. Concrete Toppings: Normal-weight concrete.

1. Minimum Compressive Strength: 4500 psi at 28 days.

2. Minimum Cementitious Materials Content: 540 lb/cu. yd.

3. Slump Limit: 4 inches, plus or minus 1 inch.

2.12 FABRICATING REINFORCEMENT

A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."

03 30 00 - 8

PART 3 - EXECUTION

3.1 FORMWORK INSTALLATION

A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.

B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117.

C. Limit concrete surface irregularities, designated by ACI 347 as abrupt or gradual, as follows:

1. Class A, 1/8 inch for smooth-formed finished surfaces.

2. Class C, 1/2 inch for rough-formed finished surfaces.

D. Construct forms tight enough to prevent loss of concrete mortar.

E. Construct forms for easy removal without hammering or prying against concrete surfaces.

Provide crush or wrecking plates where stripping may damage cast-concrete surfaces.

Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.

1. Install keyways, reglets, recesses, and the like, for easy removal.

2. Do not use rust-stained steel form-facing material.

F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds.

G. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations.

H. Chamfer exterior corners and edges of permanently exposed concrete.

I. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work. Determine sizes and locations from trades providing such items.

J. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete.

K. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.

L. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.

3.2 EMBEDDED ITEM INSTALLATION

A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

1. Install anchor rods, accurately located, to elevations required and complying with tolerances in Section 7.5 of AISC 303.

03 30 00 - 9

3.3 REMOVING AND REUSING FORMS

A. General: Formwork for sides of beams, walls, columns, and similar parts of the Work that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F for 24 hours after placing concrete. Concrete has to be hard enough to not be damaged by form-removal operations and curing and protection operations need to be maintained.

1. Leave formwork for beam soffits, joists, slabs, and other structural elements that support weight of concrete in place until concrete has achieved at least 70 percent of its 28-day design compressive strength.

2. Remove forms only if shores have been arranged to permit removal of forms without loosening or disturbing shores.

B. Clean and repair surfaces of forms to be reused in the Work. Split, frayed, delaminated, or otherwise damaged form-facing material are not acceptable for exposed surfaces. Apply new form-release agent.

C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints.

Align and secure joints to avoid offsets. Do not use patched forms for exposed concrete surfaces unless approved by Architect.

3.4 VAPOR-RETARDER INSTALLATION

A. Sheet Vapor Retarders: Place, protect, and repair sheet vapor retarder according to ASTM E 1643 and manufacturer's written instructions.

1. Lap joints 6 inches and seal with manufacturer's recommended tape.

B. Bituminous Vapor Retarders: Place, protect, and repair bituminous vapor retarder according to manufacturer's written instructions.

3.5 STEEL REINFORCEMENT INSTALLATION

A. General: Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.

1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.

B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that reduce bond to concrete.

C. Accurately position, support, and secure reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars.

D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.

E. Install welded-wire reinforcement in longest practicable lengths on bar supports spaced to minimize sagging. Lap edges and ends of adjoining sheets at least one mesh spacing. Offset laps of adjoining sheet widths to prevent continuous laps in either direction. Lace overlaps with wire.

F. Epoxy-Coated Reinforcement: Repair cut and damaged epoxy coatings with epoxy repair coating according to ASTM D3963. Use epoxy-coated steel wire ties to fasten epoxy-coated steel reinforcement.

03 30 00 - 10

G. Zinc-Coated Reinforcement: Repair cut and damaged zinc coatings with zinc repair material according to ASTM A780. Use galvanized-steel wire ties to fasten zinc-coated steel reinforcement.

3.6 JOINTS

A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Architect.

1. Place joints perpendicular to main reinforcement. Continue reinforcement across construction joints unless otherwise indicated. Do not continue reinforcement through sides of strip placements of floors and slabs.

2. Locate joints for beams, slabs, joists, and girders in the middle third of spans. Offset joints in girders a minimum distance of twice the beam width from a beam-girder intersection.

