Attachment_3_Specifications.pdf
PDF 9 MB Posted
- Attached to
- Rehab Limantour Residence 160, Point Reyes N. S.
- Solicitation number
- 140P8426R0003
About this file
This is a Project Specifications document for Request for Proposal (RFP) No. 140P8426R0003 issued by the National Park Service (NPS) Point Reyes National Seashore for the rehabilitation of Limantour Residence 160, a single-family home constructed circa 1962 located at 160 Limantour Drive, Inverness, California. The project addresses foundational stabilization and residential rehabilitation based on recommendations from a 2013 geotechnical and structural analysis that identified slow ongoing settlement due to weak, poorly compacted sandy soil beneath shallow spread footings.
The base contract consists of eight line items valued on a lump-sum percentage-of-completion basis: (1) installation of an Earth Contact Products (ECP) Wall Mounted Steel Pier Foundation System with approximately 44 hydraulically driven steel piers and wall-mounted brackets; (2) installation of an ECP Steel Pier Slab Jack System with approximately 20 hydraulically driven steel piers, slab jacking, lean concrete fill, and patching; (3) interior utility and storage area retaining wall work including demolition and reconstruction of pressure-treated wood walls, soil removal, and PVC wall drain pipe rebuild; (4) removal and rebuild of wood deck, railings, and stair systems with pressure-treated lumber and stainless steel fasteners; (5) demolition and replacement of a driveway retaining wall; (6) installation of a new security screen front door; (7) removal and replacement of lower-level flooring with engineered hardwood plank; and (8) pest exclusion measures. Seven optional line items include exterior painting, upper-level flooring replacement, exterior vinyl window replacement, deck sealing and staining, bathroom rehabilitation, kitchen rehabilitation, and interior painting. The contract period is approximately 10 months from November 9, 2026 to August 31, 2027, with work hours generally limited to 7 a.m. to 5 p.m., Monday through Friday, and work hours outside normal business hours requiring advance approval. The specifications require submittals including a project superintendent designation, detailed construction schedule incorporating long lead times, schedule of values, site-specific safety and health plan, subcontractor list, quality control plan, and waste management plan prior to the preconstruction conference. Contractors must comply with applicable California building codes, National Electrical Code (2023), OSHA requirements, and NPS regulations, including protection of cultural resources, existing utilities, and natural features. All work shall be performed by California-licensed specialty contractors. The residence will be unoccupied during construction, and contractors are responsible for temporary facilities including restroom facilities, dumpsters, water, and power from existing systems at no charge. Final acceptance includes a one-year construction warranty from the date of final acceptance and submission of all manufacturer warranty information and operation manuals organized by division.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PORE 285171 Div. 1 V. 2023-11-11 Page | 1
NATIONAL PARK SERVICE
POINT REYES NATIONAL SEASHORE (PORE)
POINT REYES STATION, CA
REHABILITATE LIMANTOUR RESIDENCE 160
(Morgan Horse Ranch)
PMIS 285171
Drawing Set TIC No: 612-198224
PROJECT SPECIFICATIONS
Request for Proposal (RFP) no. 140P8426R0003 Attachment 3 (8/18/26)
Page | 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 - Division 01 Short Form General Requirements 01 26 01 - Contract Modification Procedures 01 35 23 - Safety Requirements
DIVISION 02 TO 48 – SPECIFICATIONS
02 00 00 to 48 99 99 - Outline Specifications by Division 02 26 00 - Asbestos and Lead Work Plan 02 82 33 - Removal and Disposal of Asbestos Containing Materials 02 83 33 - Removal and Disposal of Material Containing Lead 03 01 30.70 - Concrete Removal and Surface Preparation 03 01 30.71 - Concrete Patching 03 01 30.72 - Concrete Patch Repair 03 21 00 - Reinforcing Steel
DIVISION 99 – VENDOR SPECIFICATIONS AND DETAILS
99 00 01 - PPB-400 - WM Typical Specification – ECP Steel Pier Wall Mounted Systems 99 00 02 - PPB-400 - Wall Mount Bracket Detail 99 00 03 - PPB-166 - Typical Specification – ECP Steel Pier PPB-166 Slab Jack System 99 00 04 - PPB-166 - Hydraulic Lift Slab Bracket Detail
ATTACHMENTS
A - Photos B - Drawings C - Daily Report D - Transmittal Form E - RFI Form F - Submittal Tracking Form G - Accident/Property Damage Report H - Asbestos Testing Records I - Geotechnical Report Excerpt
Page | 3
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: The project site is a two-level single-family home located near Limantour Beach in Point Reyes National Seashore. The residence was constructed circa 1962. Two relatively level pads were graded into the original sloping terrain. The home consists of a main living space on the upper level constructed over a partial basement and garage on the lower level. The upper pad is roughly ten feet above the lower pad. The lower-level partial basement and garage are constructed on a concrete-slab-on-grade. Half of the upper level is on wood frame over the lower level, while the balance is atop a shallow spread footing of unknown dimensions.
