Attachment 3 Clauses and Provisions (AHALEY).doc

DOC document 482 KB Posted

Attached to
DOCKSIDE REPAIRS USCGC ALEX HALEY (WMEC 39)
Solicitation number
70Z08521RP4503200
Issued by

About this file

This solicitation requests proposals for dockside repairs of the USCGC Alex Haley (WMEC 39). Products and services required include items listed in Attachment 1 such as anchor chain inspection and repair, single point davit inspection and repair, sewage pump room preservation, and raw water piping repair. Proposals are due by 2:00 pm PST on November 27, 2020 and award is expected on or about December 15, 2020, subject to availability of funds. Pricing will be on a firm fixed-price basis. The solicitation is set aside for total small businesses with a NAICS code of 336611 and size standard of 1250 employees. The period of performance includes Phase 1 from February 1-March 2, 2021 and Phase 2 from May 17-July 15, 2021. The solicitation incorporates FAR provisions by reference and includes 17 attachments related to requirements, pricing, and evaluation criteria.

View the file

Other files

File Type Posted
Page 2 A0003.docx DOCX document
SF 30 - A0003.pdf PDF
ALEX HALEY (WMEC 282) DS RTO 21R2 (120720).pdf PDF
ALEX HALEY (WMEC 282) DS RTO 21R1.pdf PDF
SF 30 - A0002.pdf PDF
Page 2 - A0002.docx DOCX document
SF 30 - A0001.pdf PDF
PAGE 2 - A0001.docx DOCX document
Attachment 2 Schedule of Items-Prices (AHALEY).docx DOCX document
Attachment 4 Request for Clarifications (AHALEY).doc DOC document
Attachment 6 Notice to Protest.docx DOCX document
Attachment 7 Non-Disclosure Agreement (AHALEY).pdf PDF
Attachment 5 Government Property Report (AHALEY).doc DOC document
Attachment 1 ALEX HALEY (WMEC 282) DS RTO 21R0.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL

SOLICITATION NO. 70Z08521RP4503200

DOCKSIDE REPAIRS OF CGC ALEX HALEY (WMEC 39)

ATTACHMENT 3 – Contract Clauses & Provisions Continuation of Synopsis/Solicitation

Addendum to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS (OCT 2018)

(1) TIME OF PERFORMANCE: USCGC ALEX HALEY will be available for performance of the work under this contract during the following periods:

Phase 1: 01 February 2021 through 02 March 2021 Phase 2: 17 May 2021through 15 July 2021 (2)

PLACE OF PERFORMANCE

All work under this contract will be performed onboard CGC ALEX HALEY at their home moorage in Coast Guard Kodiak Base, Kodiak, AK.

(3)

FAR 52.204-1 APPROVAL OF CONTRACT (DEC 1989)

This contract is subject to the written approval of the Contracting Officer for SFLC-C&P2-LREPL and shall not be binding until so approved.

(4)

FAR 52.252-2: CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

www.acquisition.gov/far/ http://www.dhs.gov/publication/hsar The following is the summary of applicable FAR & HSAR clauses incorporated by reference:

Clause No.
Clause Title
Date
FAR 52.203-12
Limitation on Payments to Influence Certain Federal Transaction
JUN 2020
FAR 52.203-17
Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
JUN 2020
FAR 52.204-4
Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
FAR 52.212-4
Contract Terms and Conditions – Commercial Items
OCT 2018
FAR 52.215-21
Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data- Modification
JUN 2020
FAR 52.223-3
Hazardous Material Identification and Material Safety Data
JAN 1997
FAR 52.228-5
Insurance – Work on a Government Installation
JAN 1997
FAR 52.229-3
Federal, State, and Local Taxes
FEB 2013
FAR 52.232-18
Availability of Funds
APR 1984
FAR 52.242-2
Production Progress Reports
APR 1991
FAR 52.242-15
Stop-Work Order
AUG 1989
FAR 52.242-17
Government Delay in Work
APR 1984
FAR 52.245-1
Government Property Alternate 1 (APR 2012)
JAN 2017
FAR 52.245-9
Use and Charges
APR 2012
FAR 52-246-2
Inspection of Supplies – Fixed Price
AUG 1996
FAR 52.246-4
Inspection of Services – Fixed-Price
AUG 1996
FAR 52.246-16
Responsibility for Supplies
APR 1984
FAR 52.247-55
F.O.B. Point for Delivery of Government Furnished Property
JUN 2003
HSAR 3052.211-70
Index of Specification
DEC 2003
HSAR 3052.222-70
Strikes or Picketing Affecting Timely Completion of the Contract Work
DEC 2003
HSAR 3052.222-71
Strikes or Picketing Affecting Access to a DHS facility
DEC 2003
HSAR 3052.222-90
Local Hire
JUN 2006
HSAR 3052.223-90
Accident and Fire Reporting
DEC 2003

(5)

HSAR3052.212-70 CONTRACT TERMS AND CONDITIONS APPLICABLE TO

DHS ACQUISITION OF COMMERCIAL ITEMS (SEP 2012)

The Contractor agrees to comply with any provision or clause that is incorporated herein by reference to implement agency policy applicable to acquisition of commercial items or components. The provision or clause in effect based on the applicable regulation cited on the date the solicitation is issued applies unless otherwise stated herein. The following provisions and clauses are incorporated by reference:

(a) Provisions.

3052.209-72 Organizational Conflicts of Interest.

3052.216-70 Evaluation of Offers Subject to An Economic Price Adjustment Clause.

FORMCHECKBOX

3052.219-72 Evaluation of Prime Contractor Participation in the DHS Mentor Protégé Program.

(b) Clauses.

3052.203-70 Instructions for Contractor Disclosure of Violations.

3052.204-70 Security Requirements for Unclassified Information Technology Resources.

3052.204-71 Contractor Employee Access.

FORMCHECKBOX

Alternate I

3052.205-70 Advertisement, Publicizing Awards, and Releases.

3052.209-73 Limitation on Future Contracting.

3052.215-70 Key Personnel or Facilities. Fill-in: [Contractor’s facility and Technical Representatives will be inputted at contractor award]

3052.216-71 Determination of Award Fee.

3052.216-72 Performance Evaluation Plan.

3052.216-73 Distribution of Award Fee.

3052.217-91 Performance. (USCG)

3052.217-92 Inspection and Manner of Doing Work. (USCG)

3052.217-93 Subcontracts. (USCG)

FORMCHECKBOX

3052.217-94 Lay Days. (USCG)

3052.217-95 Liability and Insurance. (USCG)

3052.217-96 Title. (USCG)

3052.217-97 Discharge of Liens. (USCG)

3052.217-98 Delays. (USCG)

3052.217-99 Department of Labor Safety and Health Regulations for Ship Repair. (USCG)

3052.217-100 Guarantee. (USCG) (60 DAYS)

FORMCHECKBOX

3052.219-70 Small Business Subcontracting Plan Reporting.

FORMCHECKBOX

3052.219-71 DHS Mentor Protégé Program.

FORMCHECKBOX

3052.228-70 Insurance.

3052.228-90 Notification of Miller Act Payment Bond Protection. (USCG)

3052.228-91 Loss of or Damage to Leased Aircraft. (USCG)

3052.228-92 Fair Market Value of Aircraft. (USCG)

3052.228-93 Risk and Indemnities. (USCG)

3052.236-70 Special Provisions for Work at Operating Airports.

3052.242-72 Contracting Officer’s Technical Representative.

3052.247-70 F.o.B. Origin Information.

Alternate I

Alternate II

3052.247-71 F.o.B. Origin Only.

3052.247-72 F.o.B. Destination Only.

(End of clause) (6) FAR 52.217-7 OPTION FOR INCREASED QUANTITY – SEPARATELY PRICED LINE ITEM (MAR 1989) The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within twenty-four hours via email. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

End of Clause (7)

OPTIONAL ITEMS:

Optional items listed under CLIN 0002 of the SCHEDULE OF ITEMS – PRICES may be awarded if inspection reports reveal the necessity for activation, or if funds are made available, at the price proposed in the Contractor’s proposal and without any other consideration whatsoever. However, after midnight on 23 February 2021, the Contractor shall have the right to refuse to accept the award of such Optional Item.

Such award refusals shall bar neither the Government nor the Contractor from subsequently negotiating with each other for performance of the work embodied in the refused Optional Item/s.

Optional items shall be awarded by written notice to the Contractor through issuance of a contract modification (SF-30). Transmission of the SF-30 notice of exercise to the contractor via e-mail is authorized; for purposes of determining the exact time of e-mail transmission, the time, date, and year of transmission automatically applied to the e-mail and/or the e-mail transmission record of transmission at the contracting office shall govern. Evaluation of the Optional items will not obligate the Government.

(8) HSAR 3052.223-70 REMOVAL OR DISPOSAL OF HAZARDOUS SUBSTANCES – APPLICABLE LICENSES AND PERMITS (JUN 2006)

The Contractor shall have all licenses and permits required by Federal, state, and local laws to perform hazardous substance(s) removal or disposal services. If the Contractor does not currently possess these documents, it shall obtain all requisite licenses and permits within 30 days after date of award. The Contractor shall provide evidence of said documents to the Contracting Officer or designated Government representative prior to commencement of work under the contract.

(End of clause) (9)

HAZARDOUS WASTE

Contractors performing ship repair work required to comply with FAR 52.223-3, Hazardous Material Identification and Material Safety Data (JAN 1997) Alt I, the U.S. Coast Guard shipboard hazardous waste policy, as prescribed in COMDINST M16478.1B, and MLCA standard specifications. Disposal of all hazardous wastes shall be performed by the Contractor and the Contractor shall meet all federal and state requirements. The Contractor is also required to submit an acceptable hazardous waste management plan to the Port Engineer/Contracting Officer’s Representative at the arrival conference. The plan will be reviewed by the facility hazardous waste manager. An acceptable plan must address, at a minimum, the following requirements:

(a) EPA and local authority hazardous waste generator ID numbers or registration of the Contractors, his transporters, and disposal facilities (TSDFs);

(b) An inventory of all hazardous chemicals, compounds and other agents brought aboard the facility accompanied by their respective Material Safety Data Sheets;

(c) A list of all anticipated hazardous wastes to be generated and a federal/state/local regulation cross reference list for those wastes;

(d) Waste collection and containment procedures;

(e) A hazardous material spill and cleanup plan including tools and materials that will be on hand and readily available to facility containment and cleanup;

(f) Training certification for the Contractor's hazardous waste manager.

The Contractor shall note the local environmental regulations in the city where work will be performed, are more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with, the local and state regulations.

All waste generated under the performance of this contract shall be disposed under the applicable ISC Base Kodiak, AK EPA hazardous waste generator ID number. The Contractor shall notify the Contracting Officer's Representative (COR) 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays). All hazardous waste manifests shall be reviewed and signed by ISC Base Kodiak, Kodiak, AK hazardous waste personnel. Contractor must contact the designated Contracting Officer’s Representative (COR) for any environmental issues.

(10)

VOLATILE ORGANIC COMPOUNDS (VOC) REGULATIONS

(a) Contractors are required to comply with federal, state and local VOC compliance laws and regulations. Among other requirements, certain Contractors may also be required to operate pursuant to a Title V permit. The need for such a permit will depend on the provisions of the applicable state’s “State Implementation Plan” (SIP) and the type/quantity of the Contractor’s regulated emissions, including VOCs. Certain SIPs may also mandate certain Contractors to operate under the terms of a compliance plan intended to reduce VOC emissions.

(b) Contractors, therefore, must submit the following to the designated Port Engineer not later than two weeks after contract award:

(1) Copies of any federal, state or local permits required and applicable to the use or application of VOCs at Contractor’s facility or offsite work places;

(2) Copies of any compliance plans required and applicable to the use or application of VOCs at Contractor’s facility or offsite work places.

(c) If no federal, state or local permits or compliance plans are required and applicable to the use or application of VOCs at Contractor’s facility or offsite workplaces, then Contractor shall submit to the designated Port Engineer a letter, notarized under oath, that such documents are not required.

(d) Contractors will submit the following to the designated Port Engineer not later than two weeks after contract award: Data Sheets (MSDS) documents, certificates, specifications or any other manufacturing data verifying the VOC ratings of paints to be applied to the Cutter in accordance with MLCA Standard Spec 63000N, Section 5.3.1.

(11)

ACCESS TO VESSEL

(a) A reasonable number of officers, employees, and associates of the Government, or other Prime Contractors with the Government, and their subcontractors, shall, as authorized by the Contracting Officer, have, at all reasonable times, admission to the plant, and access to vessel(s) to perform and fulfill their respective obligations to the Government on a noninterference basis.

The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Contracting Officer, to be given admission to the Contractor's facilities and access to the vessel(s) and to office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of their respective responsibilities and reasonable to their performance. All such above personnel shall be required to comply with all Contractor rules and regulations governing personnel at its shipyard, including those relative to safety and security.

The Contractor further agrees, as authorized by the Contracting Officer, to afford to a reasonable number of officers, employees, and associates of bidders on other contemplated work, the same privileges of admission to the Contractor's plant and access to the vessel(s) on a noninterference basis subject to all Contractor rules and regulations governing personnel in its shipyard, including those relative to safety and security.

(12)

INDEMNIFICATION FOR ACCESS TO VESSELS

Notwithstanding any provision in the "Access to Vessels" clause, or any other clause of the contract, the Contractor agrees to allow officers, employees, and associates of the Government, or other Prime Contractors with the Government and their subcontractors, and officers, employees, and associates of quoters on other contemplated work, admission to the Contractor's facilities and access to the vessel without any further request for indemnification from any party, which has not been previously included in the contract price.

(13)

INSPECTIONS

Except as specified elsewhere, the U.S. Coast Guard shall rely on the Contractor to accomplish all inspection and testing needed to ensure that the work conforms to contract quality requirements.

Records of all inspection work by the Contractor shall be kept complete and available to the Government during the term of this contract and for such longer period as may be specified elsewhere in this contract.

The name and telephone number of the U.S. Coast Guard Inspector will be provided after the award of a contract resulting from this solicitation.

(14)

GROWTH WORK

(a) The Contractor shall not perform growth work without the Contracting Officer's authorization. Growth work is work within the scope of the contract, which has not been previously priced as a pre-priced CLIN. The Contracting Officer reserves the right to contract for growth work on the basis of a negotiated, firm, fixed price, when it is in the best interest of the Government. Scope of services shall include ship repair and associated support work, and may include work that is not currently listed as Definite and Optional Items.

(b) The Contractor shall furnish a price breakdown directly to the Contracting Officer, itemized as required by the Contracting Officer, of any proposal submitted for a contract modification. Unless otherwise directed, the breakdown shall be submitted on an SFLC 002 proposal form provided at the arrival conference permitting an analysis of all materials, labor, equipment, subcontract, overhead costs, and profit covering all work involved in the change/modification whether such work was deleted, added or changed. Any amount claimed for subcontracts shall be supported by a separate, similar price breakdown. If the proposal includes a request for a time extension, justification shall be furnished with the proposal.

(c) This clause is to be used in conjunction with the clause COMPOSITE LABOR RATE incorporated into this solicitation. The Contractor is required to have and/or furnish all tools and equipment incidental to each bench trade. Supplies such as wiping rags, hacksaw blades, sandpaper, welding wire, helium, etc., are also to be furnished by the Contractor. Other materials are to be charged at regular rates and prices currently in effect and as agreed to by the Contracting Officer. Material shall be best commercial quality available except where a precise specification is indicated in which case the specification shall apply, e.g., MILSPEC, FEDERAL SPEC.

(15)

COMPOSITE LABOR RATE:

The composite labor rate offered shall be the sole labor hour rate used to price the Prime Contractor's direct labor hours for contract changes, i.e. growth work. The Contractor shall not receive any compensation in addition to this rate for the Prime Contractor's direct labor associated with such changes under this contract.

(a) The composite labor hour rate shall represent total compensation for the following:

(1) direct labor wages and salaries;

(2) all employee benefits including, but not limited to, paid leave, supplemental pay, insurance, retirement, savings, and legally required benefits;

(3) other direct costs associated with transit time, delay, disruption, expendable supplies, and equipment;

(4) all indirect costs such as overhead and general and administrative expense;

(5) any port or association fees, rents, or other levies;

(6) profit (fee); and

(7) all direct and indirect costs and profit associated with the following support functions:

Supervision Quality Assurance

Planning Engineering

Surveyors Worker Transit Time

Material Handling Testing

Cleaners Guards

Estimating Contract Administration

Transportation Drivers

Fire Watches

The composite labor hour rate will be applied to production labor hours only. Production labor hours include only those hours necessary and reasonable to perform direct production functions and do not include the hours expended on the support functions listed above. This exclusion of support function hours applies whether such support functions are normally charged directly or indirectly by the Contractor's accounting system. These support functions are to be priced into the composite labor rate quoted and shall not be separately compensated.

(c) The Quantity of Composite Labor hours indicated in the Schedule of Items – Prices, is only an estimate and is an Optional Item pursuant to this solicitation. The Estimated Quantity represents the Government’s best estimate of the total number of additional hours that may be required throughout the contract. The Government may elect to exceed this value at the prices stated in the schedule and its discretion during performance of the contract. The inclusion of this item does not obligate the Government to exercise the item nor entitle the Contractor to compensation if not exercised.

(16)

DISCOVERIES AND CHANGES TO CONTRACT:

Condition Found Report, Change Orders will be transmitted electronically by using email. The bullets below display the process of how these documents are to be followed for the duration of the contract performance period:

(a) Condition Found Report (CFR) - All readings and inspections are to be taken within 24 hours after the machinery or system is opened. All reports of reading and inspections required by the specifications shall be submitted to the COR in writing using a "Condition Found Report (CFR)" form, within 24 hours after the readings and/or inspections are made.

Promptness in taking and reporting readings is particularly important for underbody work items such as shaft bearing or rudder bearing clearances. Often during the progress of a work item, conditions are discovered by the contractor which are considered abnormal for reasons of safety, expected reliability, health, or habitability. These conditions must be brought to the attention of the Coast Guard using a CFR. Details provided by the Contractor in a CFR are important because the CFR may result in a contract change. To speed the contract change progress, the Contractor should include in his/her CFR the following details as a minimum:

(i) A sequential number.

(ii) The contract item which the "CFR" relates to.

(iii) A clear statement, definition, and description of the condition found, including but not limited to frame numbers, part numbers, materials and dimensions as appropriate.

(iv) A proposed or recommended repair to correct the defective condition.

(v) Indicate whether the report requires Cost Guard action, or if it is provided "for info" only. If action is required, indicate the response time required by the Coast Guard and whether or not a contract extension would be needed if the additional work is authorized.

(vi) A space on the form for the Coast Guard to make comments.

(vii) All CFR's willl be dated, submitted, and signed by a representative of the Contractor. Contracting Officer’s Representative (COR) will respond to the Contractor’s within 24 hours of receiving a Condition Found Report. A copy of ALL condition found reports shall be retained in the Cutter’s file.

(b) Change Request Process will occur in the following order:

1. Condition Found Report-Generated by the contractor and provided to COR .

2. Condition Report Reply-Generated by the COR and provided to Contractor

3. Change Request- CR and IGE are generated by the COR and entered in the Contract Workbook. COR will assign the Change request number.

4. COR provides copy of Change Request to the Contractor

5. Contractor’s Proposal- Provided to the KO for the identified tasking on CR

6. Negotiations- If needed, take place to establish pricing

7. Approved Change Request- Forwarded to Contractor and COR by the KO Change Request must be submitted by the COR to the contractor within 24 hours after responding to the CFR. Contractor must submit proposal to the Contracting Officer within 72 hours receipt of the Change Request.

A modification will be issued to incorporate and implement all changes made by change orders.

(17)

CONTRACT DEFICIENCY REPORT

The Contracting Officer or Contracting Officer’s Representative (COR) may issue a Contract Deficiency Report (CDR), SFLC Form 005. The Contractor shall respond in writing within 24 hours of receipt, unless otherwise approved by the Contracting Officer, to the COR. The COR will comment on the Contractor's response and will forward the Deficiency Report and comments to the Contracting Officer, with a copy to the Contractor and Availability Program Manager. The Contracting Officer will render a final determination and provide it to the Contractor and COR in writing.

(18) MAINTAINING, REPORTING, AND DISPOSING OF GOVERNMENT PROPERTY IN THE PERFORMANCE OF A SHIP REPAIR CONTRACT

1.

