This is a Statement of Work (SOW) for the fabrication and delivery of two boat landing platforms to the US Department of Transportation Maritime Administration at Suisun Bay Reserve Fleet in Benicia, California.
The contractor is required to fabricate two boat landing platforms according to government-provided fabrication drawings. The platforms will be suspended above water alongside ships at Suisun Bay Reserve Fleet and used to land accommodation ladders and dock water taxis, work boats, or patrol boats for personnel debarkation and embarkation. The platforms will be hung from existing fittings on the main deck using wire rope, with SBRF personnel responsible for the installation. The contractor must deliver the completed platforms to 2595 Lake Herman Road, Benicia, CA 94510, and the government intends to inspect the platforms at the contractor's facility prior to shipment. The SOW incorporates sustainable acquisition requirements consistent with Federal Acquisition Regulations Part 23, requiring the contractor to provide or use energy-efficient products (ENERGY STAR® or FEMP-designated), water-efficient products, biobased products, environmentally preferable products, non-ozone depleting products, or products made with recovered materials, meeting minimum EPA or USDA-designated content standards. These sustainable acquisition requirements apply to products delivered to the government, acquired for use at federally-controlled facilities, furnished for government use, or incorporated into the design or construction of a building or work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 3 - Landing Platform Statement of Work
Statement of Work Fabricate Boat Landing Platforms
Core Services
The core services for this project are to fabricate two (2) boat landing platforms that can be suspended above the water alongside a ship at Suisun Bay Reserve Fleet. The platforms will be used to land a ship’s accommodation ladder upon its deck, and to dock a water taxi, work boat or patrol boat alongside to debark and embark personnel.
The platforms will be hung from existing fittings on the main deck of a ship with wire rope. The Contractor will not be responsible for hanging the platforms on the ships – this will be accomplished by SBRF personnel.
The government intends to inspect the landing platforms at the contractor's facility prior to shipping to the address listed below.
00001 Fabrication
Fabricate two (2) boat landing platforms according to the fabrication drawings provided.
Government Furnished Material: Fabrication Drawings
00002 Delivery
Deliver the completed platforms to:
US Department of Transportation Maritime Administration Suisun Bay Reserve Fleet 2595 Lake Herman Road Benicia, CA 94510
To the maximum extent possible and consistent with the Federal Acquisition Regulations Part 23, the Government requires during the performance of the work under this Statement of Work (SOW) the Contractor to provide or use products that are: energy efficient (ENERGY STAR® or Federal Energy Management Program (FEMA)-designated); water-efficient; biobased; environmentally preferable (e.g., EPEAT-registered, or non-toxic or less toxic alternatives); non-ozone depleting; or made with recovered materials. Unless otherwise identified in this SOW, each recovered materials or biobased product provided and delivered must meet, but may exceed, the minimum recovered materials or biobased content of an EPA- or USDA-designated product.
The sustainable acquisition requirements specified herein apply only to products that are required to be: (1) delivered to the Government during contract performance; (2) acquired by the contractor for use in performing services (including construction) at a Federally-controlled facility; (3) furnished by the contractor for use by the Government; or (4) specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance.