Attachment_3_Statement_of_Work.pdf
PDF 417 KB Posted
- Attached to
- Inspect & Clean Water Tanks, Crater Lake N. P.
- Solicitation number
- 140P8426Q0076
About this file
This is a Scope of Work (SOW) for a Request for Quotations (RFQ) numbered 140P8426Q0076 for cleaning and inspecting four water tanks at Crater Lake National Park in Klamath County, Oregon.
The base work requires contractors to inspect and clean tank walls, floors, and remove sediment from four potable water storage tanks: one 150,000-gallon tank at park headquarters (Munson), two 100,000-gallon tanks at Mazama, and one 185,000-gallon tank at Garfield Reservoir. The Munson and Mazama tanks are accessible by service roads, while the Garfield tank is accessible only by hiking trail. All work must comply with American Water Works Association (AWWA) and commercial diving standards, including OSHA regulations for confined spaces and diving operations. Certified divers must perform underwater cleaning and inspection, fully encapsulated in dry suits and helmets, disinfected according to AWWA Standard C652-02. The contractor is responsible for all sediment removal, with costic sediment requiring off-site disposal following federal, state, and local regulations. Optional repair work identified during inspection must be presented as a change order quote using the same pricing structure as the original bid. Written and digital reports documenting sediment removal and inspection findings are required upon completion.
The period of performance is 45 days from award, with work anticipated between September 14 and October 30, 2026, with Garfield tank prioritized due to potential seasonal weather impacts and snowfall shutdowns. Quality control daily reports must be submitted documenting work progress. Water supply to Crater Lake must remain uninterrupted during inspection. Post-cleaning water testing for chlorine residual and turbidity must meet Oregon Department of Environmental Quality drinking water standards, conducted by the contractor in the presence of a licensed NPS water operator. Contractors must provide temporary restroom facilities, comply with park traffic and vehicle regulations, implement resource protection measures for endangered species and archaeological resources, and conduct work Monday through Friday, 7:00 a.m. to 5:00 p.m., excluding government holidays. Pre-work deliverables include designation of a Project Lead/Project Manager and a baseline project schedule.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation (Request for Quotations) no. 140P8426Q0076 – Attachment 1, Scope of Work (8/23/26)
Clean and Inspect Water Tanks, Crater Lake National Park (CRLA)
PART 1 – SUMMARY OF WORK
1.1 DESCRIPTION OF WORK
A. Contractor will clean & inspect four water tanks located within Crater Lake National
Park(CRLA or Park), Klamath County, Oregon. Park water storage tanks need to be cleaned and inspected to document the normal buildup of sediment and identify any equipment deterioration that may require repairs in the future.
Tank Locations and Sizes:
• One each, 150,000 gallon tank at park headquarters (Munson)
• Two each, 100,00 gallon tanks are at Mazama
• One each, 185,00 gallon tank at Garfield Reservoir
• Tanks at headquarters and Mazama are accessible by service roads.
• The tank at Garfield is accessible only by a hiking trail.
• Refer to map as Figure 1 at end of this document.
BASE WORK. Inspect and clean tank walls, floors, and remove sediment from the four tanks identified/listed above.
B. OPTIONAL REPAIR WORK. The Government anticipates that the contractor team may find repair work needed. Contractor shall submit a request for change order of the repair work that the Contracting Officer may consider. The Contracting Officer may proceed with incorporating the additional repair work as a contract modification by agreement of the parties. The request for change order pricing shall be based on the same rates/pricing structure as used in Contractor’s original quote for the award of the purchase order.
Contracting Officer may require contractor to submit a price breakdown for the change order request for a modification that supports the lump sum price requested, at a minimum, to view labor categories with job titles indicating hourly rates and number of hours for each.
C. WRITTEN DIGITAL REPORTS. The contractor will provide written and digital reports to the park once work has been completed. Sediment that needs to be removed will be the responsibility of the contractor and may or may not be deposited at location of removal depending on the contents of the sediment. Any Costic sediment will require the contractor to remove it off-site following all Federal, State and Local regulation for debris removal.
PART 2 – EXECUTION
A. Examination: Examine the project area and site facilities and verify compatibility between existing conditions and the scope of work.
B. Preparation: Take field measurements or conduct surveys to verify dimensions before fabrication or installation.
C. Installation: Install all systems or components according to the specifications, manufacturer’s recommendations, permit conditions (where applicable), and local, State, and Federal codes, standards, and regulations.
D. Correction of the Work: Upon discovery of defects or damage of new work or to existing facilities damaged by new work, repair or replace damaged systems or components and restore substrates and finishes.
E. Progress Cleaning: Clean the project site and work area daily. Keep site free of waste and debris in proper containment. Contractor shall be responsible for disposal of all waste and debris offsite.
F. Final Cleaning & Waste Disposal: At the completion of the work, clean all surfaces and remove all waste materials, trash, tools, equipment, machinery, and surplus items from the project site and legally dispose of all waste items.
PART 3 - REGULATORY AND COMPLIANCE STANDARDS
3.1 All potable water tank cleaning procedures and equipment shall comply with American
Water Works Association (AWWA) and ADC operations for commercial diving in potable water tanks.
The contractor should be familiar with the following standards to complete all work:
• OSHA 29 CFR, Part 1910, Subpart 1910.00 – Safety and Health Requirements
• OSHA 29 CFR, Part 1910, Subpart 1910.401(A)(2)(LV)(B) - Commercial Diving Standards
• OSHA 29 CFR, Part 1910, Subpart 1910(g)(t) - Commercial Diving Operations
• OSHA 29 CFR, Part 1910, Subpart 1910.146 – Permit Required Confined Spaces
• NIOSH 87-113 – Confined Air Space Regulations
• NACE – National Association of Corrosion Engineers
• ANSI/AWWA D101-53(R86) – Inspecting and Repairing Steel Water Storage Tanks
• ANSI/AWWA D102 – Painting and Inspecting Steel Water Storage Tanks
• ANSI/AWWA C652-92 Disinfection of Water Storage Facilities
• ANSI/AWWA D130-97(M25) – Maintenance of Flexible Membrane Covers and Linings
• ASTM D3359-92a – Testing of Coating Adhesion to Metallic Substrates
• NSF 60/61 – Approved For Use in, or in contact with, Potable Water
3.2 UNDERWATER OPERATIONS
A. All four (4) tanks will require a certified diver for cleaning, inspection and repair and follow all applicable laws associated with this project to be performed in the State of Oregon. All reports or permits will be the responsibility of the contractor.
B. All Dive Maintenance Technicians and associated in-tank equipment shall be fully disinfected in accordance with AWWA Standard C652-02.
C. All divers shall be fully encapsulated in a dry suit and helmet, then washed down with 200 ppm chlorine solution prior to entry into the tank.
D. All system entries shall be conducted in accordance with applicable OSHA regulations pertaining to diving in confined spaces, including 1910.401 through 1910.441.
E. Specialty equipment may include but is not limited to appropriate OSHA climbing and personal fall protection, AWWA and ADC approved commercial diving equipment dedicated to in-service potable water operations.
F. Dive team must have OSHA approved Standards, Procedures, and Safe Practices Manual present and available for review at worksite.
3.3 QUALITY CONTROL
A. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance follow applicable specifications, drawings, building codes and standards.
B. Quality Control (QC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. The Contractor’s Quality Control Supervisor shall utilize the forms attached at the end of this Section. The submission frequency of the QC Daily
Report to the contracting officer will be determined at the preconstruction meeting.
3.4 SAFETY REQUIREMENTS
A. First Aid Equipment: Provide adequate first aid equipment for all contract employees and the hazards associated with the types of ongoing construction work at the site.
B. First Aid Training: Provide adequate training to all Contractor personnel to ensure prompt and efficient application of first aid.
C. Personal Protective Equipment (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees.
D. Hazardous Materials: Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury. Store hazardous materials in accordance with manufacturers and OSHA recommendations. Maintain SDS onsite for each chemical used on the jobsite. Immediately report all spills of hazardous materials to the contracting officer.
E. Safety Meetings: At a minimum, conduct weekly "tailgate" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the week.
F. Emergency Contacts: Post telephone numbers and reporting instructions for ambulance, hospital, fire department, police, and park dispatch in conspicuous locations at the site.
G. Emergency Reporting: In the event of an emergency medical incident, the Contractor shall
Dial 911 as needed for any medical emergency, traffic accident, or personal injury occurring within the park. Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles need to enter the Park and so that any available Emergency Medical
Services personnel in the park might respond until such time as the ambulance arrives.
3.4 INSPECTION REQUIREMENTS
A. This work consists of the inspection and analysis of the extent of coating and materials deterioration within and outside the tank.
B. The principal areas of consideration shall be the roof, the exterior wall and appurtenances, the interior underside of the roof and supporting columns and the non-immersed areas of the interior wall and appurtenances.
C. Interior inspection, both over and underwater, shall be conducted to determine coating condition of the tanks’ interior walls, roof beams, columns, ladder, interior coating, depth monitoring equipment, cathodic protection equipment, etc.
D. Water supply to CRLA shall remain uninterrupted during tank inspection.
E. After finishing the tank inspection, contractor shall meet with the NPS water operator to test water to measure the chlorine residual level and turbidity to ensure water is within Oregon
Department of Environmental Quality (ODEQ) drinking water quality standards.
F. Chlorine residual and turbidity shall be tested at the CRLA water sampling locations.
Contractor shall furbish all materials and devices necessary for testing of chlorination and turbidity. Chlorine residual and turbidity shall be tested in the presence of a licensed NPS water operator.
G. If ODEQ drinking water quality standards cannot be met after cleaning and the water in the tank needs to be flushed, then contractor and water operator will begin flushing the tank until the chlorine residual and turbidity is satisfactory of the safe drinking water guidelines.
H. If potable water tank requires flushing, Contractor shall discharge all chlorinated water onto parking lot from the first fire hydrant on the water line, located at the vehicle staging area, adjacent and below the water tanks. Protective measures must be taken to prevent erosion of surfaces when discharging in parking areas, ditches, or trailway.
3.5 CLEANING REQUIREMENTS
A. Cleaning procedure shall combine vigorous brushing of surfaces cleaned, in addition to removal of material from the reservoir by vacuum or water suction. Use of a stationary or fixed brush inside or outside the vacuum head for this purpose is not allowed.
B. Contractor shall ensure that all sediment is removed from the floor to wall seams, support column bases, plumbing fixtures and supports, man entries, or any other areas where the vacuum does not reach during normal floor cleaning.
C. Contractor shall clean the tanks vertical wall surfaces with similar equipment and procedures as used in cleaning the floor.
D. The cleaning procedures shall not create any visible turbidity in the water column.
E. The potable water reservoir shall remain in service during cleaning.
F. Maximum discharge rate during the cleaning operations shall be 200 gallons per minute. The contractor shall make every effort to minimize the quantity of water discharged.
G. During cleaning operations, water may be discharged onto the ground to a location within
200 feet of the tank as approved by the COR.
3.6 VEHICLES/HEAVY EQUIPMENT
A. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
B. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as established by the COR. Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts.
C. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles always.
D. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
E. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the
Contracting Officer of spills.
F. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
G. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the
Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
H. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road). Oversized vehicles must not exceed the clearances along the park road corridor. Oversized vehicles will require an escort and drivers must avoid driving on the edges of the park road. The
Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates, and estimated arrival times at the park entrance; and the identity of who is escorting the vehicle
(e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park
AFTER 2:00 p.m. and exit the Park BEFORE sunset.
I. Road & Weight Restrictions: All vehicle load, weight, and size limitations, as established by
State law, apply to vehicles operated on the park road (36 CFR § 4.11). No loads heavier than the current load rating for park roads and bridges will be permitted.
J. Specific to Garfield Tank Site: Since the Garfield tank is located off trail in wilderness, equipment must be under 36" in width. Use must be kept to a minimum, must not permanently block trail access for visitors, and any erosion from equipment tracks or tires must be mitigated/rehabbed.
3.7 RESOURCE PROTECTION
General: The Park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
A. Preservation of Natural Features: Prevent damage to natural surroundings. Do not attach ropes, wires, guy lines, cables, or chains to trees or vegetation. Restore damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.
B. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles (especially the tires), equipment, tools, supplies, and materials prior to packing / loading. The Park requires and will perform inspections to prevent transport of non-native species PRIOR to arriving at the park entrance.
C. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and watch for animals on or alongside road or at the jobsite. Contact Park Dispatch at 541-592-2100 immediately if animal is hit or injured or will not move off the road.
D. The following measures are required to minimize disturbance to endangered wildlife:
a. Work shall be conducted to ensure the work area is cleaned up at the end of each work shift so that loose tools, debris, and materials are not left out in a manner that could present a hazard to a listed species.
b. Noise and vibrations of equipment shall be kept to a minimum when working in the vicinity of a listed species.
c. Hazmat spill prevention protocols shall be employed when using gas-powered equipment.
d. Tarps shall be used to contain all paint chips and building debris from exterior surfaces that may fall to the ground.
e. Ensure loose nails and screws do not make it to the ground when working on exterior surfaces as these can be detrimental to listed species.
E. Archaeological Resources: Archaeological resources are physical evidence of past human activity, including evidence of the effects of that activity on the environment.
Archaeological resources are found above and below ground and underwater. The
Contractor’s Project Lead/Project Manager, or designee, will observe all ground-disturbing activities in archaeological sensitive areas. If the Contractor discovers resources, the
Contractor shall stop work or relocate to a non-sensitive area and contact the Contracting
Officer immediately. The Park may also have an Archaeological Monitor at the jobsite who is authorized to stop work upon discovery of archaeological resources.
F. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.
3.8 REPAIR REQUIREMENTS
Repair work identified during the inspection process shall be presented to the Government as a change order quote. The Government has the right to accept or reject the repair proposal option.
PART 4 - ALL OTHER REQUIREMENTS
4.1 MOBILIZATION IN/OUT
A. Contractor shall attend a pre-work meeting as arranged by the COR prior to mobilization to the site for starting onsite work.
B. Contractor shall test chlorination residual and turbidity in the presence of an ORCA water operator to ensure water meets the safe drinking water standards, prior to demobilization.
4.2 USE OF THE SITE
The project site will be open to the public & staff during performance of work. The contractor shall always conduct their operations to ensure the least inconvenience to the public and staff.
Temporary closures may be permitted upon approval of the COR.
A. Electrical Power Service: Electrical power service is available from facilities at or near the project site for use on the contract without charge. Provide all connections and extensions of services in a safe manner in compliance with NEC, NEMA, and UL standards and regulations. NOTE: There is no power available at the Garfield site. Contractor will need to provide their own generator(s).
B. Water Service: Potable water service is available from facilities at or near the project site for use on the contract without charge. Provide all connections and extensions of services with proper backflow prevention devices in compliance with AWWA standards and local regulations.
C. Sanitary Facilities: No restrooms available at any of the tank locations. Contractor shall provide their own temporary restroom(s).
D. Telephone Cellular Service: The project site does have cellular service but is spotty.
E. Park Regulations: Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
F. Park Entry: Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
G. Provide the COR with a listing of all contract personnel and their associated vehicles entering the park, either on a daily or weekly basis.
H. Provide the COR with anticipated deliveries for each week, if applicable.
I. Site Access: The contractor shall access the project site as outlined on the attached site map.
Do not drive vehicles off road or access non-project areas without permission from the COR.
J. Working Hours: Work hours shall be limited to 7:00 a.m. until 5:00 p.m. Monday through
Friday, excluding government holidays. Work outside regular hours requires approval from the Contracting Officer.
K. Staging and Storage: Confine the storage of equipment and materials to the staging / lay-down / storage areas as established by the COR.
L. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to a Law Enforcement Ranger or Park Dispatch at the first available opportunity at 541-776-7206
M. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings and buildings under construction or renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
PART 5 – DELIVERABLES PRIOR TO START OF WORK
1. Contractor’s written designation of their Project Lead/Project Manager, the primary point of contact for the COR and must be onsite at all times work is occurring. Email contact info
(name, title, phone, email) to the Contracting Officer and COR.
2. Project Schedule - Submit a baseline schedule with start date before commencement of onsite work. The period of performance is short, 45 days after award, so Contractor’s project schedule can focus on only the major milestones/key tasks/key phases of work through being ready for inspection, and contract completion date. Government anticipates period of performance to be from September 14 – October 30, 2026. Weather may affect total completion to which a seasonal shutdown period may need to go into effect pausing the project during winter months due to snowfall, so the priority is to complete work on the
Garfield tank first.