Attachment 3 0200000 F Management and Administration.pdf
PDF 302 KB Posted
- Attached to
- Crane Lease/ Rental Services
- Solicitation number
- N4008526R0245
About this file
This document is Section F of a federal contract detailing the Management and Administration deliverables and performance requirements. The contract specifies 58 distinct deliverables that the contractor must submit according to defined schedules, with distribution to the Contracting Officer (KO) and Contracting Officer's Representative (COR) as primary recipients.
Key administrative deliverables include requests for work outside regular hours (seven calendar days advance notice), sign-in sheets and meeting minutes (within two working days), permits and licenses (before work commences), certificates of insurance (within 15 calendar days prior to contract start), and Plans of Action and Milestones (within 15 calendar days prior to start). Cybersecurity incident reporting is required immediately upon discovery during working hours or by 0800 the next work day. Personnel-related deliverables include lists of key personnel and qualifications, organizational charts, employee lists, proof of legal residency and U.S. citizenship, and Service Contract Reporting (due no later than October 31 annually).
Safety and environmental compliance submissions are extensive, encompassing accident prevention plans, activity hazard analyses, OSHA citation corrective action reports (within 48 hours), monthly on-site labor reports, and safety certifications. Environmental deliverables include water conservation plans, environmental protection plans, fuel and hazardous substance spill notifications (within 15 minutes to 48 hours depending on type), asbestos notifications (within one hour verbally, 24 hours written), hazardous air pollutant reports (monthly and semiannually), and contractor hazardous material inventory logs (annually). Quality management, scheduling updates, work status reports, and property management plans are required on monthly, weekly, or as-needed bases. All deliverables are single copies unless otherwise specified, with submission frequencies ranging from as-required to monthly to annually.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section F – 0200000 Management and Administration
Section F 0200000 Deliveries or Performance
DELIVERABLES
Spec Item
Form Attachment
Number Deliverable Title Date (s) of
Submission
Distribution
Frequency Original
Copies (including original)
2.2.1.2 N/A Request to Work
Outside Government’s Regular Working Hours
At least seven calendar days prior to requested day.
KO and
COR
1 As required
2.3.1 N/A Sign-in Sheets and
Minutes for Review and Comments
Within two working days
KO, COR
and all attendees
1 As Required
2.3.1 N/A Sign-in Sheets and
Minutes Final Revision
Within two working days
KO, COR
and all attendees
1 As Required
2.3.4 N/A Permits and
Licenses
Before work commences and as requested by the KO.
KO and
COR
1 As specified
2.3.5 N/A Certificate of
Insurance
Within 15 calendar days prior to contract start.
KO and
COR
1 As specified
2.3.5 N/A Written Notice of
cancellation or material change in policy coverage
At least 30 calendar days prior to cancellation or material change in policy coverage
KO and
COR
1 As required
2.6.1 N/A Plans of Action
and Milestones (POA&Ms)
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO, COR,
and
Command Security Manager
1 As required
2.6.1 N/A Cybersecurity
Incident
Immediately upon discovery during regular working hours and by 0800 the following work day for discoveries after regular working hours
KO, COR,
and
Command Security Manager
1 As required
Form Attachment
Number Deliverable Title Date (s) of
Submission
Distribution
Frequency Original
Copies (including original)
2.6.4 N/A Scheduling and
Work Status Updates
Weekly, within 30 minutes of the inquiry during regular working hours, and by 08:00 the following work day for inquiries after regular working hours
KO and
COR
1 As Specified
2.6.4 N/A Work Schedules Within 15
calendar days prior to contract start, 10 days prior to the beginning of the month in which services are scheduled to be performance, and within two calendar days of changes.
COR 1 Monthly
2.6.5 N/A Notification of any
Difficulty in Scheduling Work
By the end of each workday
KO and
COR
1 As required
2.6.6 N/A Status of
Deliverables
Within 30 minutes of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours
KO and
COR
1 As required
2.6.7 N/A Service
Interruptions
At least five working days in advance
KO and
COR
1 As required
2.6.9.1 N/A Quality
Management Plan
Within 15 calendar days prior to contract start.
KO and
COR
1 As specified
2.6.9.1 N/A Revised Quality
Management Plan
Within seven calendar days of changes.
KO and
COR
specified
Form Attachment
Number Deliverable Title Date (s) of
Submission
Distribution
Frequency Original
Copies (including original)
2.6.9.2 N/A QC Inspection File Within five
calendar days of completion/ termination of the contract.
KO and
COR
1 As specified
2.6.9.3 J-0200000-
05H
Contractor Quality Inspection and Surveillance Report
First work day of each month.
KO and
COR
1 Monthly
2.6.10 N/A Property
Management Plan
Within 45 calendar days after award.
KO and
COR
1 As specified
2.7.1 N/A List of Key
Personnel and Qualifications
Within 15 calendar days prior to contract start
KO and
COR
1 As specified
2.7.1 N/A Organizational
Chart
Within 15 calendar days prior to contract start
KO and
COR
1 As specified
2.7.2.6 N/A Proof of Legal
Residency
Prior to be admitted to site of work.