The Government Property Clause incorporated by reference delineates the Contractor's overall responsibility when taking possession of government property in performance of a contract. In performance of this contract the Contractor will be required to properly identify, track and control property within its possession. This includes, a) property furnished by the government (GFP) to the Contractor in conjunction with specific CLIN Items. These items and their values are listed in the specification, b) property that is pre-existing in a location that during the course of performance will be replaced or renewed.

2.

The items listed in the specification, as government furnished property will be provided in the quantities designated. Government furnished property may be provided in person by an official Coast Guard employee, shipment via commercial carrier, etc. The Contractor shall sign for all government furnished property using either a DD Form 1149, entitled, “Requisition and Invoice/Shipping Document” or a DD Form 1348, entitled, “Issue Release/Receipt Document”. A copy of the DD 1149 or DD 1348 must be sent within 48 hours of receipt of property, to the designated Government Property Administrator. The name of the individual assigned as Property Administrator will be furnished to the Contractor at time of award. The Contractor shall not take receipt of property that is not listed in the specification, has not been previously identified as becoming part of the contract (via contract modification) or which otherwise cannot be identified. Such irregularities shall be immediately reported to the Property Administrator.

3.

The Contractor shall complete the report provided herein, entitled, “Government Property Report”. This report is intended as a living document whereby relevant fields shall be filled in, maintained and kept current at all times. All property described in paragraph 1 (a and b) above shall be reported on the report. At contract completion the Contractor and the Property Administrator shall ensure that all fields are appropriately completed. A signature block is provided at the end of the report for both parties to attest to the report's accuracy and completeness. The Government Property Report shall clearly delineate the complete track that all Government property took over the course of the contract. This completed report must accompany the Contractor's final invoice. Final payment may be delayed, without penalty of interest, until such time as the report is received. A separate copy of the completed report and any final DD 1149s or DD 1348s executed, as a result of carrying out disposition instructions shall be provided to the Property Administrator.

4.

Pursuant to the Government Property Clause the authority to render disposition instructions of Government property associated with this contract is delegated to the Property Administrator. The Contractor shall comply with all instructions in the contract for the return of government property to the Coast Guard. This includes government property taken off the vessel (shafts, propellers, etc.), government property returned to the vessel (special tools, etc.) or surplus government property not used during performance of the contract.

(19)

SECURITY REQUIREMENTS

A.

For access to USCG Base Kodiak, Alaska, the contract shall have RAPIDGate credentials. All personnel that need access to the base, such as on-site personnel, subcontractors (including second and third-tier subcontractors) and suppliers will need RAPIDGate credentials. This process must be completed prior to the start of work. Therefore, the Contractor shall begin the RAPIDGate registration process no less than 45 calendar days before on-site work is to commence. For enrollment into the RAPIDGate program for base access privileges, information can be found at www.rapidgate.com or by calling the RAPIDGate program at 1-877-727-4342. Please note that all costs associated with registration and participation in the RAPIDGate Program is at the sole expense of the contractor.

B.

The Contractor shall provide a list of all on-site personnel, sub-contractors (including second and third tier subcontractors), and suppliers, to the contracting officer and Contracting Officer’s Representative no less than 30 calendar days before on-site work is to commence. The Contractor shall update this list when changes occur and ensure all personnel satisfy base access standards and have RAPIDGate credentials.

C.

Contractor personnel not listed and without RAPIDGate credentials may be denied access to the Coast Guard Facility. Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the Coast Guard Facility. Contractor personnel shall have photo identification at all times while working on Coast Guard facilities. Special identification requirements may be needed to obtain the RAPIDGate credentials.

D.

Contractor and delivery personnel may be required to present personal photo identification to gain access to a Coast Guard installation. Valid forms of identification are current passport or driver’s license that meet Real ID Act requirements. Driver’s licenses from the following states are not accepted: Maine, Minnesota, Missouri, and Montana. The Real ID Act of 2005 established minimum security standards for license issuance and production and prohibits Federal agencies from accepting, for certain purposes, driver's licenses and identification cards from states not meeting the Act's minimum standards. Anyone requiring access to a military facility under this contract, to include subcontractors, who holds a driver's license from any state without approved licenses will be required to provide identification other than that driver's license to gain access. Government IDs annotated with "Federal Limits Apply" will not be accepted for access purposes. It is the responsibility of the Contractor to ensure that their personnel have federally acceptable personal photo identification and comply with any other requirements for base access. TWIC and DBIDS identification cards are not sufficient forms of identification for access to Coast Guard Base, Alameda, California.

E.

If identification does not indicate United States citizenship, Coast Guard Security may require proof of the legal right to work in the United States. Contractor and delivery personnel also may be subjected to an immigration status and outstanding criminal warrants check.

F.

Contractors shall provide the Contracting Officer’s Representative with 24 hours of advance notice of every delivery to the site (e.g. concrete, lumber, parts, etc.) and provide the company name, delivery person. And phone number of the firm(s) making deliveries. All vehicle access to Government property requires vehicle registration and proof of liability insurance. Otherwise access to the Coast Guard facility may be denied. Please contact the APM, LT Ran Ostrander, at (510) 437-6209, or by email at Ryan.T.Ostrander@uscg.mil for additional information and processes on base access protocols.

(20)

CONTRACTING OFFICER’S AUTHORITY

No oral or written statement of any person other than the Contracting Officer will in any manner or degree modify or otherwise affect the terms of this contract. The Contracting Officer is the only person authorized to approve changes in any of the requirements under this contract, and, notwithstanding any provisions contained elsewhere in this contract, said authority remains solely with the Contracting Officer. In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in cost incurred as a result thereof.