3. Locate horizontal joints in walls and columns at underside of floors, slabs, beams, and girders and at the top of footings or floor slabs.

C. Isolation Joints in Slabs-on-Grade: After removing formwork, install joint-filler strips at slab junctions with vertical surfaces, such as column pedestals, foundation walls, grade beams, and other locations, as indicated.

1. Extend joint-filler strips full width and depth of joint, terminating flush with finished concrete surface unless otherwise indicated.

2. Install joint-filler strips in lengths as long as practicable. Where more than one length is required, lace or clip sections together.

D. Doweled Joints: Install dowel bars and support assemblies at joints where indicated. Lubricate or asphalt coat one-half of dowel length to prevent concrete bonding to one side of joint.

3.7 WATERSTOP INSTALLATION

A. Waterstops: Install in construction joints and at other locations indicated, according to manufacturer's written instructions.

3.8 CONCRETE PLACEMENT

A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections are completed.

B. Do not add water to concrete during delivery, at Project site, or during placement unless approved by Architect.

C. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete is placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated.

Deposit concrete to avoid segregation.

1. Deposit concrete in horizontal layers of depth not to exceed formwork design pressures and in a manner to avoid inclined construction joints.

2. Consolidate placed concrete with mechanical vibrating equipment according to ACI 301.

03 30 00 - 11

3. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches into preceding layer. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity. At each insertion, limit duration of vibration to time necessary to consolidate concrete and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate.

D. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete.

1. Consolidate concrete during placement operations, so concrete is thoroughly worked around reinforcement and other embedded items and into corners.

2. Maintain reinforcement in position on chairs during concrete placement.

3. Screed slab surfaces with a straightedge and strike off to correct elevations.

4. Slope surfaces uniformly to drains where required.

5. Begin initial floating using bull floats or darbies to form a uniform and open-textured surface plane, before excess bleedwater appears on the surface. Do not further disturb slab surfaces before starting finishing operations.

3.9 FINISHING FORMED SURFACES

A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie holes and defects repaired and patched. Remove fins and other projections that exceed specified limits on formed- surface irregularities.

1. Apply to concrete surfaces not exposed to public view.

B. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defects. Remove fins and other projections that exceed specified limits on formed-surface irregularities.

1. Apply to concrete surfaces exposed to public view, to receive a rubbed finish.

C. Rubbed Finish: Apply the following to smooth-formed-finished as-cast concrete where indicated:

1. Smooth-Rubbed Finish: Not later than one day after form removal, moisten concrete surfaces and rub with carborundum brick or another abrasive until producing a uniform color and texture. Do not apply cement grout other than that created by the rubbing process.

2. Grout-Cleaned Finish: Wet concrete surfaces and apply grout of a consistency of thick paint to coat surfaces and fill small holes. Mix 1 part portland cement to 1-1/2 parts fine sand with a 1:1 mixture of bonding admixture and water. Add white portland cement in amounts determined by trial patches, so color of dry grout matches adjacent surfaces.

Scrub grout into voids and remove excess grout. When grout whitens, rub surface with clean burlap and keep surface damp by fog spray for at least 36 hours.

3. Cork-Floated Finish: Wet concrete surfaces and apply a stiff grout. Mix 1 part portland cement and 1 part fine sand with a 1:1 mixture of bonding agent and water. Add white portland cement in amounts determined by trial patches, so color of dry grout matches adjacent surfaces. Compress grout into voids by grinding surface. In a swirling motion, finish surface with a cork float.

03 30 00 - 12

D. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed surfaces, strike off smooth and finish with a texture matching adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent unformed surfaces unless otherwise indicated.

3.10 FINISHING FLOORS AND SLABS

A. General: Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

B. Float Finish: Consolidate surface with power-driven floats or by hand floating if area is small or inaccessible to power-driven floats. Restraighten, cut down high spots, and fill low spots.

Repeat float passes and restraightening until surface is left with a uniform, smooth, granular texture.

