Attachment 3 RSL Roof Statement of Work.pdf
PDF 300 KB Posted
- Solicitation number
- 127EAX26Q0065
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the U.S. Department of Agriculture for the Redwood Sciences Laboratory Roof Replacement project located at Cal-Poly Tech Humboldt Campus in Arcata, California.
The primary scope requires removal and replacement of approximately 10,300 square feet of failing Built-Up Roof (BUR) system, including complete removal of existing roof materials, insulation, flashings, and trims down to the original decking with legal off-site disposal. The contractor must examine the existing deck substrate and repair or replace any deteriorated sections. Work includes installation of a new BUR system from a manufacturer with minimum five years of successful production experience, with membrane, flashing, and adhesives from a single standard manufacturer. Additional tasks include removal and replacement of roof deck joint sealants with high-performance materials, new flashing installation for all rooftop HVAC curbing, conduit, pipe supports, vents, roof hatch, ventilation fans, and penetrations with pre-molded pipe flashings and stainless steel clamps. The contractor must also provide new walkway protection around roof-mounted equipment, remove and reset all roof drains below membrane surface, and ensure no water ponding on the roof with proper drainage away from building foundations.
The Government will furnish temporary water (with contractor providing hoses), temporary electrical service (with contractor providing wiring and lighting), and will pay for these utilities. The contractor is responsible for providing temporary ladders, ramps, scaffolds, hoists, chutes, and portable toilets. The project requires a Safety and Health Program Manager to implement Cal-OSHA regulations and conduct frequent inspections. All contractor and subcontractor personnel must be U.S. Citizens and subject to background checks for unescorted building access. Personnel must access the roof from the building exterior with material loading/offloading also from exterior only. The total period of performance is 155 days, including 30-day pre-proposal site visit window, 14-day bond and insurance submittal requirement, 30-day material procurement, and 30-day onsite main roof construction period, with final cleanup beginning 5 days prior to completion. Additional time allowance may be necessary due to rain occurrence from September through June at this location.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements ........................................................................................................................... Error! Bookmark not defined.
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Storage of Equipment and Materials
6.0 Procedures
7.0 Contractor’s Key Personnel
8.0 Equipment and Safety
9.0 Access
10.0 Quality Assurance
Attachment
Project Redwood Sciences Laboratory Roof Replacement
General Information
1.0 Scope of Work
The existing Built-Up Roof (BUR) has deteriorated causing the roof to leak into the interior of the building and needs to be replaced. The work consists of furnishing all labor, supervision, equipment, transportation, and materials for the installation of the new BUR roof system. Prior to the installation of the new roof systems, inspect the existing roof substrate for signs of deterioration or damage.
Notify the COR if repairs are needed before proceeding with the repairs and the installation of the new BUR roof system.
The Contractor should carefully review all sections of the specifications to completely understand the work and all constraints including schedule, and material requirements.
The Contractor is encouraged to proceed in an orderly and expeditious manner according to a construction schedule developed by the Contractor and mutually agreed upon with the Contracting Officer prior to the commencement of the work. All work is to be done in strict accordance with all building codes and regulations, plans and specifications, and subject to the terms and conditions of the contract.
2.0 Redwood Sciences Laboratory Building
The Redwood Sciences Laboratory (RSL) Building #27012809 Is located on the Cal-Poly Tech Humboldt Campus at 1700 Bayview St., Arcata, California, 95521. Some of the Six Rivers National Forest Supervisors’ Office Staff (SO) have moved into the RSL to share the space with the Pacific Southwest Research Station staff. The existing BU R5dR roof is failing and needs to be replaced.
3.0 Tasks
Existing Roof System Removal Remove and replace approximately 10,300 square feet of the existing built-up roofing (BUR) system on the Redwood Sciences Laboratory. The existing roof system, insulation, flashings, and related trims shall be completely removed to the original decking and legally disposed of off the property. The existing deck substrate should be examined, and any deteriorated sections of the deck shall be repaired or replaced. The removal of the existing roof system shall be coordinated with the installation of the new roof to prevent exposure to weather conditions and potential water infiltration into the building. The contractor shall identify all requirements for safety devices, dumpster location, chutes or other methods of roofing material removal, protection from exposure to the weather, protection of property and personnel, building access routes and circulation patterns, contractors use of the premises, parking, security procedures, equipment and materials storage, waste disposal, etc.
Caulking & Joint Sealants All defective roof deck joint sealants shall be removed and replaced with high performance sealant as part of the roof system. The design shall include cleaning, priming, and installation of new sealants with new backer rods and bond breakers.
New Roofing System Install a new BUR system in accordance with the requirements of the roofing manufacturer. The manufacturer of the roofing system shall have no less than five (5) years of successful experience in producing the materials required for this project. Membrane, flashing, and adhesives shall be the single product of a standard manufacturer.
Flashing All rooftop HVAC curbing, conduit, pipe supports, pipe vents, roof hatch, ventilation fans, and other roof penetrations must have new flashing installed as part of this project. All pipe flashings are to be pre-molded and provided with stainless steel pipe clamps at each penetration.
Walkways Provide new walkway protection from access points to and around all roof mounted HVAC units and/or other similar equipment requiring periodic servicing and any other trafficking areas.
Roof Drains All drains shall be removed and reset or repositioned so that the drain is below the roof membrane surface. Provide for the interior cleaning, repair, replacement and additional drains as required and ensure that drainage water will be carried away from the building foundations, footings, lanes, sidewalks and driveways. Ensure that there is no ponding of water on the roof and that water flow is directed to the drains.
4.0 Government Furnished
A. Temporary Water:
1. Government will provide access to water required for construction. The Government will pay for the cost of water.
2. Do not disrupt the existing water service to the building.
3. Contractor shall provide hoses for conveyance.
B. Temporary Electrical
1. Government will provide for temporary electrical service. The Government will pay for provided power.
2. Contractor shall provide all necessary wiring, extensions, connections and temporary lighting.
C. Temporary Ladders, Chutes, Scaffolds, Hoists and Cranes:
1. Contractor shall furnish and maintain temporary ramps, scaffolds, hoists, or chutes required for proper execution of work.
D. Toilet Facilities
1. Portable toilets shall be the responsibility of the contractor.
5.0 Storage of Equipment and Materials
A laydown area will be determined for contractor equipment and materials storage.
1. Proper storage of equipment and materials is the sole responsibility of the contractor.
2. Store materials on site. Cover and protect materials subject to damage by weather, including during transit.
All materials shall be available for inspection.
3. Store flammable materials and volatile liquids in sealed containers located at a minimum of 20 feet from existing buildings.
4. Liquid products shall be in sealed original containers
5. Keep all labels intact and legible, clearly showing the product, manufacturer, and other pertinent information.
6.0 Procedures
A. Owner will occupy the premises during the entire period of construction. Cooperate with owner’s representee in all construction operations to minimize conflict and facilitate owner’s usage.
7.0 Contractor’s Key Personnel
The Contractor shall demonstrate the ability to provide qualified and experienced personnel for the completion of this task. Key project personnel shall have successfully participated in the completion of similar projects. All contractors and subcontractor personnel working on this task order shall be U.S. Citizens. The Contractor shall identify the personnel in the regardless of the type of task and provide contact information for each. NOTE: Contractor personnel shall subject to background checks through the Person-Model system for unescorted access to the building.
8.0 Equipment and Safety
Quality:
Hand tools, power tools, equipment, machinery, materials, and personal protective apparatus shall be of manufacture listed by U.S. or internationally recognized testing laboratory for specific application for which they are to be used. They shall be quality products recognized for professional construction use, applications, and work practices.
Scaffolding:
There will be a standard tubular frame and clamp system manufactured and tested according to international standards.
The Scaffold system shall include the scaffold manufacturers integrated access stairway sections, handrails, toe boards and walking platforms.
Safe Clearance Procedure:
Prior to initial use, and periodically thereafter at times of continued use, provide inspections of construction tools, equipment, and machinery. Do not permit continued use of tools, equipment, and machinery that are not in good condition.
Fall Protection:
On unprotected sides of the building edge provide workers with warning lines, guardrail, safety net or personal fall arrest systems or a combination of safety monitoring systems.
Hot Work:
Includes all work that results in open flames such as welding, cutting, brazing, and burning.
The use of cranes, forklifts, hoists, or generators powered by petroleum fuel when used on or near the building.
The Contractor shall always provide effective fire protection and prevention during such operations.
9.0 Access
Access to the roof:
1. Contractor personnel shall access from the EXTERIOR of the building.
2. Material loading/off-loading shall be from the EXTERIOR of the building.
3. Limit personnel movement through the interior.
10.0 Quality Assurance
Safety and Health Program Manager:
1. Appoint a manager whose duties shall include effective implementation, coordination, and enforcement of Cal-OSHA Regulations. The manager shall be qualified to anticipate, identify, evaluate, and implement corrective action in relation to potential safety and health hazards and dangerous exposures for accident prevention.
2. Provide for frequent safety, health, and housekeeping inspections conducted by the Safety and Health Program Manager, temporary structures, fabrication shops, material, machinery, and equipment.
PERIOD OF PERFORMANCE:
A. Solicitation:
1. Pre‐proposal Site Visit 30 days prior to Award
2. Award Day Zero
B. Pre‐Construction Submittals:
1. Bond & Insurance Submittals 14 days after award
2. Contractor Officer Review 6 days
3. Pre‐Construction Submittals 30 days
4. Contracting Officer Submittal Review 10 days
5. Material Procurement 30 days
C. Construction:
1. Main Roof 30 days onsite
2. Final Clean up Begins 5 days prior to completion
D. Total Period of Performance 155 days
Note that rain can occur at this location from September through June. So, an additional allowance of time may be necessary depending upon the start date.
Attachment If applicable, include an Attachment stating Evaluation Factors and significant Subfactors representing the key areas of importance and emphasis to be considered in the source selection decision.
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Redwood Sciences Laboratory Building |
| 3.0 Tasks |
| Existing Roof System Removal |
| Caulking & Joint Sealants |
| 4.0 Government Furnished |
| 5.0 Storage of Equipment and Materials |
| 6.0 Procedures |
| 7.0 Contractor’s Key Personnel |
| 8.0 Equipment and Safety |
| 9.0 Access |
| Access to the roof: |
| 10.0 Quality Assurance |
| PERIOD OF PERFORMANCE: |
| A. Solicitation: |
| 1. Pre‐proposal Site Visit 30 days prior to Award |
| 2. Award Day Zero |
| B. Pre‐Construction Submittals: |
| 1. Bond & Insurance Submittals 14 days after award |
| 2. Contractor Officer Review 6 days |
| 3. Pre‐Construction Submittals 30 days |
| 4. Contracting Officer Submittal Review 10 days |
| 5. Material Procurement 30 days |
| C. Construction: |
| 1. Main Roof 30 days onsite |
| 2. Final Clean up Begins 5 days prior to completion |
| D. Total Period of Performance 155 days |
| Note that rain can occur at this location from September through June. So, an additional allowance of time may be necessary depending upon the start date. |
| Attachment |