(21)

CONTRACTOR PERFORMANCE EVALUATION

The U.S. Coast Guard Surface Forces Logistic Center (SFLC) will monitor and evaluate the successful offeror’s past performance of this contract and prepare a Contractor Performance Assessment Report (CPAR) in accordance with FAR Part 42.15. All information contained in this assessment may be used, within the limitations of FAR 42.15, by the government for future source selections and in accordance with FAR 15.304, when past performance is an evaluation factor for award.

(b) NOTIFICATION: Upon completion of the contract, the contractor will be notified of the assessment. The contractor will be allowed 60 days to respond to the SLFC’s assessment of its performance entered into CPARS. The contractor’s response, if any, will be made part of the CPAR system at https://www.cpars.csd.disa.mil.

(c) INFORMATION: Information included in the CPAR may include, but is not limited to, the contractor’s record of conforming to contract requirements and to standards of good workmanship; the contractor’s record of forecasting and controlling costs; the contractor’s adherence to contract schedules, including the administrative aspects of performance; the contractor’s history of reasonable and cooperative behavior and commitment to customer s satisfaction; the contractor’s record of integrity and business ethics, and generally, the contractor’s business-like concern for the interest of the customer.

(d) RELEASE OF DATA: CPARS information is considered business sensitive and will not be released except: (1) to other Federal procurement activities which request it; (2) when SFLC must release pursuant to a Freedom of Information Act (FOIA) request; or (3) when prior written consent is requested and obtained from the contractor.

(22)

METHOD OF PAYMENT AND INVOICING INSTRUCTIONS

INVOICE SUBMISSION PROCESS:

(a) A request for payment is proper if it includes the items required by the clause at FAR 52.232-25, Prompt Payment [(a)(3)(i) through (a)(3)(ix)] and those items are accurate. If a request for payment does not include all the items required by the clause at FAR 52.232-25, Prompt Payment, or any information is inaccurate, then the request is not proper and shall be returned to the contractor with a statement of the reason(s) it is not proper.

Each invoice shall at a minimum contain the following information:

(1) Invoice Date

(2) Invoice Number

(3) Contract and Delivery/Task Order Number

(4) Contractor’s Name

(5) Contractor’s Address

(6) Contractor’s DUNS

(7) Contracting Officer’s Name

(8) Contracting Officer’s Representative’s (COR’s) Name

(9) Invoice Routing Code (IRC) assigned by the Coast Guard as follows: SFLC-2

(10) Period of Performance for Work Invoiced

(11) Contract Line Item Number(s) (CLIN(s)) and Description

(12) CLIN units for the period (if applicable), CLIN rate (if applicable), CLIN Total

(13) Invoice Total

(14) For Travel: Components in accordance with FAR 31.205-46

(15) Discount Offerings

(16) Status as a Small Business (if applicable) for accelerated payment

(17) The last invoice submitted for this award shall be clearly labeled with “FINAL INVOICE.”

(c) The contractor shall submit each invoice in accordance with the information at: https://www.fincen.uscg.mil/electron.htm.

(d) The contractor shall email the invoice and supporting documentation to include the invoice receipt generated by FINCEN from step (c) above. Failure to email the invoice and supporting documentation to the following contacts may result in invoice rejection or delay in payment:

Valerie.s.riverachase@uscg.mil

(e) In accordance with the Prompt Payment Act, for the purposes of determining a payment due date and the date on which interest will begin to accrue if a payment is late, a proper invoice shall be deemed to have been received:

(1) On the later of:

(i) For invoices that are mailed, the date a proper invoice is actually received by the designated billing office and annotates the invoice with date of receipt at the time of receipt.

(ii) For invoices electronically transmitted by the contractor via web based submission, the date a transmission is received by the designated billing office, and receipt confirmation is provided to the designated recipient; or

(ii) The seventh day after the date on which the property is actually delivered or performance of the services is actually completed; unless—

a) The agency has actually accepted the property or services before the seventh day in which case the acceptance date shall substitute for the seventh day after the delivery date; or

b) A longer acceptance period is specified in the contract, in which case the date of actual acceptance or the date on which such longer acceptance period ends shall substitute for the seventh day after the delivery date;

(2) On the date placed on the invoice by the contractor, when the agency fails to annotate the invoice with date of receipt of the invoice at the time of receipt (such invoice must be a proper invoice); or

(3) On the date of delivery, when the contract specifies that the delivery ticket may serve as an invoice.

(4) Web-based submission by the contractor and receipt confirmation does not reflect Government review or acceptance of the invoice.

(5) Payment inquiries and status may be obtained at the following website: https://www.fincen.uscg.mil/electron.htm.

(f) Failure to follow any of these instructions shall result in invoice rejection.

(23)

PROGRESS PAYMENTS

A.

The Contractor may invoice requesting progress payments without discount, other than any prompt payment discount offered, not more frequently than every two weeks.

B.

The invoice amount should reflect the percentage and dollar amount of completion established by the cutter's appropriate weekly progress report. Payments shall be derived from the accomplished percentage of completion as determined by the Contracting Officer.

C.

All material and work paid for by progress payments shall thereby become the sole property of the Government, but this provision shall not relieve the Contractor from the obligation to complete the requirements of the contract.

D.

The contractor shall be paid the remaining amount due upon completion and acceptance of all work under this contract.

(24) FAR 52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS CONTRACTORS (DEC 2013)

(a) Upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract, to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, after receipt of a proper invoice and all other required documentation from the small business subcontractor.

(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.

(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial items.

(25)

ASSOCIATE CONTRACTOR AGREEMENT (ACA)

After award, the Contractor shall enter into an Associate Contractor Agreement, if applicable, with one or more other prime contractors with the Government who will be present and performing work on the vessel during the dry dock availability.

ASSOCIATE CONTRACTOR CLAUSE

(1) This clause is intended to ensure that there will be appropriate integration of work by the USCGC ALEX HALEY, associate contractors to maximize coordination and prevent delay or additional costs.

(2) The Firm Fixed-Price (FFP) for each Work Item in ATTACHMENT 2, Price Schedule shall include all costs associated with the Prime Contractor executing each requirement stipulated in the Associate Contractor Agreement (“ACA”) as required by this clause, in support of this contract.

(3) For purposes of this clause, the Associate Contractor, known at this time, is defined as:

(a) Prime Contractor under (TBD).

(b) Additional contractors may be identified at a later date.

(4) The Associate Contractors shall work and maintain close liaison with each other. In order to assure accomplishment of this objective, the Associate Contractors shall enter into a written ACA with each other.

(5) The ACA shall provide for a complete and unbiased exchange of scheduling information to include work locations. The following shall be included in the ACA:

(a) Identification of the information to be furnished between the Associate Contractors.

This shall, at a minimum, include the schedule and locations of work to be performed.

(b) Services to be provided by one Associate Contractor to another [if applicable]

(c) The materials to be provided between the Associate Contractors during performance.

[if applicable]

(d) In accordance with Specification General Requirements, the Prime Contractor shall hold a weekly progress meeting, and also daily production meetings.

(i) At the daily production meetings, Associate Contractors shall attend and participate to resolve any potential conflicts in the work schedule for that day, so as to minimize delay, disruption or overlapping work.

(ii) At the weekly progress meetings, the Associate Contractors shall provide an integrated and de-conflicted master planning document for review by the USCG COR. Associate Contractors shall meet together prior to the weekly progress meeting to develop this master planning document.

(iii) The Associate Contractors are responsible to resolve all planning conflicts. However, the USCG COR reserves the right to serve as final decision authority when needed to ensure timely schedule completion and/or that Operational Commander’s priorities are met.

(e) The ACA may also address treatment of any proprietary or confidential information.[if applicable] (6) Following execution by both Associate Contractors, the ACA may be made an attachment to this contract. The ACA is for information purposes only and shall not be subject to or governed by this contract. In the event of a conflict between the terms of this contract and terms of the ACA, the terms of this contract shall control.

(7) Where the Associate Contractors fail to agree upon action to be taken in connection with their respective responsibilities, each of them shall promptly notify the COR responsible for their respective contract and furnish their recommendations for a solution. The Associate Contractors shall not be relieved of its obligations to make timely deliveries or be entitled to any other adjustment because of their failure to: (a) resolve ACAs disputes; (b) promptly refer matters to the COR assigned to their respective contract; or (c) to implement any direction given by the COR assigned to their respective contract.

(End of FAR 52.212-4 Addendum) FAR 52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders -- Commercial Items (OCT 2020) (a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Aug 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).

(5) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(6) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Public Laws 108-77 and 108-78 ( 19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

[Contracting Officer check as appropriate.]

FORMCHECKBOX

(1) 52.203-6, Restrictions on Subcontractor Sales to the Government (June 2020), with Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).

52.203-13 (2) , Contractor Code of Business Ethics and Conduct (Jun 2020) (41 U.S.C. 3509)).

52.203-15 (3) , Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

FORMCHECKBOX

(4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) (Pub. L. 109-282) ( 31 U.S.C. 6101 note).

(5) [Reserved]

(6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

52.204-15 (7) , Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

(8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (Jun 2020) 31 U.S.C. 6101 note).

FORMCHECKBOX

(9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) (41 U.S.C. 2313).

(10) [Reserved].

52.219-3 (11) (i) , Notice of HUBZone Set-Aside or Sole-Source Award (Mar 2020) (15 U.S.C. 657a).

52.219-3 (ii) Alternate I (Mar 2020) of .

52.219-4 (12) (i) , Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Mar 2020) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

52.219-4 (ii) Alternate I (Mar 2020) of .

(13) [Reserved]

(14) (i) 52.219-6, Notice of Total Small Business Set-Aside (Mar 2020) (15 U.S.C. 644).

52.219-6 (ii) Alternate I (Mar 2020) of .

52.219-7 (15) (i) , Notice of Partial Small Business Set-Aside (Mar 2020) (15 U.S.C. 644).

52.219-7 (ii) Alternate I (Mar 2020) of .

(16) 52.219-8, Utilization of Small Business Concerns (Oct 2018) (15 U.S.C. 637(d)(2) and (3)).

52.219-9 (17) (i) , Small Business Subcontracting Plan (Jun 2020) (15 U.S.C. 637(d)(4)).

52.219-9 (ii) Alternate I (Nov 2016) of .

52.219-9 (iii) Alternate II (Nov 2016) of

52.219-9 (iv) Alternate III (Jun 2020) of

52.219-9 (v) Alternate IV (Jun 2020) of

52.219-13 (18) (i) , Notice of Set-Aside of Orders (Mar 2020) (15 U.S.C. 644(r)).

52.219-13 (ii) Alternate I (Mar 2020) of .

(19) 52.219-14, Limitations on Subcontracting (Mar 2020) (15 U.S.C. 637(a)(14)).

52.219-16 (20) , Liquidated Damages-Subcontracting Plan (Jan 1999) (15 U.S.C. 637(d)(4)(F)(i)).

52.219-27 (21) , Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Mar 2020) (15 U.S.C. 657f).

(22) (i) 52.219-28, Post Award Small Business Program Rerepresentation (May 2020) (15 U.S.C. 632(a)(2)).

52.219-28 (ii) Alternate I (MAR 2020) of .

52.219-29 (23) , Notice of Set-Aside for, or Sole Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Mar 2020) (15 U.S.C. 637(m)).

52.219-30 (24) , Notice of Set-Aside for, or Sole Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (Mar2020) (15 U.S.C. 637(m)).

52.219-32 (25) , Orders Issued Directly Under Small Business Reserves (Mar 2020) (15 U.S.C. 644(r)).

52.219-33 (26) , Nonmanufacturer Rule (Mar 2020) (15U.S.C. 637(a)(17)).

52.222-3 (27) , Convict Labor (Jun 2003) (E.O.11755).

(28) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (Jan2020) (E.O.13126).

FORMCHECKBOX

(29) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).

(30) (i) 52.222-26, Equal Opportunity (Sep 2016) (E.O.11246).

52.222-26 (ii) Alternate I (Feb 1999) of .

(31) (i) 52.222-35, Equal Opportunity for Veterans (Jun 2020) (38 U.S.C. 4212).

52.222-35 (ii) Alternate I (Jul 2014) of .

(32) (i) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) (29 U.S.C. 793).

52.222-36 (ii) Alternate I (Jul 2014) of .

(33) 52.222-37, Employment Reports on Veterans (Jun 2020) (38 U.S.C. 4212).

FORMCHECKBOX

(34) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).

(35) (i) 52.222-50, Combating Trafficking in Persons (Oct 2020) (22 U.S.C. chapter 78 and E.O. 13627).

52.222-50 (ii) Alternate I (Mar 2015) of (22 U.S.C. chapter 78 and E.O. 13627).

(36) 52.222-54, Employment Eligibility Verification (Oct 2015). (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)

52.223-9 (37) (i) , Estimate of Percentage of Recovered Material Content for EPA–Designated Items (May 2008) ( 42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

52.223-9 (ii) Alternate I (May 2008) of (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

(38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) (E.O. 13693).

FORMCHECKBOX

(39) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (Jun 2016) (E.O. 13693).

52.223-13 (40) (i) , Acquisition of EPEAT®-Registered Imaging Equipment (Jun 2014) (E.O.s 13423 and 13514).

52.223-13 (ii) Alternate I (Oct 2015) of .

52.223-14 (41) (i) , Acquisition of EPEAT®-Registered Televisions (Jun 2014) (E.O.s 13423 and 13514).

52.223-14 (ii) Alternate I (Jun2014) of .

52.223-15 (42) , Energy Efficiency in Energy-Consuming Products (May 2020) (42 U.S.C. 8259b).

52.223-16 (43) (i) , Acquisition of EPEAT®-Registered Personal Computer Products (Oct 2015) (E.O.s 13423 and 13514).

52.223-16 (ii) Alternate I (Jun 2014) of .

(44) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (Jun 2020) (E.O. 13513).

FORMCHECKBOX

(45) 52.223-20, Aerosols (Jun 2016) (E.O. 13693).

FORMCHECKBOX

(46) 52.223-21, Foams (Jun2016) (E.O. 13693).

52.224-3 (47)(i) Privacy Training (Jan 2017) (5 U.S.C. 552 a).

52.224-3 (ii) Alternate I (Jan 2017) of .

(48) 52.225-1, Buy American-Supplies (May 2014) (41 U.S.C. chapter 83).

(49) (i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (May 2014) (41 U.S.C.chapter83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.

52.225-3 (ii) Alternate I (May 2014) of .

52.225-3 (iii) Alternate II (May 2014) of .

52.225-3 (iv) Alternate III (May 2014) of .

52.225-5 (50) , Trade Agreements (Oct 2019) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

FORMCHECKBOX

(51) 52.225-13, Restrictions on Certain Foreign Purchases (Jun 2008) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

52.225-26 (52) , Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302Note).

52.226-4 (53) , Notice of Disaster or Emergency Area Set-Aside (Nov2007) (42 U.S.C. 5150).

52.226-5 (54) , Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov2007) (42 U.S.C. 5150).

52.229-12 (55) , Tax on Certain Foreign Procurements (Jun 2020).

52.232-29 (56) , Terms for Financing of Purchases of Commercial Items (Feb 2002) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).

52.232-30 (57) , Installment Payments for Commercial Items (Jan2017) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).

FORMCHECKBOX

(58) 52.232-33, Payment by Electronic Funds…