KO and
COR
1 As specified
2.7.2.6 N/A Proof of United
States of America Citizenship
Prior to be admitted to site of work.
KO and
COR
1 As specified
2.7.3 N/A Service Contract
Reporting (SCR)
No later than 31 October
KO and
COR
1 Annually for labor executed during the period of performanc e during each Governmen t fiscal year
(FY)
2.8.1 N/A Employee List Within 15
calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
Form Attachment
Number Deliverable Title Date (s) of
Submission
Distribution
Frequency Original
Copies (including original)
2.8.8 N/A OF-306
Declaration for Federal Employment and Digital Fingerprints
Prior to commencement of work
KO, COR,
and
Security Manager
1 As required
2.9.2 N/A Accident
Prevention Plan
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
1 As specified
2.9.3 N/A Activity Hazard
Analysis
Together with the Accident Prevention Plan and within seven calendar days of and changes.
KO and
COR
1 As specified
2.9.4 N/A Compliance Plans, Programs, and Procedures
Together with the Accident Prevention Plan and within seven calendar days of and changes.
KO and
COR
1 As specified
2.9.4.7 N/A Control of
Hazardous Energy (lockout/tagout)
Within 30 calendar days after annual inspection.
KO and
COR
1 Annually
2.9.6 J-0200000-05-
F
NAVFAC
Contractor Incident Reporting System
(CIRS)
Within five calendar days of accident.
KO and
COR
1 As required
2.9.6 J-0200000-05-
F
Weight Handling Equipment Accident Report
Within 15 working days of accident.
KO and
COR
1 As required
2.9.6 J-0200000-05-
G
Crane and Rigging Gear Near Miss Report
Within 15 working days of accident.
KO and
COR
1 As required
2.9.8 J-0200000-05-
A
Monthly On-Site Labor Report
First work day of each month.
KO and
COR
1 Monthly
2.9.9 N/A OSHA Citations
and Violations Corrective Action Report
Within 48 hours after receiving a citation.
KO and
COR
1 As required
2.9.10 N/A Safety Inspection
and Monitoring Report
Upon request. KO and
COR
Form Attachment
Number Deliverable Title Date (s) of
Submission
Distribution
Frequency Original
Copies (including original)
2.9.11 N/A Safety
Certifications
Within 15 calendar days prior to contract start and as old certifications, expire.
KO and
COR
1 As specified
2.10 N/A EMS Goals and
Policy Measurement Information
Upon request. KO and
COR
1 As required
2.10.1.1 N/A Water
Conservation Plan
Within 15 calendar days after award and for changes.
KO and
COR
1 As specified
2.10.2 N/A Environmental
Protection Plan
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
1 As specified
2.10.2.7 N/A Fuel and hazardous
substance spill notification
Within 15 minutes of discovery
Regional Dispatch Center
1 As required
2.10.2.7 N/A Fuel and hazardous
substance spill notification
As soon as possible but not more 24 hours of discovery
KO and
COR
1 As required
2.10.2.7 N/A Fuel and hazardous
substance spill report
Within 48 hours of discovery
KO and
COR
1 As required
2.10.2.8 J-0200000-05-
C
Emergency Planning and Community Right- To-Know Act (EPCRA) Report
Within 15 calendar days prior to contract start and not less than 10 working days prior to planned use of hazardous material.
KO and
COR
1 As specified
2.10.2.8 J-0200000-05-
C
Contractor Hazardous Material Inventory Log
Within 15 calendar days after the end of each calendar year and at termination of the contract.
KO and
COR
1 Annually
Form Attachment
Number Deliverable Title Date (s) of
Submission
Distribution
Frequency Original
Copies (including original)
2.10.2.12 N/A Asbestos
Containing Material (ACM)
Verbally notify the KO and COR within one hour and follow-up with written Notification within 24 hours
KO and
COR
1 As specified
2.10.2.13 J-0200000-05-
D
Hazardous Air Pollutants Semi-annual Reports
At intervals of 160 to 200 calendar days
KO, COR,
Installation Environme ntal Division, City, State, and EPA
1 Semi-annually
2.10.2.13 J-0200000-05-
D
Hazardous Air Pollutants Monthly Data
First workday of each month.
KO, COR,
Installation Environme ntal Division
1 Monthly
2.10.3 N/A Sustainable
Procurement and Practices Plan
Within 15 calendar days prior to contract start and within 15 calendar days after exercised option periods.
KO and
COR
1 Annually
2.10.3 N/A Sustainable
Delivery of Services Report
Within five calendar days after each contract period.
KO and
COR
1 Annually
2.10.3.2 N/A Recovered
Material Certification
As specified KO and
COR
1 When a product containing recovered materials is equal to or better than the original and could be used.
2.11 N/A Mission Essential
Contractor Services Plan
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
Required
Form Attachment
Number Deliverable Title Date (s) of
Submission
Distribution
Frequency Original
Copies (including original)
2.11 N/A Mission
Critical/Mission Essential Personnel
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
1 As specified
2.15.2.1 N/A Non-Recurring
Work Proposals
Within two working days following receipt of request
KO 1 As required