This document is a Schedule of Items for a Solicitation related to Drinking Water Sanitary Surveys throughout the Chugach National Forest in Alaska. The solicitation number is 1240BF24Q0045, and it is issued by the Department of Agriculture Forest Service.

The Schedule of Items outlines the contract line items (CLINs) for the base year and three option years. The CLINs include performing sanitary surveys at various locations within the Chugach National Forest, such as the Kenai Lake Work Center, Glacier Ranger District Office, Begich Boggs Visitor Center, and multiple campground and water system locations. The estimated quantities and unit prices are provided for each CLIN, with the total estimated cost for the base year and option years. The performance period is from the date of award through April 30, 2028.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SUMMARY SHEET

ONLY FILL OUT THE YELLOW HIGHLIGHTED CELLS THROUGHOUT THIS QUOTE SHEET
The quanities in this quote sheet are estimates only. The unit prices will not be changed based on the quantities ordered.
Chugach National Forest - Drinking Water Sanitary Survey
SOLICITATION: 1240BF24Q0045
Company Name:
Point of Contact (POC):
CAGE Code:
UEI Number:
Address:
Phone:
E-mail:
Fax:
Base Year - Date of Award - 04/30/2025
CLIN # (Item number)DescriptionEstimated QuantityUnitUnit PriceTotal
The following item(s) are anticipated to be ordered.
0001Task 1 Sanitary Survey - Kenai Lake Work Center Admin Site1JOB$0.00
0002Task 1 Sanitary Survey - Glacier Ranger District Office1JOB$0.00
0003Task 1 Sanitary Survey - Begich Boggs Visitor Center Well #21JOB$0.00
0004Task 1 Sanitary Survey - Tenderfoot Campground - Upper Well1JOB$0.00
0005Task 1 Sanitary Survey - Tenderfoot Campground - Lower Well1JOB$0.00
0006Task 1 Sanitary Survey - Tenderfoot Campground - DWS1JOB$0.00

Estimated Total: $0.00

Option Ordering Period 1: 05/01/2025 - 04/30/2026
CLIN # (Item number)DescriptionEstimated QuantityUnitUnit PriceTotal
The following item(s) are anticipated to be ordered.
1001Task 1 Sanitary Survey - Porcupine 1 - Southeast1JOB$0.00
1002Task 1 Sanitary Survey - Porcupine 2 - West1JOB$0.00
1003Task 1 Sanitary Survey - Porcupine 3 - Northeast1JOB$0.00
The following item(s) will be ordered as needed or as funding allows.
1004Task 1 Sanitary Survey - Spencer-Whistle Stop1JOB$0.00
Estimated Total:$0.00
Option Ordering Period 2: 05/01/2026 - 04/30/2027
CLIN # (Item number)DescriptionEstimated QuantityUnitUnit PriceTotal
The following item(s) are anticipated to be ordered.
2001Task 1 Sanitary Survey - Broadview Guard Station1JOB$0.00
2002Task 1 Sanitary Survey - Portage Work Center1JOB$0.00
2003Task 1 Sanitary Survey - Begich Boggs Visitor Center (BBVC)1JOB$0.00
The following item(s) will be ordered as needed or as funding allows.
2004Task 1 Sanitary Survey - KLTP Mobile Home Park1JOB$0.00
2005Task 1 Sanitary Survey - Schooner Bend Work Center1JOB$0.00
2006Task 1 Sanitary Survey - Hope Guard Station1JOB$0.00
Estimated Total:$0.00
Option Ordering Period 3: 05/01/2027 - 04/30/2028
CLIN # (Item number)DescriptionEstimated QuantityUnitUnit PriceTotal
The following item(s) are anticipated to be ordered.
3001Task 1 Sanitary Survey - Williwaw 1 East1JOB$0.00
3002Task 1 Sanitary Survey - Williwaw 2 Middle1JOB$0.00
3003Task 1 Sanitary Survey - Williwaw 3 West1JOB$0.00
3004Task 1 Sanitary Survey - Williwaw 41JOB$0.00
3005Task 1 Sanitary Survey - Quartz Creek1JOB$0.00
3006Task 1 Sanitary Survey - Cooper Creek 1 South1JOB$0.00
3007Task 1 Sanitary Survey - Cooper Creek 2 North1JOB$0.00
3008Task 1 Sanitary Survey - Russian River1JOB$0.00
The following item(s) will be ordered as needed or as funding allows.
3009Task 1 Sanitary Survey - Black Bear Campground1JOB$0.00
3010Task 1 Sanitary Survey - Trail River 1 Lakeside1JOB$0.00
3011Task 1 Sanitary Survey - Trail River 2 Riverview1JOB$0.00
3012Task 1 Sanitary Survey - Trail River 3 Sprucewoods1JOB$0.00
3013Task 1 Sanitary Survey - Trail River 5 River Terrace1JOB$0.00
3014Task 1 Sanitary Survey - Trail River 7 Lake Side Day Use1JOB$0.00
3015Task 1 Sanitary Survey - Trail River 8 Eagle Point1JOB$0.00
3016Task 1 Sanitary Survey - Trail River 10 Spruce Woods1JOB$0.00
3017Task 1 Sanitary Survey - Primrose 841JOB$0.00
3018Task 1 Sanitary Survey - Ptarmigan 1 South1JOB$0.00
3019Task 1 Sanitary Survey - Ptarmigan 2 North1JOB$0.00
3020Task 1 Sanitary Survey - Tern Lake 1 Lower1JOB$0.00
3021Task 1 Sanitary Survey - Bertha Creek Campground1JOB$0.00
3022Task 1 Sanitary Survey - Granite Creek 1 South Campground1JOB$0.00
3023Task 1 Sanitary Survey - Granite Creek 2 North Campground1JOB$0.00
3024Task 1 Sanitary Survey - Crescent Creek Campground1JOB$0.00
Estimated Total:$0.00
Estimated Grand Total:$0.00

