Attachment_3_Drawings_and_Document_BKR_SPS2_Maint.pdf
PDF 60 KB Posted
- Attached to
- 138 KV Oil Breaker Replacements Project
- Solicitation number
- RFP-2024-010
- Issued by
- Alachua County, Graceville City, Florida
About this file
This document is a Breaker Maintenance checklist form for an SPS2 type circuit breaker, associated with Gainesville Regional Utilities' (GRU) 138 KV Oil Breaker Replacements Project in Florida. The form provides a comprehensive maintenance inspection template for electrical circuit breakers, detailing multiple critical testing procedures including timing tests, travel tests, ductor measurements, megger testing, power factor testing, SF6 gas analysis, pressure switch settings verification, alarm checks, mechanical inspections, and general maintenance tasks.
The maintenance checklist includes specific technical parameters such as first trip timing (< 26ms), closing time (< 63ms), stroke measurement (110 mm), electrical resistance measurements (< 130 micro ohms), insulation resistance testing, SF6 gas purity requirements (> 97%), moisture levels (< 300 ppm), and pressure switch settings (operating pressure at 87 psi). The form allows for detailed documentation of test results across three separate poles, with space for recording serial number, breaker type, ambient temperature, and technician comments, supporting GRU's systematic approach to maintaining and replacing aging electrical infrastructure.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Breaker Maintenance
Breaker Ser # Date
Type SPS2 kv Amps
Counter Found Left Amb. Temp
Pole 1 Pole 2 Pole 3 Timing Test
(1) First Trip (< 26ms)
(2) Closing Time (< 63ms)
Travel Test
(1) Stroke (110 mm)
(2) Wipe
Ductor (< 130 Micro ohms)
Megger - 1000V Closed
(> 1000 Mega ohms) Open 1 3 5
(> 2000 Mega ohms) 2 4 6 1 to 2 3 to 4 5 to 6
Power Factor Testing
Test SF6 Gas
(1) Purity (> 97%)
(2) So2 (< 40)
(3) Moisture (< 300 ppm)
Check Pressure switch settings
(1) Operating pressure (87 psi)
(2) Low pressure Alarm (75 psi)
(3) Low Pressure Cut-out (72 psi)
Test Alarms
Check Mech. for loose or warn parts
Lube Mech.
Spring Charging time (< 15 sec.)
Check Heaters
Clean Cabinet
Performed by
Comments
File details come from the government source that posted it. Updated .