Attachment 3 Specification Critical Housing DM Crawford WC.pdf
PDF 1 MB Posted
- Attached to
- Critical Housing Maintenance Construction at Crawford Work Center, Boise National Forest, Idaho (GAOA)
- Solicitation number
- 1240LT26Q0017
About this file
This is a Specification and Statement of Work (SOW) document for critical housing maintenance construction at the Crawford Work Center in the Cascade Ranger District of the Boise National Forest, Idaho. The project involves remodeling a barracks (1199 Crawford Barracks) and mess hall (1606 Crawford Mess Hall) with work including bedroom reconfiguration, bathroom renovation, flooring replacement, interior painting, snow guard installation, and associated site work. The barracks work converts five shared bedrooms into nine individual bedrooms plus a laundry room with new doors, lighting, baseboard heaters, flooring, and appliances. The mess hall remodeling includes bathroom and bedroom modifications, laundry room installation with washer/dryer, window blind replacement, baseboard heater upgrades, and interior finishing. Site work encompasses removal of existing porch structures, concrete sidewalk construction, and propane tank installation with associated piping and pad.
The contract is a firm-fixed-price Purchase Order under a 100% Small Business Set-Aside with estimated construction costs between $250,000 and $500,000. The estimated start date is April 1, 2026, with required completion by April 15, 2027, though no interior work is permitted from April 15 through October 31, 2026. Quotation deadline is 5:00 p.m. Central Standard Time on March 10, 2026, with technical proposals addressing past performance, technical experience, and project management approach required alongside price proposals. A mandatory site visit is scheduled for February 24, 2026, at 9:00 a.m. Mountain Time. Payment and Performance Bonds are required. The specification document includes detailed requirements across multiple construction disciplines including concrete, carpentry, plumbing, electrical, HVAC, flooring, painting, and landscape work, with comprehensive submittal, quality control, and inspection procedures specified throughout.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
CRITICAL HOUSING MAINTENANCE
CONSTRUCTION AT CRAWFORD WORK CENTER
Final Revision – 4/7/2025
1.1 SCOPE OF CONTRACT
A. This project includes remodeling a barracks and mess hall at the Crawford Work Center in the Cascade Ranger District of the Boise National Forest.
B. The includes the following work and all related activities:
1. 1. 1199 CRAWFORD BARRACKS
a. Remodel bedrooms -turn 5 shared bedrooms into 9 bedrooms and a laundry room
1) Construct partition walls
2) Install 36" doors
3) Install new light switches and fixtures
4) Install new baseboard heaters
5) Replace blinds
6) Install washer, dryer and associated utilities
7) Install countertop and cabinets
b. Remodel bathroom into 2 accessible bathrooms
1) Remove existing showers, toilets, sinks, and hot water heaters
2) Construct new divider walls
3) Install new doors, showers, sinks, toilets, mirrors, tp holders, towel hooks, and on demand hot water heater
4) Install new lighting, switches and wall heaters
c. Replace all flooring with lvp flooring
d. Patch all drywall and ceilings
e. Paint all interior walls, ceilings and trim
f. Install snow guards on roof
g. Install new electronic door lock on front door
2. 2. 1606 Crawford Mess Hall
a. Remodel bathroom and bedrooms
1) Remove existing shower, toilet, sink
2) Construct partition wall
3) Install 36" doors
4) Install new baseboards and wall heater w/ thermostats
5) Install new lights and switches
6) Install LVP flooring
7) Install new shower, toilet, sink, mirror, tp holder, and towel rack
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
b. Remodel laundry room
1) Install new electronic keypad lock on existing exterior door
2) Install new partition wall with fridge, washer and dryer connections
3) Install new stacked washer and dryer, on demand hot water heater, and mop basin
4) Move existing cabinets
c. Replace existing vent hood
d. Replace all window blinds
e. Replace all baseboard heaters
f. Paint all interior walls, ceiling and trim
g. Install snow guards on roof
3. Site work
a. Remove existing porch roof, concrete stairs and wood boardwalk
b. Construct concrete sidewalk
c. Install propane tank, pad, and propane lines
C. Quantities associated with these options are identified in the Schedule of Items.
1.2 PROJECT LOCATION
A. The project is located in the Cascade Ranger District of the Boise National Forest, Valley County, Idaho, in Section 21, T14N, R4E Boise Meridian. It is located approximately 4 miles east of Cascade, Idaho. The project may be accessed from State Highway 55 and Warm Lake Road.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Crawford Work center is an administrative site closed to the public. The barracks and mess hall will be closed to FS personnel during construction but the rest of the Crawford Work Center will remain open to administrative personnel. The Forest Service will issue a closure order. The Contractor will be responsible for signing and limiting access.
2. Contractor will provide all materials and labor necessary to protect streams, wet or dry, during construction activities. The Contractor will be required to submit a stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction.
3. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
D. No interior work is allowed during the period 4/15/2026 through 10/31/2026.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3
4. Water is available at the site for construction purposes. Utilities are not available at the site for construction purposes.
5. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Idaho Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site.
B. No overnight camping will be allowed on site.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature
1.7 and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
ESTIMATED START DATE
A. APRIL 1, 2026
1.8
1.9
CONTRACT TIME
A. 15 Months. No interior work shall occur while the barracks are occupied April 15, 2026- October 31st, 2026.
SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
SECTION 011250 - MEASUREMENT AND PAYMENT
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-4
SECTION 011400 - WORK RESTRICTIONS
SECTION 011900 - MOBILIZATION
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 014100 - QUALITY CONTROL
SECTION 015100 - TEMPORARY TRAFFIC CONTROL
SECTION 017320 - SELECTIVE DEMOLITION
SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES
SECTION 024100 - WASTE MATERIAL DISPOSAL
SECTION 024113 - SELECTIVE SITE DEMOLITION
SECTION 033000 - CAST-IN-PLACE CONCRETE
SECTION 033540 - CONCRETE SIDEWALK
SECTION 061000 - ROUGH CARPENTRY
SECTION 064116 - PLASTIC-LAMINATE-FACED ARCHITECTURAL
CABINETS
SECTION 072100 - THERMAL INSULATION
SECTION 077253 - SNOW GUARDS
SECTION 081416 - FLUSH WOOD DOORS
SECTION 087100 - DOOR HARDWARE
SECTION 092900 - GYPSUM BOARD
SECTION 096513 - RESILIENT BASE AND ACCESSORIES
SECTION 096519 - RESILIENT TILE FLOORING
SECTION 099001 - COLORS
SECTION 099123 - INTERIOR PAINTING
SECTION 102800 - TOILET AND BATH ACCESSORIES
SECTION 113100 - RESIDENTIAL APPLIANCES
SECTION 122113 - HORIZONTAL LOUVER BLINDS
SECTION 220500 - COMMON WORK RESULTS FOR PLUMBING
SECTION 220501 - INTERIOR PEX PIPING
SECTION 221316 - SANITARY WASTE AND VENT PIPING
SECTION 223400 - FUEL-FIRED, DOMESTIC-WATER HEATERS
SECTION 224100 - RESIDENTIAL PLUMBING FIXTURES
SECTION 224213.13 - WATER CLOSETS
SECTION 224216.13 - COMMERCIAL LAVATORIES
SECTION 231126 - FACILITY LIQUEFIED-PETROLEUM GAS PIPING
SECTION 260000 - COMMON WORK RESULTS FOR ELECTRICAL
SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND
CABLES
SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
SECTION 260533.13 - CONDUITS FOR ELECTRICAL SYSTEMS
SECTION 260923 - LIGHTING CONTROL DEVICES
SECTION 262726 - WIRING DEVICES
SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS
SECTION 312000 - EARTHWORK
SECTION 312010 - SELECT BORROW
SECTION 312100 - PROJECT SITE PREPARATION AND GRADING
SECTION 321204 - CRUSHED AGGREGATE BASE OR SURFACE COURSE
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-5
END OF SECTION C
April 2025
MEASUREMENT AND PAYMENT 011250-1
USDA FOREST SERVICE, R4
Set New Title
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
MEASUREMENT AND PAYMENT 011250-2
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
MEASUREMENT AND PAYMENT 011250-3
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
WORK RESTRICTIONS 011400-1
Set New Title
SECTION 011400 - WORK RESTRICTIONS
PART 1 - GENERAL
1.1 USE OF PREMISES
A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to the barracks and mess hall. Work to be complete between 7am and 7pm.
2. Government Occupancy: Allow for Government occupancy of the Crawford Work Center.
3. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Occupants, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
B. Use of Existing Building: Maintain existing building in a weathertight condition throughout construction period. Repair damage caused by construction operations.
Protect building and its occupants during construction period.
1.2 OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will occupy work center during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government operations.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011400
MOBILIZATION 011900-1
Set New Title
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
SUBMITTAL PROCEDURES 013300-1
Set New Title
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
SUBMITTAL PROCEDURES 013300-2
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
SUBMITTAL PROCEDURES 013300-3
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
SUBMITTAL PROCEDURES 013300-4
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required
SUBMITTAL PROCEDURES 013300-5
submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section Section Title Subse ction Required Submittal
C General Specifications 1.3, 1.4
Stream Protection Plan, Traffic Control Plan
013300 Submittal Procedures 2.1D Construction Schedule 014100
Quality Control
1.3 Contractor quality control plan, Permits, Licenses and
Certificiates, Test and Inspection Reports, As- Built drawings
017320 Selective Demo 1.4 Schedule of Selective Demo Activities
023701 Sediment & Erosion Control Measures
1.2A Sediment & Erosion Control Plan
033000
Cast-in-Place Concrete
1.3 Product Data, Design Mix, Shop
Drawings, Samples, Qualifcation
Data, Material Test Reports, Material Certificaties
061000 Rough Carpentry 1.3.A Product Data 064116 Plastic-Laminate Faced
Architechtural Cabinets
1.2 Product Data, Shop Drawings, Samples 072100 Thermal Insulation 1.2 Product Data 077253 Snow Guards 1.2 Product Data, Shop Drawings, Samples 081416 Flush Wood Doors 1.2 Product Data, Shop Drawings 087110 Door Hardware 1.2 Product Data, Hardware Schedule, Keying Schedule 092900 Gypsum board 1.2.A Product Data 096530 Resilient Wall Base and Accessories 1.2A Product Data 096519 Resilient Tile Flooring 1.2 Product Data, Samples, Maintenance Data 099120 Interior Painting 1.2 Product Data, Samples 102800 Toilet and Bath Accessories 1.2 Product Data, Maintenance Data 113100 Residential Appliances 1.2,
1.3 Product Data, Operation and
Maintenance Data, Final Warranty 122113 Horizontal Louvered Blinds 1.2 Product Data, Shop Drawings, Samples, Maintenance Data 220500 Common Work Results for Plumbing 1.3A Welding Certificates 220501 Interior PEX Piping 1.3 Product Data 221316 Sanitary Waste and Vent Piping 1.3 Product Data 223400 Fuel Fired Domestic Water Heaters
Instantaneous
1.2- 1.5
Product Data, Product Certificates, Labels, Operation and Maintenance Data, Warranty
SUBMITTAL PROCEDURES 013300-6
Spec.
Section Section Title Subse ction Required Submittal
224100 Residential Plumbing Fixtures 1.3 Product Data, Maintenance Data 224213 Water Closets 1.3 Product Data 224216
Commercial Lavatories
1.2 Product Data, Operations and
Maintenance Data, Extra Materials
231126
Facility Liquified Petroleum Gas Piping
1.4 Product Data, Shop Drawing, Concrete Footers, Pipe Sizing
Calculations, Field Quality Control Reports, Operation and
Maintenance Data 260000 Common Work Results for Electrical 1.5 Product Data, Operation and
Maintenance Data 260923 Lighting Control Devices 1.2 Product Data, Operations and
Maintenance Manual 262726 Wiring Devices 1.2 Product Data
262816 Enclosed Swithced and Circuit Breakers
1.3 Product Data
312000 Earthwork 1.3 Aggregate and Backfill Sources, Certified Sieve Analysis
END OF SECTION 013300
QUALITY CONTROL 014100-1
Set New Title
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
D. As-Built Drawings
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not Applicable)
QUALITY CONTROL 014100-2
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit three copies of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
QUALITY CONTROL 014100-3
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and reinspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
B.