A geotechnical and structural analysis was conducted in 2013 due to extensive slab cracking and settlement [reference report included as Attachment I]. The shallow spread footing and slab were identified to be on top of a relatively thin layer (5-9 ft thickness) of weak, poorly compacted, sandy soil that has been subject to slow ongoing settlement. It is expected that slow settlement will continue unless foundation stabilization is undertaken.
This project addresses recommendations for foundational stabilization contained in the 2013 Miller Pacific geotechnical and structural analysis along with other residential rehabilitation items described herein.
The project residence is used for housing park employees. The residence will be vacated and unoccupied during the contract work.
1.2 Work Covered by the Contract Documents:
A. Project Location: The project is located at 160 Limantour Drive, Inverness, CA within Point
Reyes National Seashore. The site is roughly seven miles west of Point Reyes Station, CA at latitude/longitude 38.027080, -122.876278.
https://maps.app.goo.gl/tuMhkELcziufphES8
B. The work consists of the following Price Schedule Line Items, Base and Optional as noted:
a. (Base) Line Item 1 - Install Wall Mounted Steel Pier Foundation System
i. Install Earth Contact Products (ECP) Wall Mounted Steel Pier System consisting of approximately 44 hydraulically driven steel piers with wall mounted brackets around the slab perimeter and the spread footing foundation perimeter as shown on the drawings.
ii. Lift the perimeter structure foundation level in coordination with the lower level slab and mechanically secure the load to the wall mounted brackets.
b. (Base) Line Item 2 - Install Slab Jack Steel Pier Foundation System https://maps.app.goo.gl/tuMhkELcziufphES8
Page | 4
i. Install ECP Steel Pier Slab Jack System consisting of approximately 20 hydraulically driven steel piers with slab jack brackets in the lower level slab as shown on the drawings.
ii. Lift the slab level and mechanically secure the slab to the brackets.
iii. Install lean concrete in the void between the slab and the underlying soil.
iv. Patch holes and cracks in the slab.
c. (Base) Line Item 3 - Install Interior Utility & Storage Area Retaining Wall & Excavate New Slab & Utility Access
i. Demolish approximately 4 linear feet of pressure treated wood retaining wall, approximately 3.5-ft high.
ii. Remove approximately 3.33 cubic yards (90 cubic feet) of soil to facilitate new retaining wall construction.
iii. Install approximately 15 linear feet of pressure treated wood retaining wall, approximately 3.5-ft high.
iv. Rebuild approximately 18 linear feet of PVC wall drain pipe disturbed by new wall construction.
v. Install approximately 50 square feet of 6-inch thick aggregate walkway.
ci. d. (Base) Line Item 4 - Remove and Rebuild Wood Deck, Railing, Stair System
i. Demolish and dispose of existing wood deck, railing, and stair system.
ii. Install new deck footings.
iii. Rebuild deck, railing, and stair system with pressure treated lumber.
cii. e. (Base) Line Item 5 - Remove and Replace Driveway Retaining Wall
i. Demolish existing 17-ft long by 3-ft high wood and block retaining wall along the driveway.
ii. Rebuild new pressure treated lumber retaining wall.
ciii. f. (Base) Line Item 6 - Install New Security Screen Front Door
i. Install a new security screen door on the front entry door of the residence.
civ. g. (Base) Line Item 7 - Remove and Replace Flooring – Lower Level
i. Remove existing carpet in lower level Bedroom 3 and from the stairs between floors.
ii. Install new engineered wood plank flooring in Bedroom 3 and on the stairs between floors following foundation repair completion.
cv. h. (Base) Line Item 8 - Pest Exclusion
i. The contractor shall install pest-exclusion measures to prohibit the intrusion of rodents into the residence. Patch holes, install metal mesh, and/or install other exclusions as needed.
cvi. (Optional) Option Line Item A - Paint Exterior Siding and Trim
i. The contractor shall paint the exterior wood siding and trim of the structure with two coats of Sherwin Williams Emerald Exterior Acrylic Satin K48 Series.
cvii. (Optional) Option Line Item B - Remove and Replace Flooring – Upper Level
i. Remove existing carpet in the upper level dining area, living room, bedrooms, closets. Remove existing vinyl and plank flooring in the living room, hallways, utility room, bedrooms, and closets.
ii. Install new engineered wood plank flooring in the upper level dining area, living room, hallways, bedrooms, closets, and utility room.
cviii. (Optional) Option Line Item C - Install New Exterior Vinyl Windows
i. Remove all nine exterior sliding windows and replace each with Simonton
DaylightMax or 6200 Series (or approved equal) vinyl windows of the same nominal size. Patch openings and trim to match existing, interior and exterior.
Page | 5
l. (Optional) Option Item D - Seal and Stain New Deck, Railings, Stairs, and Retaining Wall
i. Pressure wash wood to be sealed.
ii. Apply PenaShield Ready-to-use Wood Preservative.
iii. Seal and stain new pressure treated wood deck, railings, stairs, and retaining wall with two coats of Seal-Once Marine Ready Mix marine premium wood sealer or approved equal.
li. (Optional) Option Item E - Bathroom Rehabilitation
i. Demo existing bathroom. Install new mold-resistant purple drywall, resinous flooring, vanity, sinks, faucets, toilet, tub/shower combo, tub/shower faucet, cabinets, mirror, lighting, shelving, hardware, and vent fan.
lii. (Optional:) Option Item F - Kitchen Rehabilitation
i. Demo existing kitchen. Install new cabinets, hardware, countertops, sink, faucet, resinous flooring, vent hood, dishwasher. Salvage and reinstall existing refrigerator and electric stove.
liii. (Optional) Option Item G - Paint Interior Walls and Ceilings
i. Painting interior walls, ceilings, built-ins, painted trim, and painted millwork with two coats of interior acrylic latex paint.
C. All work will be performed under a single contract.
D. Period of performance: Approx. 10 months from November 9, 2026 to August 31, 2027.
a. Clarification: The Notice to Proceed issued with the stated period of performance that will be all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days.
E. All dimensions and measurements provided herein are approximate and provided for reference. All dimensions and measurements should be verified by the contractor.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
i. The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological remains or data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts not specifically noted within the contract. The Contractor shall immediately suspend all operations in the vicinity and continue work in other areas outside a 50-foot radius of discovery and notify the
Page | 6
Contracting Officer immediately. When safe to do so, follow up in writing with photographs within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
B. The structure involved in the work of this Contract is not a designated historic structure listed in the National Register of Historic Places.
C. Protection of Landscaping, Utilities, and Surrounding Structures: All Ground Disturbance at this project shall have oversite by the COR. The Contractor shall take all necessary measures to provide protection for all trees, fencing, walks, utilities, drains, other landscape features, and surrounding structures near the work site as noted with the contract. Any such surrounding features damaged, scarred or broken as a result of the Contractor’s operations at the site and/or outside of agreed upon documented extents, shall be treated, repaired or replaced in kind to the satisfaction of the Contracting Officer at no additional expense to the Government.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns that impact other properties/adjacent sites shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods
Page | 7 longer than stated allowance or if required for critical systems as determined by COR. Utility shutdowns to the project site shall otherwise be limited to the extent practicable.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
https://www.nps.gov/pore/learn/management/lawsandpolicies_superintendents_compendium.htm
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes. Smoking waste shall be deposited safely into approved receptacles and shall be disposed of and otherwise safely removed from the site.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. Road traffic at this site is limited to residents of park housing.
The public is discouraged from accessing the project area; but not explicitly prohibited. Safe access to the adjacent residence shall be maintained.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year’s Day Inauguration Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day https://www.nps.gov/pore/learn/management/lawsandpolicies_superintendents_compendium.htm Phaedra Fuller Cross-Out
Page | 8
• Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of the minimum required footprint required to complete the work.
Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction. Contractor shall remediate soil compaction as directed to do so by the CO/COR.
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract
Sum as required.
2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges as limited by the service. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators as needed. Use power in a resourceful manner and avoid excess power waste.
4. Sanitary Operations: Restrooms are not available at the immediate project site for contractor use. Public (vault toilet) restrooms are located within approximately 0.6 miles of the site. The contractor is expected to provide temporary toilet and handwashing facilities for employees onsite.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022
Page | 9 of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant Protection: Trees and plants not in the direct line of work shall be protected from disturbance. Avoid unnecessary vehicle traffic over tree root systems.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: Provide fencing and barriers around work areas as needed for safety.
6. Hot Work Permit: Prior to conducting any hot work, provide a permit to the COR for approval and coordinate scheduling with the COR for awareness.
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Storage units may be provided by the contractor and located at the site at locations approved by the COR. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility. Any ground disturbance from storage and staging shall be restored to the existing condition or better.
3.5 Preservation of Natural Features: Preserve natural features by avoiding unnecessary actions that will disturb such.
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.7 Waste Removal, Recycling, and General Housekeeping:
A. Keep project site in a neat, orderly, and safe condition at all times.
1. Contractor is responsible for providing dumpsters for waste and recycling and for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site.
Coordinate with COR for approved dumpster locations prior to commencing construction.
2. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters.
3. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to the extent possible during this project, recycling material as much as possible within local
Page | 10 means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
4. For all waste and recycling removals offsite, contractors shall provide estimates and/or tickets to quantify material weights and report back to the park, submit to COR for review and record filing.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Government Occupancy: The Government will not occupy this Residence/building that will be under construction during the entire contract period. Provisions shall be made to limit construction dust and debris from entering the residence during construction.
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital format and submitted electronically by email or file share, 8 mega pixels minimum, within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meeting. This/these meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at
Page | 11 the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA
29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
B. Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
C. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
a) Do not exceed 100 dB(A) at 50 feet.
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION – SITE SPECIFIC SAFETY AND HEALTH PLAN
7.1 See award special contract requirements and specifications Section 01 35 23 Safety
Requirements.
https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.nps.gov/orgs/1671/do-business-with-us.htm
Page | 12
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 The Contractor is required to attend a preconstruction conference prior to the issuance of the
Notice to Proceed. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below. At a minimum, the designated Project Superintendent is required to attend this conference.
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan / Site-Specific Safety and Health (see award special contract requirements, section 7 of this document, and specifications Section 01 35 23 Safety Requirements).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical
Page | 13 specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
Page | 14
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the
Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
Page | 15
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. COR/Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of
Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
Page | 16
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
A. Contract Line-Item No. 0001 - Install Wall Mounted Steel Pier Foundation System
1. This item consists of:
a. Install Earth Contact Products (ECP) Wall Mounted Steel Pier System consisting of approximately 44 hydraulically driven steel piers with wall mounted brackets around the slab perimeter and the spread footing foundation perimeter as shown on the drawings.
b. Lift the perimeter structure foundation level in coordination with the lower level slab and mechanically secure the load to the wall mounted brackets.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
B. Contract Line-Item No. 0002 - Install Slab Jack Steel Pier Foundation System
1. This item consists of:
a. Install ECP Steel Pier Slab Jack System consisting of approximately 20 hydraulically driven steel piers with slab jack brackets in the lower level slab as shown on the drawings.
b. Lift the slab level and mechanically secure the slab to the brackets.
c. Install lean concrete in the void between the slab and the underlying soil.
d. Patch holes and cracks in the slab.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
C. Contract Line-Item No. 0003 - Install Interior Utility & Storage Area Retaining Wall & Excavate New Slab & Utility Access
1. This item consists of:
a. Demolish approximately 4 linear feet of pressure treated wood retaining wall, approximately 3.5-ft high.
b. Remove approximately 3.33 cubic yards (90 cubic feet) of soil to facilitate wall construction.
c. Install approximately 15 linear feet of pressure treated wood retaining wall, approximately 3.5-ft high.
d. Rebuild approximately 18 linear feet of PVC wall drain pipe disturbed by new wall construction.
e. Install approximately 50 square feet of 6-inch thick aggregate walkway.
