This document outlines specifications for drydock repairs and preservation work for the USCGC BLUEBELL. The Coast Guard is soliciting bids for various work items to be completed at a commercial shipyard facility. Key work items include side scan ultrasonic testing of the vessel's underwater hull plating, inspection and assessment of hull and appendage coatings and conditions, and 100% preservation and recoating of underwater body surfaces. Bidders must meet certification and personnel qualification requirements and adhere to safety, quality control, and environmental protection standards set forth in referenced Coast Guard specifications. The solicitation identifies areas of known interference that will require protective measures during work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC BLUEBELL (WLI 313)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2024

Developed By: Adrian J Rubio

(Rev-0, 20 June 2023)

USCGC BLUEBELL (WLI-100) DRYDOCK AVAILABILITY FY2024

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property ................................................................................. xi Consolidated List of Critical Inspection Items ........................................................................................... xii Principal Characteristics - Tender ............................................................................................................. xiii General Requirements WORK ITEM 1: Fire Prevention Requirements WORK ITEM 2: Hull Plating, Side Scan, Ultrasonic Testing WORK ITEM 3: Hull Plating, U/W Body, Inspect WORK ITEM 4: U/W Body, Preserve, 100 percent WORK ITEM 5: U/W Body, Preserve, Partial, Condition A WORK ITEM 6: U/W Body, Preserve, Partial, Condition B WORK ITEM 7: Hull Plating Freeboard, Preserve, Partial WORK ITEM 8: Hull Plating Freeboard, Preserve, 100 Percent WORK ITEM 9: Hull and Structural Plating, General, 12.75 lbs. Steel Plate, Renew WORK ITEM 10: Hull And Structural Plating, General, Cracked Steel Welds, Repairs WORK ITEM 11: Hull and Structural Plating, General, Degraded Weld, Steel, Repair WORK ITEM 12: Appendages, U/W, Leak Test WORK ITEM 13: Propulsion Shaft Rope Guards, Inspect WORK ITEM 14: Appendages, U/W, Internal, Preserve WORK ITEM 15: Tanks, Potable Water, Clean and Inspect WORK ITEM 16: Tanks, Ballast, Clean and Inspect WORK ITEM 17: Voids, Accessible, Clean and Inspect WORK ITEM 18: Propulsion Shaft Bearings, External, Check Clearances WORK ITEM 19: Propeller , Clean And Inspect WORK ITEM 20: Main Diesel Engine, MDE, Exhaust Piping, Commercial Clean WORK ITEM 21: Ship Service Diesel Generator, SSDG, Exhaust Piping, Commercial Clean WORK ITEM 22: Boiler Exhaust Stack Uptakes, Commercial Clean WORK ITEM 23: Vent Ducts, Engine And Motor Room, All, Commercial Cleaning WORK ITEM 24: Vent Ducts, Galley and Pantry Room, All, Commercial Cleaning WORK ITEM 25: Vent Ducts, Laundry Exhaust, Commercial Cleaning WORK ITEM 26: Vent Ducts, All Other, Commercial Cleaning WORK ITEM 27: Vent Fans and Motors, Non-Machinery Spaces, Overhaul WORK ITEM 28: Sea Strainers, Duplex, All Sizes, Overhaul WORK ITEM 29: Potable Water Pneumatic Tanks, Clean and Inspect WORK ITEM 30: Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift . 108 WORK ITEM 31: Rudders, Preserve, 100 Percent WORK ITEM 32: Rudder Stock Bearings Clearances, Check WORK ITEM 33: Boat Boom, Inspect & Service WORK ITEM 34: Buoy And Cargo Crane, Inspect And Service WORK ITEM 35: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 36: Sewage Holding Tanks, Clean and Inspect WORK ITEM 37: Grey Water Piping, Clean and Flush WORK ITEM 38: Sewage Piping, Clean and Flush WORK ITEM 39: Tanks, Grey Water Holding, Preserve, Partial WORK ITEM 40: Tanks (Sewage Holding), Preserve, 100 percent WORK ITEM 41: Tanks (Sewage Holding), Preserve, Partial WORK ITEM 42: Tanks, Ballast, Preserve, 100 Percent iii (Rev-0)

WORK ITEM 43: Tanks, Ballast, Preserve, Partial WORK ITEM 44: Tanks, Potable Water, Preserve, Partial, WORK ITEM 45: Decks – Exterior (Buoy or Construction Deck), Preserve 100% WORK ITEM 46: Drydock WORK ITEM 47: Temporary Services, Provide - Tender WORK ITEM 48: Engine, Overhaul, Tender/Barge, Crane, Center Section WORK ITEM 49: Deck Covering, Interior, Wet and Dry, Renew WORK ITEM 50: Machinery Exhaust Stack Insulation, Renew WORK ITEM 51: Tanks, Clean and Inspect WORK ITEM 52: Ship Service Air Receiver, Overhaul WORK ITEM 53: Ship Service Air Receiver, Renew WORK ITEM 54: Crew’s Quarters Racks, Renew WORK ITEM 55: CPO Stateroom Racks, Renew WORK ITEM 56: Point of Use Potable Water Filters, Install WORK ITEM 57: Various Pipe Hangers, Renew WORK ITEM 58: Piping Insulation, Renew WORK ITEM 59: Heating and Chilled Piping, Renew WORK ITEM 60: Sea Trial Performance, Support, Provide WORK ITEM 61: Independent NACE Inspector (Level 3), Provide WORK ITEM 62: Tenting, Provide iv (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

v (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 180 TE 4301-7, Rev -, Prop Shaft Details (313)

Coast Guard Drawing 180 TE 4301-8, Rev A, Shaft Arrangements

Coast Guard Drawing 180 TE 4302-8, Rev A, Strut & Stern Tube Dets

Coast Guard Drawing 180 TE 0500-001, Rev 1, Offsets

Coast Guard Drawing 180 TE 0500-002, Rev 1, Lines

Coast Guard Drawing 180 TE 0700-003, Rev F, Docking Plan (WLIC 313)

Coast Guard Drawing 180 TE 0700-003, Rev G, Docking Plan (WLIC 313)

Coast Guard Drawing 180 TE 103-005, Rev J, Booklet of Plans

Coast Guard Drawing 180 TE 103-5, Rev J, Booklet of Plans(BLUEBELL)

Coast Guard Drawing 180 TE 103-5, Rev J; Booklet of Plans (BLUEBELL) (313)

Coast Guard Drawing 180 TE 103-5, Rev M, Booklet of Plans(BLUEBELL)

Coast Guard Drawing 180 TE 1101-003, Rev 2, Shell Expansion

Coast Guard Drawing 180 TE 1101-005, Rev -, Shell & Deck Framing Plqn Aft Section

Coast Guard Drawing 180 TE 1101-3, Rev 2; Shell Expansion

Coast Guard Drawing 180 TE 2200-001, Rev -, Rudder, Rudder Stock and Bearings

Coast Guard Drawing 180 TE 2200-001, Rev-, Rudder, Rudder Stock and Bearings

Coast Guard Drawing 180 TE 4000-005, Rev -, Machinery Arrangement

Coast Guard Drawing 180 TE 4804-1, Rev A, Hot Cold and Potable Water Diagram (BLUEBELL)

Coast Guard Drawing 180 TE 4804-2, Rev A, Hot Cold and Sanitary Water Piping

Coast Guard Drawing 180 TE 700-3, Rev F; Docking Plan (BLUEBELL) (313)

Coast Guard Drawing 180-TE 4301-7, Rev B, Prop Shaft Details (313)

Coast Guard Drawing 180-TE 4302-8, Rev A, Strut & Stern Tube Dets (BLUEBELL as Built) (313)

Coast Guard Drawing 180-TE 4400-4, Rev -, Prop Hub Dets (BLUEBELL)

Coast Guard Drawing 180-TE 103-005, Rev J, Booklet of Plans (Bluebell) (313)

Coast Guard Drawing 180-TE 103-5, Rev J; Booklet of Plans (BLUEBELL) (313)

Coast Guard Drawing 180-TE 103-5, Rev M, Booklet of General Plans (BLUEBELL) (313)

Coast Guard Drawing 180-TE 3801-1, Rev -, Vent Sys

Coast Guard Drawing 180-TE 3801-10, Rev -, Heating & Ventilation Upgrades

Coast Guard Drawing 180-TE 3801-2, Rev -, Engine Room Vent vi (Rev-0)

Coast Guard Drawing 180-TE 3801-9, Rev C, Ventilation & Air Conditioning Arrangement

Coast Guard Drawing 180-TE 4808-4, Rev D, Instl of Vacuum Flush Sys (BLUEBELL) (313)

Coast Guard Drawing 180-TE- 4900-013, Rev A, Compressed Air System Diagram (BLUEBELL)

Coast Guard Drawing 180-TE- 4900-013, Rev, Compressed Air System Diagram

Coast Guard Drawing 180-TE 8201-1, Rev -, Boat Davit and Details

Coast Guard Drawing 180-TE_1101-5, Rev -, Shell & Deck Framing Plan Aft Section (SMILAX 315, BLUEBELL 313)

Coast Guard Drawing 180-TE-0103-005. Rev M, Booklet of General Plans

Coast Guard Drawing 180-TE-103-5, Rev M, Booklet of General Plans (BLUEBELL) (313)

Coast Guard Drawing 180-TE-3802-4, Rev B, Diagram Heating & Chilled Water System

Coast Guard Drawing 180-TE-4804-1, Rev A, Hot & Cold Potable Water Diagram (BLUEBELL)

Coast Guard Drawing 180-TE-4808-3, Rev G, Sanitary Drainage System

Coast Guard Drawing FL 533-001, Rev B, Placard Potable Water Flush

Coast Guard Drawing FL 533-002, Rev A, Point of Use Water Filter Install

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

NAVSEA Drawing 805-1626726, Rev E, Manhole, Flush, WT and OT Bolted Plate, 15x23 and 15x18

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual

Coast Guard Technical Publication (TP) 1843, SWBS 583-A, Boat Hoist and Crane Winches

Coast Guard Technical Publication (TP) 3370, SWBS 589, Feb 1993, Hydraulic Crane - Model TB 16-40

Coast Guard Technical Publication (TP) 3830, 04-APR-03, Air Compressor - Series Qr-25

Delete SFLC Std Spec 0740, if UT measurement paragraph 3.3 is not retained

Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018 General

Requirements

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General

Requirements

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General

Requirements

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0000, (SFLC Std Spec 0000), 2020, General

Requirements

Surface Forces Logistics Center Standard Specification 0174 (SFLC Std Spec 0174), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes vii (Rev-0)

Surface Forces Logistics Center Standard Specification 0740, (SFLC Std Spec 0740), 2020, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2020, Overhaul AC

Electrical Motors

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2020, Auxiliary

Machine Systems

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2020, Clean

Shipboard Ventilation Systems

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire

Prevention and Response

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310, (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2020, Install Interior

Deck Covering Systems

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2020, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2020, Temporary

Services

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2020, Temporary

Hull Accesses

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary

Hull Accesses

Surface Forces Logistics Center Technical Specification 245-2 (SFLC TS 245-2), 2014, CPP Propellers and Blades

OTHER REFERENCES

«OTHERREF»

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities

American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System

Components - Health Effects

American National Standards Institute/NSF International (ANSI/NSF) 61, 2013, Drinking Water System

Components - Health Effects

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System

Components - Health Effects viii (Rev-0)

American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2020, Recommended Practice for

Personal Qualification and Certification in Nondestructive Testing

American Society for Testing and Materials (ASTM) International F1508, 2016, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services

American Society of Mechanical Engineers (ASME) B16.34, 2017, Valves-Flanged, Threaded, and

Welding End

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D3359, 2009, Standard Test Methods for Measuring Adhesion by Tape

Test

ASTM International (ASTM) D3951, 2015, Standard Practice for Commercial Packaging

ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component

Adhesives (AN)

ASTM International (ASTM) F683, 2003, Standard Practice for Selection and Application of Thermal

Insulation for Piping and Machinery

ASTM International (ASTM) F683, 2014, Standard Practice for Selection and Application of Thermal

Insulation for Piping and Machinery

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Code of Federal Regulations (CFR) Title 29, Part 1910, Subpart T, 2007, Commercial Diving Operations

Code of Federal Regulations (CFR) Title 29, Part 1915, 2014, Occupational Safety and Health Standards for Shipyard Employment

Code of Federal Regulations (CFR) Title 29, Part 1915, 2022, Occupational Safety and Health Standards for Shipyard Employment

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for

Shipyard Employment

Code of Federal Regulations (CFR) Title 40, Protection of the Environment

Commercial Item Description (CID) A-A-59588, 2005, Rubber Silicone

Cummins Service Manual B3.9, B4.5, B5.0 RGT and B5.9 series Engines.

Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections

GM Diesel Maintenance and overhaul manual for 71 In-Line Engines Three, Four, and Six cylinder Single and multiple engine units.

International Standard Organization (ISO) 2953, 2000, Mechanical Vibration, Balancing Machines, Description and Evaluation

John Deere Component Technical Manual 4.5L and 6.8L Diesel Engines –Base engines CTM104

15FEB18

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2019 Edition, Pressure Testing Of Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2017 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service ix (Rev-0)

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2019 Edition, Bronze Gate, Globe, Angle and Check Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe

Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-DTL-24244, May 2000, Insulation Material, With Special Corrosion, Chloride, and Fluoride

Requirements

MIL-DTL-32585, July 2021, Insulation, Thermal and Acoustic, Fiberglass

MIL-I-2781, Aug 2020, Insulation; Pipe, Thermal

MIL-PRF-16173, Sep 2006, Corrosion Preventive Compound, Solvent Cutback, Cold-Application

MIL-PRF-24647, 2013, Paint System, Anticorrosive and Antifouling, Ship Hull

MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull

MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

MIL-Y-1140, Sep 1985, Yarn, Cord, Sleeving, Cloth, And Tape- Glass

Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-

PRO-160, Nov 2011, Chapter 16, Cofferdams

NAVSEA Drawing 804-5959214, Rev-, Piping Insulation - Installation Details

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure

Perkins Diesel Maintenance and overhaul manual 1100 Series 1106C-E60TA 129.5kW/174.5 bake horse power (PHP)

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C 6183, 2005, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C 6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and

Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2020 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning x (Rev-0)

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 12/NACE No.5, 2007, Surface Preparation and Cleaning of Steel & Other Hard

Materials by High and Ultrahigh Pressure Water Jetting

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough

Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning xi (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

19 Y **Propeller NSN: 2 ea.

19 Y *Propeller end nut wrench

NSN: 1 ea. 2,250.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xii (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5

(Inspection report particulars)):

Work

Item Title

2 Hull Plating, Side Scan, Ultrasonic Testing

5 U/W Body, Preserve, 100 percent

13 Appendages, U/W, Leak Test

16 Tanks, MP Fuel Stowage and Overflow, Clean and Inspect

18 Tanks, Ballast, Clean and Inspect

20 Propulsion Shaft Bearings, External, Check Clearances

21 Propeller , Clean And Inspect

30 Sea Strainers, Duplex, All Sizes, Overhaul

34 Rudder Stock Bearings Clearances, Check

35 Boat Boom, Inspect & Service

36 Buoy And Cargo Crane, Inspect And Service

51 Drydock

53 Engine, Overhaul, Tender/Barge, Crane, Center Section

54 Deck Covering, Interior, Wet and Dry, Renew

55 Machinery Exhaust Stack Insulation, Renew

58 Ship Service Air Receiver, Renew

61 Tank and Void Covers, Renew

63 Various Pipe Hangers, Renew

64 Piping Insulation, Renew xiii (Rev-0)

PRINCIPAL CHARACTERISTICS - TENDER

100' WLI (CGC BLUEBELL), INLAND CONSTRUCTION TENDER

PHYSICAL

Length overall 100' 0"

Depth 5' 0"

Maximum beam 24' 0"

Frame spacing 1' 6"

Full load draft 4' 8 1/4" LCF Draft

Full load displacement 218.16 Long Tons SW

HULL

Hull material Steel

MACHINERY

Number of propellers 2

Number of blades 5

Diameter 46"

Pitch 44" fixed

Shaft RPM 480

TANK CAPACITIES

Fuel tanks 3, 853 Gal

Fresh water tanks 9,030 Gal

Lube oil

1 (Rev-0)

00000_0522_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for

Shipyard Employment

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure

2 (Rev-0)

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire

Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety

Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast

Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.

3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec

0000, in accomplishing the following task:

• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3 (Rev-0)

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurements” for coating thickness is defined as follows:

• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5 inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B-

Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY-

130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with

NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B-

Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in

NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding

Weldox 900 are considered the same as those for welding HY-130.

4 (Rev-0)

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at

Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is _________.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an

NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’

Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous

Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements

5 (Rev-0) and individual position requirements; coordinate removal of waste containers; and maintain the Environmental

Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For

Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. The Contractor must refer to site (e.g. Base) Regulations and Instructions for details regarding local policies (e.g. crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. The Contractor must be aware that the following are approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:

3.7.1 SFLC Standard Specification 8636. Add missing paragraphs between 3.2 and 3.5 of Std Spec 8636 as follows:

“3.3 Access cut boundaries. The Contractor shall ensure that access cuts comply with the requirements and restrictions detailed in the following and in SFLC Std Spec 0740, and referenced codes.

3.3.1 Location of boundaries. Boundaries of access cuts and closure plates shall, in general, be located between principal ship framing, bulkheads, and other structural members and shall be at least three inches from any of these members or from the toes of other welds. A reduction in this three inch minimum may be approved by the KO on a case by case basis provided sufficient clearance is maintained for welding and inspection requirements. The boundaries of access cuts and closure plates should land on existing butts or seams, wherever practicable. The boundaries of prior access cuts should be utilized wherever possible. Boundaries may extend across one or more frames as required for the size of the opening.

3.3.2 Access hole dimensions and arrangements. Holes or access cuts shall be the minimum size necessary and shall be in accordance with the following:

• Rectangular access cuts and closure plates welded into primary hull structure shall be at least 12 inches wide in the lesser dimension.

• For circular access cuts, the minimum diameter shall be 4T, where T = thickness of the involved structural member, but not less than three inches.

• Circular closure plates for access cuts less than two feet in diameter shall be dished 1/16 to 1/8 inch to allow for shrinkage when welded.

• Corners of rectangular access cuts and closure plates shall have a minimum radius of 6 inches except when a boundary lands on an existing hull longitudinal seam or transverse butt weld.

• Corners at an existing seam or butt shall intersect at a 90 degree angle.

• Cuts that are to cross existing butts or seams shall do so at an angle of 90 degrees plus or minus 15 degrees.

• In primary hull structure, existing welds forming the boundary of a cut shall be cut back 3 inches beyond the toe of the access cut, except that the cut back shall not intersect or cross an existing weld, frame, or structural member. In which case, the cut back may be reduced to a minimum of two inches in length.

• Existing welds crossed by the cut shall not be cut back.

6 (Rev-0)

3.3.3 Primary hull structure. Primary Hull Structure includes the shell, main strength decks, principal longitudinal bulkheads, vertical keel, deep web girders and stiffeners designed to withstand the ship bending stress.

3.3.4 Mechanically fastened joints. Welding closer than six inches to a mechanically fastened joint should be avoided. When access cuts cross or come within six inches of a mechanically fastened joint, the fasteners shall be checked for tightness and if necessary, loose fasteners shall be seal welded or removed, and replaced for a distance of 6 inches beyond the edge of the cut. When a cut crosses a mechanically fastened seam the cut plates shall be repaired using single V welds backed with glass tape (MIL-C-20079) to prevent fusion between the mechanically fastened plates.