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency
033000 2.12 Mixing and Delivery Each Truck 033000 3.13 Concrete – Slump, Air, Temperature 1 composite per truck load delivered 033000 3.13 Concrete - Compression Test
Specimens at 7 days and 28 days (see spec)
231126 3.6 LPG Pipe Test, Inspect, & Purge See Spec.
312000 3.13C Compaction Test – at Pipe Zone One per 600 Feet of
Trench 312000 3.13C Compaction Test – at Pipe Zone One test – at each road crossing 312000 3.13D Compaction Test – above Pipe
Zone One per 600 Feet of
Trench
QUALITY CONTROL 014100-4
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency 312000 3.13D Compaction Test – above Pipe
Zone One test every other lift – at each road crossing
312000 3.13I Tracer Wire Conductivity Test Until Passing 312000 3.16A Compaction Test – Backfill/Fills One per Tank, Utility Building or Utility Box
312000 3.18A Compaction Test - Subsurface Drainage Material
One per Tank
312000 3.18B Compaction Test – Drainage Backfill
One per Tank
312000 3.19D Compaction Test – Backfill/Fills under Buildings
One test every 600 S.F. area per lift, minimum of one test per building
312000 3.19D Compaction Test – Exterior Concrete Slabs
1 per slab
312000 3.19D Compaction Test – Backfill/Fills and Subgrade under Buildings and
Driveways
One test every 150
sq. yd. area per lift and at Subgrade 312000 3.19D Compaction Test – Backfill/Fills
Foundation Walls One test for each 100 feet of wall length
END OF SECTION 014100
TEMPORARY TRAFFIC CONTROL 015100-1
Set New Title
SECTION 015100 - TEMPORARY TRAFFIC CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. This work consists of furnishing, maintaining, relocating, and removing temporary traffic control and safety devices and services for the control and protection of public traffic near the project site. Prior to beginning construction the Contractor shall submit a traffic control and safety plan to the Contracting Officer for review and approval. As a minimum the traffic control and safety plan shall address signing in and near the project site and at all road and highway junctions that will be used as access to the project site, material sources, water sources and disposal sites as well as any other areas where the Contractor will be performing work under this contract.
1.2 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 2 - PRODUCTS
2.1 TRAFFIC CONTROL
A. Traffic control and safety device (barricades, cones, tubular markers, vertical panels, drums, portable barriers and so forth) designs and configurations shall conform to the MUTCD. When interpreting the requirements in the applicable MUTCD sections, replace the word should with the word shall.
PART 3 - EXECUTION
3.1 GENERAL
A. All signs shall be constructed to comply with the requirements of MUTCD for the construction operations. Install and maintain temporary traffic control and safety devices adjacent to and within the project as shown on the approved traffic control and safety plan and MUTCD. Install and maintain traffic control and safety devices as follows:
1. Furnish and install traffic control and safety devices before the start of construction operations.
2. Install only those traffic control and safety devices needed for each stage or phase.
3. Relocate temporary traffic control devices as necessary.
4. Immediately replace any device that is lost, stolen, destroyed, or inoperative.
5. Keep temporary traffic control and safety devices clean.
TEMPORARY TRAFFIC CONTROL 015100-2
6. Remove all temporary traffic control devices upon contract completion or when approved.
B. Barricades
1. Perform the work described under MUTCD Part VI. Use type III or IV reflective sheeting. Use wood, metal, or plastic barricades. When type II barricades are used, use barricades that collapse when tipped over.
C. Construction Signs
1. Use type III or IV reflective sheeting. Use wood, metal, fiberglass, or other approved posts.
END OF SECTION 015100
SELECTIVE DEMOLITION 017320-1
Set New Title
SECTION 017320 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes demolition and removal of the following:
1. Selected portions of a building.
2. Repair procedures for selective demolition operations.
1.2 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Salvage: Detach items from existing construction and deliver them to Government.
C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.
D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site.
1.4 SUBMITTALS
A. Schedule of Selective Demolition Activities: Indicate detailed sequence of selective demolition and removal work, with starting and ending dates for each activity, including interruption of utility services.
B. Waste Manifests for materials deemed hazardous by the State of Idaho including refrigerant and fluorescent lights.
1.5 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI A10.6 and NFPA 241.
SELECTIVE DEMOLITION 017320-2
C. Pre-demolition Conference: Conduct conference at Project site with contractor, subcontractors and Contracting Officer’s Representative.
1.6 PROJECT CONDITIONS
A. Conduct selective demolition so Government operations will not be disrupted. Provide not less than 72 hours' notice to CO of activities that will affect Government operations.
B. Maintain access to existing building amenities, pathways, and other adjacent occupied or used facilities.
1. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the COR.
C. Government assumes no responsibility for condition of areas to be selectively demolished.
1. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.
D. Storage or sale of removed items or materials on-site will not be permitted.
1.7 MEASUREMENT AND PAYMENT
A. Selective Demo – Lump Sum per building including full compensation for all labor, equipment, hauling, dumping and incidentals necessary to complete the work as shown on the drawings.
PART 2 - PRODUCTS
2.1 REPAIR MATERIALS
A. Use repair materials identical to existing materials.
1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.
2. Use materials whose installed performance equal or surpasses that of existing materials.
3. Salvage appliances and cabinets as noted in the plans and store for reinstallation.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped.
B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
SELECTIVE DEMOLITION 017320-3
C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.
3.2 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Do not close or obstruct roads, without permission from CO. Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.
2. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.
3. Protect existing site improvements, appurtenances, and landscaping to remain.
B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
C. Temporary Enclosures: Provide temporary enclosures for protection of existing building and construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.
3.3 POLLUTION CONTROLS
A. Dust Control: Use temporary enclosures, and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations.
B. Disposal: Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
1. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.
C. Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
3.4 SELECTIVE DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.
1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.
SELECTIVE DEMOLITION 017320-4
2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.
4. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
5. Use cardboard or a drum to store fluorescent lighting to prevent breakage. Label the container clearly as ““Universal Waste Mercury-Containing Lamp(s)”
6. Demo condensing units and drinking fountain in a manner that will not release refrigerant.
7. Dispose of universal hazardous waste as required by EPA and State laws. A disposal site is listed above.
B. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.
2. Pack or crate items after cleaning and repairing. Identify contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
3.5 PATCHING AND REPAIRS
A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.
B. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.
1. Completely fill holes and depressions in existing masonry walls that are to remain with an approved masonry patching material applied according to manufacturer's written recommendations.
C. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.
D. Floors and Walls: Where walls or partitions that are demolished extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish color, texture, and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.
SELECTIVE DEMOLITION 017320-5
E. Ceilings: Patch and repair existing ceilings as necessary to provide an even-plane surface of uniform appearance.
3.6 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.
B. Dispose of universal hazardous waste as required above.
C. Burning: Do not burn demolished materials.
D. Disposal: Transport demolished materials off Government property and legally dispose of them.
END OF SECTION 017320
FEBRUARY 2022
SEDIMENT AND EROSION CONTROL MEASURES 023701-1
Set New Title
SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES
PART 1 - GENERAL
1.1 The work under this section consists of furnishing all necessary labor, equipment, materials, and performing all operations in connection with construction sediment and control measures.
A. General
1. All erosion and sediment control measures are to be placed prior to any disturbance caused by grading and or excavation and shall conform to the requirements of the appropriate regulatory agency for the State.
2. The Contractor shall be solely responsible for ensuring that erosion and sediment control measures are implemented and maintained at the site.
3. Soil disturbing activities include but are not limited to: Clearing and grubbing, excavation for utilities and foundations, roadway and parking lot construction, construction or modification of site drainage, grading, and preparation for final seeding.
1.2 SUBMITTALS
A. The Contractor shall be required to submit a sediment and erosion control plan in accordance with this specification for approval by the Contracting Officer 2 weeks prior to start of work.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 SYNTHETIC FILTER FABRIC FOR SILT FENCES.
A. Pervious sheet of polypropylene, nylon, or polyethylene fabric conforming to the following physical and hydraulic characteristics:
Physical Properties (Min.) Requirement Test Method Grab…