Page | 17
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
D. Contract Line-Item No. 0004 - Remove and Rebuild Wood Deck, Railing, Stair System
1. This item consists of:
a. Demolish and dispose of existing wood deck, railing, and stair system.
b. Install new deck footings.
c. Rebuild deck, railing, and stair system with pressure treated lumber.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
E. Contract Line-Item No. 0005 - Remove and Replace Driveway Retaining Wall
1. This item consists of:
a. Demolish existing 17-ft long by 3-ft high wood and block retaining wall along the driveway.
b. Rebuild new pressure treated lumber retaining wall.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
F. Contract Line-Item No. 0006 - Install New Security Screen Front Door
1. This item consists of:
a. Install a new security screen door on the front entry door of the residence.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
G. Contract Line-Item No. 0007 - Remove and Replace Flooring – Lower Level
1. This item consists of:
a. Remove existing carpet in lower level Bedroom 3 and from the stairs between floors.
b. Install new engineered wood plank flooring in Bedroom 3 and on the stairs between floors following foundation repair completion.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
H. Contract Line-Item No. 0008 - Pest Exclusion
1. This item consists of:
Page | 18
a. The contractor shall install pest-exclusion measures to prohibit the intrusion of rodents into the residence. Patch holes, install metal mesh, and/or install other exclusions as needed.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
I. Optional Contract Line-Item No. 0009 - Paint Exterior Siding and Trim
1. This item consists of:
a. The contractor shall paint the exterior wood siding and trim of the structure with two coats of Sherwin Williams Emerald Exterior Acrylic Satin K48 Series.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
J. Optional Contract Line-Item No. 0010 - Remove and Replace Flooring – Upper Level
1. This item consists of:
a. Remove existing carpet in the upper level dining area, living room, bedrooms, closets. Remove existing vinyl and plank flooring in the living room, hallways, utility room, bedrooms, and closets.
b. Install new engineered wood plank flooring in the upper level dining area, living room, hallways, bedrooms, closets, and utility room.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
K. Optional Contract Line-Item No. 0011 - Install New Exterior Vinyl Windows
1. This item consists of:
a. Remove all nine exterior sliding windows and replace each with Simonton DaylightMax or 6200 Series (or approved equal) vinyl windows of the same nominal size. Patch openings and trim to match existing, interior and exterior.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
L. Optional Contract Line-Item No. 0012 - Seal and Stain New Deck, Railings, Stairs, and Retaining Wall
1. This item consists of:
a. Pressure wash wood to be treated.
b. Apply PenaShield Ready-to-use Wood Preservative.
c. Seal and stain new pressure treated wood deck, railings, stairs, and retaining wall with two coats of Seal-Once Marine Ready Mix marine premium wood sealer or approved equal.
Page | 19
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
M. Optional Contract Line-Item No. 0013 - Bathroom Rehabilitation
1. This item consists of:
a. Demo existing bathroom. Replace drywall walls and ceilings with new mold-resistant purple drywall.
b. Provide and install new vanity, sink(s), faucets, toilet, tub/shower combo, tub/shower faucet, cabinets, mirror, lighting, shelving, hardware, vent fan, towel bar, hand towel bar, towel hooks, toilet paper roller, and appurtenances per the specifications.
c. Install new electrical and code compliant outlets as needed. Replace lighting.
d. Install new water resilient bathroom flooring. High performance resinous flooring: Sherwin Williams Resuflor Topcoat Metallic or approved equal.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
N. Optional Contract Line-Item No. 0014 - Kitchen Rehabilitation
1. This item consists of:
a. Demo existing kitchen. Salvage and reinstall existing refrigerator and electric stove.
b. Provide and install new flat front/shaker traditional box cabinets with plywood box construction, full overlay doors, painted/stained solid wood face frame/doors, soft close doors/drawers (lowers, uppers, island), and hardware.
c. Provide and install new vent hood and exhaust. Provide and install standard dishwasher unit with new required electrical and water connections.
d. Provide and install double bowl farmhouse style sink [ceramic/quartz], single handle pull-down sprayer faucet [stainless], quartz countertops, quartz backsplash, and quartz bench countertop.
e. Install new water resilient kitchen flooring. High performance resinous flooring:
Sherwin Williams Resuflor Topcoat Metallic or approved equal.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
O. Optional Contract Line-Item No. 0015 - Paint Interior Walls and Ceilings
1. This item consists of:
a. Painting interior walls, ceilings, built-ins, painted trim, and painted millwork with two coats of interior acrylic latex paint.
2. Measurement for payment will be made based on the percentage completion level of the work included in the line-item.
Page | 20
3. Payment will be made per the percentage of completion level of the lump sum price of the work included in the line-item.
END OF SECTION
PORE 285171 01 26 01 - 1
CONTRACT MODIFICATION PROCEDURES
NPS Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
Limantour Residence 160 Rehabilitation
PMIS-285171
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating
General Conditions:
PORE 285171 01 26 01 - 2
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel…