This document is Section F of a federal contract detailing the Management and Administration deliverables and performance requirements. The contract specifies 58 distinct deliverables that the contractor must submit according to defined schedules, with distribution to the Contracting Officer (KO) and Contracting Officer's Representative (COR) as primary recipients.

Key administrative deliverables include requests for work outside regular hours (seven calendar days advance notice), sign-in sheets and meeting minutes (within two working days), permits and licenses (before work commences), certificates of insurance (within 15 calendar days prior to contract start), and Plans of Action and Milestones (within 15 calendar days prior to start). Cybersecurity incident reporting is required immediately upon discovery during working hours or by 0800 the next work day. Personnel-related deliverables include lists of key personnel and qualifications, organizational charts, employee lists, proof of legal residency and U.S. citizenship, and Service Contract Reporting (due no later than October 31 annually).

Safety and environmental compliance submissions are extensive, encompassing accident prevention plans, activity hazard analyses, OSHA citation corrective action reports (within 48 hours), monthly on-site labor reports, and safety certifications. Environmental deliverables include water conservation plans, environmental protection plans, fuel and hazardous substance spill notifications (within 15 minutes to 48 hours depending on type), asbestos notifications (within one hour verbally, 24 hours written), hazardous air pollutant reports (monthly and semiannually), and contractor hazardous material inventory logs (annually). Quality management, scheduling updates, work status reports, and property management plans are required on monthly, weekly, or as-needed bases. All deliverables are single copies unless otherwise specified, with submission frequencies ranging from as-required to monthly to annually.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section F – 0200000 Management and Administration

Section F 0200000 Deliveries or Performance

DELIVERABLES

Spec Item

Form Attachment

Number Deliverable Title Date (s) of

Submission

Distribution

Frequency Original

Copies (including original)

2.2.1.2 N/A Request to Work

Outside Government’s Regular Working Hours

At least seven calendar days prior to requested day.

KO and

COR

1 As required

2.3.1 N/A Sign-in Sheets and

Minutes for Review and Comments

Within two working days

KO, COR

and all attendees

1 As Required

2.3.1 N/A Sign-in Sheets and

Minutes Final Revision

Within two working days

KO, COR

and all attendees

1 As Required

2.3.4 N/A Permits and

Licenses

Before work commences and as requested by the KO.

KO and

COR

1 As specified

2.3.5 N/A Certificate of

Insurance

Within 15 calendar days prior to contract start.

KO and

COR

1 As specified

2.3.5 N/A Written Notice of

cancellation or material change in policy coverage

At least 30 calendar days prior to cancellation or material change in policy coverage

KO and

COR

1 As required

2.6.1 N/A Plans of Action

and Milestones (POA&Ms)

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO, COR,

and

Command Security Manager

1 As required

2.6.1 N/A Cybersecurity

Incident

Immediately upon discovery during regular working hours and by 0800 the following work day for discoveries after regular working hours

KO, COR,

and

Command Security Manager

1 As required

Form Attachment

Number Deliverable Title Date (s) of

Submission

Distribution

Frequency Original

Copies (including original)

2.6.4 N/A Scheduling and

Work Status Updates

Weekly, within 30 minutes of the inquiry during regular working hours, and by 08:00 the following work day for inquiries after regular working hours

KO and

COR

1 As Specified

2.6.4 N/A Work Schedules Within 15

calendar days prior to contract start, 10 days prior to the beginning of the month in which services are scheduled to be performance, and within two calendar days of changes.

COR 1 Monthly

2.6.5 N/A Notification of any

Difficulty in Scheduling Work

By the end of each workday

KO and

COR

1 As required

2.6.6 N/A Status of

Deliverables

Within 30 minutes of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours

KO and

COR

1 As required

2.6.7 N/A Service

Interruptions

At least five working days in advance

KO and

COR

1 As required

2.6.9.1 N/A Quality

Management Plan

Within 15 calendar days prior to contract start.

KO and

COR

1 As specified

2.6.9.1 N/A Revised Quality

Management Plan

Within seven calendar days of changes.

KO and

COR

specified

Form Attachment

Number Deliverable Title Date (s) of

Submission

Distribution

Frequency Original

Copies (including original)

2.6.9.2 N/A QC Inspection File Within five

calendar days of completion/ termination of the contract.

KO and

COR

1 As specified

2.6.9.3 J-0200000-

05H

Contractor Quality Inspection and Surveillance Report

First work day of each month.

KO and

COR

1 Monthly

2.6.10 N/A Property

Management Plan

Within 45 calendar days after award.

KO and

COR

1 As specified

2.7.1 N/A List of Key

Personnel and Qualifications

Within 15 calendar days prior to contract start

KO and

COR

1 As specified

2.7.1 N/A Organizational

Chart

Within 15 calendar days prior to contract start

KO and

COR

1 As specified

2.7.2.6 N/A Proof of Legal

Residency

Prior to be admitted to site of work.

KO and

COR

1 As specified

2.7.2.6 N/A Proof of United

States of America Citizenship

Prior to be admitted to site of work.

KO and

COR

1 As specified

2.7.3 N/A Service Contract

Reporting (SCR)

No later than 31 October

KO and

COR

1 Annually for labor executed during the period of performanc e during each Governmen t fiscal year

(FY)

2.8.1 N/A Employee List Within 15

calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

Form Attachment

Number Deliverable Title Date (s) of

Submission

Distribution

Frequency Original

Copies (including original)

2.8.8 N/A OF-306

Declaration for Federal Employment and Digital Fingerprints

Prior to commencement of work

KO, COR,

and

Security Manager

1 As required

2.9.2 N/A Accident

Prevention Plan

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As specified

2.9.3 N/A Activity Hazard

Analysis

Together with the Accident Prevention Plan and within seven calendar days of and changes.

KO and

COR

1 As specified

2.9.4 N/A Compliance Plans, Programs, and Procedures

Together with the Accident Prevention Plan and within seven calendar days of and changes.

KO and

COR

1 As specified

2.9.4.7 N/A Control of

Hazardous Energy (lockout/tagout)

Within 30 calendar days after annual inspection.

KO and

COR

1 Annually

2.9.6 J-0200000-05-

F

NAVFAC

Contractor Incident Reporting System

(CIRS)

Within five calendar days of accident.

KO and

COR

1 As required

2.9.6 J-0200000-05-

F

Weight Handling Equipment Accident Report

Within 15 working days of accident.

KO and

COR

1 As required

2.9.6 J-0200000-05-

G

Crane and Rigging Gear Near Miss Report

Within 15 working days of accident.

KO and

COR

1 As required

2.9.8 J-0200000-05-

A

Monthly On-Site Labor Report

First work day of each month.

KO and

COR

1 Monthly

2.9.9 N/A OSHA Citations

and Violations Corrective Action Report

Within 48 hours after receiving a citation.

KO and

COR

1 As required

2.9.10 N/A Safety Inspection

and Monitoring Report

Upon request. KO and

COR

Form Attachment

Number Deliverable Title Date (s) of

Submission

Distribution

Frequency Original

Copies (including original)

2.9.11 N/A Safety

Certifications

Within 15 calendar days prior to contract start and as old certifications, expire.

KO and

COR

1 As specified

2.10 N/A EMS Goals and

Policy Measurement Information

Upon request. KO and

COR

1 As required

2.10.1.1 N/A Water

Conservation Plan

Within 15 calendar days after award and for changes.

KO and

COR

1 As specified

2.10.2 N/A Environmental

Protection Plan

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As specified

2.10.2.7 N/A Fuel and hazardous

substance spill notification

Within 15 minutes of discovery

Regional Dispatch Center

1 As required

2.10.2.7 N/A Fuel and hazardous

substance spill notification

As soon as possible but not more 24 hours of discovery

KO and

COR

1 As required

2.10.2.7 N/A Fuel and hazardous

substance spill report

Within 48 hours of discovery

KO and

COR

1 As required

2.10.2.8 J-0200000-05-

C

Emergency Planning and Community Right- To-Know Act (EPCRA) Report

Within 15 calendar days prior to contract start and not less than 10 working days prior to planned use of hazardous material.

KO and

COR

1 As specified

2.10.2.8 J-0200000-05-

C

Contractor Hazardous Material Inventory Log

Within 15 calendar days after the end of each calendar year and at termination of the contract.

KO and

COR

1 Annually

Form Attachment

Number Deliverable Title Date (s) of

Submission

Distribution

Frequency Original

Copies (including original)

2.10.2.12 N/A Asbestos

Containing Material (ACM)

Verbally notify the KO and COR within one hour and follow-up with written Notification within 24 hours

KO and

COR

1 As specified

2.10.2.13 J-0200000-05-

D

Hazardous Air Pollutants Semi-annual Reports

At intervals of 160 to 200 calendar days

KO, COR,

Installation Environme ntal Division, City, State, and EPA

1 Semi-annually

2.10.2.13 J-0200000-05-

D

Hazardous Air Pollutants Monthly Data

First workday of each month.

KO, COR,

Installation Environme ntal Division

1 Monthly

2.10.3 N/A Sustainable

Procurement and Practices Plan

Within 15 calendar days prior to contract start and within 15 calendar days after exercised option periods.

KO and

COR

1 Annually

2.10.3 N/A Sustainable

Delivery of Services Report

Within five calendar days after each contract period.

KO and

COR

1 Annually

2.10.3.2 N/A Recovered

Material Certification

As specified KO and

COR

1 When a product containing recovered materials is equal to or better than the original and could be used.

2.11 N/A Mission Essential

Contractor Services Plan

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

Required

Form Attachment

Number Deliverable Title Date (s) of

Submission

Distribution

Frequency Original

Copies (including original)

2.11 N/A Mission

Critical/Mission Essential Personnel

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As specified

2.15.2.1 N/A Non-Recurring

Work Proposals

Within two working days following receipt of request

KO 1 As required

File details come from the government source that posted it. Updated .