Sheet1

BASE YEAR
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0002Category I Administrative Buildings
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year)
QTYUNITUNIT PRICETOTAL COST
0002AACategory I Administrative Buildings Rest Room Cleans2,620,889sq. ft$ 0.0408$ 106,932.25*55,026x47.63= 2,620,888.58 SF (11month period)55026.0041990342522,861,352.22
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.0520.00
Period of Performance: 11 months (Base Year)0520.00
QTYUNITUNIT PRICETOTAL COSTERROR:#VALUE!52ERROR:#VALUE!
0002ABCategory I Administrative Buildings Hard Floor Cleans6,586,752sq. ft$ 0.0231$ 152,153.97*94,515x47.63= 4,501,749.45 SF138289.986773042527,191,079.31
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.0520.00
Period of Performance: 11 months (Base Year)0520.00
QTYUNITUNIT PRICETOTAL COSTERROR:#VALUE!52ERROR:#VALUE!
0002ACCategory I Administrative Buildings Carpet Floor Cleans1,204,420sq. ft$ 0.0192$ 23,124.87*19,831x47.63= 944,550.53 SF25287.0098677304521,314,924.51
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.$ 282,211.100520.00
Period of Performance: 11 months (Base Year)0520.00
0520.00
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST520.00
0003Category II Child Development Facilities520.00
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.52
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0003AACategory II Child Development Facilities Hard Floor Cleans11,485,212sq. ft$ 0.0252$ 289,427.35*390,060x238.15weeks = 9,302,139 SFTOTAL: 11,485,212.42 SF
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.*7,639x285.78 weeks = 2,183,073 SF
Period of Performance: 11 months (Base Year)
QTYUNITUNIT PRICETOTAL COST
0003ABCategory II Child Development Facilities Carpet Floor Cleans685,729sq. ft$ 0.0194$ 13,303.14*1113x238.15 weeks = 265,060.95 SFTOTAL: 685,729.11
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.*1472x285.78 weeks = 420,668.16 SF
Period of Performance: 11 months (Base Year)$ 302,730.50
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0004Category III Physical Fitness Centers
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0004AACategory III Physical Fitness Centers Hard Floor Cleans3,010,146sq. ft$ 0.0344$ 103,549.02Bldg 3452(6W) 1,330,305.90 SF1W*Hockey 1,323x17.32 = 22,914.36 SF1,330,305.90
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.Bldg 3709 (7W) 1,416,325.68 SF6W*Hockey 1,323x30.31= 240,600.00 SF1,416,325.68
Period of Performance: 11 months (Base Year).22,914.36
QTYUNITUNIT PRICETOTAL COST240,600.00
0004ABCategory III Continuous Cleaning Physical Fitness Center Bldg 370911monthly$ 4,322.26$ 47,544.86Total Hours 1,657.05Provide locker room cleaning from 13:00-15:30 daily 1Male/1Female 2-1/2 hours each.3,010,145.94
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year).
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0005Special /Emergency/Bio-Hazard Cleans
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0005AASpecial Cleaning40,538per sq. ft$ 0.28$ 11,472.25
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Special Cleaning CLIN represents 20% of the total square footage for the contract.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0005ABEmergency Cleaning22,296per sq. ft$ 0.38$ 8,405.59
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Emergency Cleaning CLIN represents 11% of the total square footage for the contract.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0005ACBio-Hazard Cleaning10,134per sq. ft$ 1.13$ 11,471.69
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Special Cleaning CLIN represents 5% of the total square footage for the contract.
Period of Performance: 11 months (Base Year).
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0006CONTRACT MANPOWER REPORTING1EA$ 100.0000$ 100.0000
Contractor Manpower Reporting Costs: 1 May 2016 to 30 March 2017. The Contractor Manpower Reporting requirement is associated with the Office of the Assistant Secretary of the Army (Manpower and Reserve Affairs) requirement to obtain better visibility of the Contractor service workforce.
The Contractor is required to enter data into the Contractor Manpower Reporting Application (CMRA) system as outlined in local information titled Contractor Manpower Reporting located with the clauses incorporated into the contract. Reporting period will be the period of performance not to exceed 12 months ending 30 September of each Government fiscal year and must be reported by 31 October of each calendar year. Data must be accurate and complete and entered into CMRA during the data gathering period of every year, or part of a year, for which the contract is in force. NOTE: If the reporting of Manpower Equivalents is not separately priced, insert “NSP in the blank shown.
BASE YEAR TOTAL COST:$ 767,485.01