1. Apply float finish to surfaces to receive trowel finish.

2. Don’t over burn with power trowel, as this will make the concrete hard to grind and polish.

3. Don’t use a screen to push the aggregate down to the bottom of the slab.

C. Trowel Finish: After applying float finish, apply first troweling and consolidate concrete by hand or power- driven trowel. Continue troweling passes and restraighten until surface is free of trowel marks and uniform in texture and appearance. Grind smooth any surface defects that would telegraph through applied coatings or floor coverings.

1. Apply a trowel finish to surfaces to be covered with carpet, ceramic or quarry tile set over a cleavage membrane.

2. Finish and measure surface, so gap at any point between concrete surface and an unleveled, freestanding, 10-ft.- long straightedge resting on two high spots and placed anywhere on the surface does not exceed 1/8 inch.

D. Trowel and Fine-Broom Finish: Apply a first trowel finish to surfaces where ceramic or quarry tile is to be installed by either thickset or thinset method. While concrete is still plastic, slightly scarify surface with a fine broom.

1. Comply with flatness and levelness tolerances for trowel-finished floor surfaces.

E. Broom Finish: Apply a broom finish to exterior concrete platforms, steps, ramps, and elsewhere as indicated.

1. Immediately after float finishing, slightly roughen trafficked surface by brooming with fiber-bristle broom perpendicular to main traffic route. Coordinate required final finish with Architect before application.

3.11 CONCRETE PROTECTING AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-weather protection during curing.

B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

03 30 00 - 13

C. Formed Surfaces: Cure formed concrete surfaces, including underside of beams, supported slabs, and other similar surfaces. If forms remain during curing period, moist cure after loosening forms. If removing forms before end of curing period, continue curing for remainder of curing period.

D. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, including floors and slabs, concrete floor toppings, and other surfaces.

E. Cure concrete according to ACI 308.1, by one or a combination of the following methods:

1. Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials:

a. Water.

b. Continuous water-fog spray.

c. Absorptive cover, water saturated, and kept continuously wet. Cover concrete surfaces and edges with 12-inch lap over adjacent absorptive covers.

2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive. Cure for not less than seven days.

Immediately repair any holes or tears during curing period, using cover material and waterproof tape.

a. Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive floor coverings.

b. Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive penetrating liquid floor treatments.

c. Cure concrete surfaces to receive floor coverings with either a moisture-retaining cover or a curing compound that the manufacturer certifies does not interfere with bonding of floor covering used on Project.

3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period.

F. Protect completed polished concrete floor system from damage until Substantial Completion.

G. Do not allow vehicle and pedestrian traffic on unprotected floor.

H. . Do not allow construction materials, equipment, and tools on unprotected floor.

I. Immediately remove mortar splatter, spilled liquids, oil, grease, paint, coatings, and other surface contaminants, which could adversely affect completed polished concrete floor system.

J. Repair damaged areas of completed polished concrete floor system to satisfaction of Architect.

3.12 CONCRETE SURFACE REPAIRS

A. Defective Concrete: Repair and patch defective areas when approved by Architect. Remove and replace concrete that cannot be repaired and patched to Architect's approval.

B. Patching Mortar: Mix dry-pack patching mortar, consisting of 1 part portland cement to 2-1/2 parts fine aggregate passing a No. 16 sieve, using only enough water for handling and placing.

03 30 00 - 14

C. Repairing Formed Surfaces: Surface defects include color and texture irregularities, cracks, spalls, air bubbles, honeycombs, rock pockets, fins and other projections on the surface, and stains and other discolorations that cannot be removed by cleaning.

1. Immediately after form removal, cut out honeycombs, rock pockets, and voids more than 1/2-inch in any dimension to solid concrete. Limit cut depth to 3/4 inch. Make edges of cuts perpendicular to concrete surface. Clean, dampen with water, and brush-coat holes and voids with bonding agent. Fill and compact with patching mortar before bonding agent has dried.

This is the start of the file's text. The full file is on GovTribe.