3.4 Ship integrity maintenance. The Contractor shall maintain safety and ship integrity by installing temporary guarding and coaming, in addition to weathertight and watertight closures. Remove these temporary fabrications after closing the hull access, and grind surfaces flush in way of removals. For shell plating cuts made at or below the waterline where temporary closures are impractical, the Contractor shall secure each vulnerable compartment and subdivision to minimize potential damage to the extent permitted by the scope and urgency of the work.

3.4.1 Guarding. Install temporary guards in accordance with 29 CFR 1915.73.

3.4.2 Coaming. Ensure that in areas where flammable liquids may be stored, a 4 inch high metal coaming shall be installed on the surface of the deck with tack welds and fully sealed with caulking compound. The coaming shall encircle the access cut in the deck.

3.4.3 Weathertight and contamination closures. Fabricate temporary closures, using fire retardant material, before cutting access openings and install closures whenever access is not in use. Closures shall be:

• Constructed to protect the access from inclement weather and entry of contaminants (shall include a coaming or dam on the deck to redirect rain runoff away from the opening).

• Fitted with fasteners that permit rapid installation and removal.

• Able to support a minimum of 150 pounds per square foot for horizontal deck closures.

• Where the access opening is in way of a removed hatch, scuttle or door, the closure shall be configured to allow normal passage of ship’s personnel and equipment.

3.4.4 Watertight closures. Ensure that access openings created four feet or less above the maximum anticipated waterline shall include temporary watertight closures when the vessel is waterborne.

NOTE

NAVSEA S0600-AA-PRO-160/CH16 provides requirements for design, fabrication, and installation of temporary watertight closures.”

3.7.2 SFLC Standard Specification 0000. Replace paragraph 3.3.4 Vessel access, as follows:

7 (Rev-0)

"3.3.4 Vessel access. During work at the Contractor’s facility, provide access and/or egress to and from the vessel in accordance with 29 CFR 1915.74, Subpart E. Provide a minimum of two gangways that have the following:

• Adequate walking surface width and strength and be safely secured.

• A railing, with a mid-rail, on each side of the gangway, and a turn table if necessary.

• Substantial steps properly secured and equipped with at least one handrail, when the upper end of the gangway rests on or is flush with the top of the bulwark of the dock.

• Nets or other suitable protection on both sides, when there is a danger of personnel falling between the ship and the dock. Nets and other suitable protection must extend beyond the projected area of the access and egress points so as to catch a personnel that may be falling outward: i.e., the nets must be wider than the gangway.

• Proper trimming at all times.

• Adequate illumination for their full length.

• Separated by one-fourth the length of the vessel, at a minimum, as to mitigate the possibility that an incident could block both means of escape."

3.7.3 SFLC Standard Specification 8635. Replace and add paragraphs as follows, "3.3.10.4.1 Contractor-furnished supporting equipment. Provide all hoses and fittings needed to supply water to the system. Provide pressure gauges at the connection(s) to the ship and the furthest firehose station to allow personnel to clearly read the gage-face to demonstrate or record the required water pressure is available at all energized portions of the system."

"3.2.3 Shipboard access/egress and routing of temporary services. Maintain a primary and secondary means of access/egress for each vessel, where practicable.

Pre-plan for the installation of temporary services to minimize the total number of service leads penetrating the hull by maximizing the use of backbones and/or manifolds for industrial services. Pre-planning for the installation of temporary services shall include removal (first in, last out, when no longer required). Pay special attention to transitional spaces (cross passages, top and bottom of stairwells) where services could potentially fall and restrict emergency personnel egress and/or casualty responder access."

"3.2.3.2 Materials used for suspending temporary services. Temporary services shall be suspended at regular intervals, to prevent impeding personnel access/egress and emergency response, using a high temperature line that meets the noncombustibility test requirements contained in reference (e). When using steel wire rope, or other potentially abrasive material, an anti-chafing material shall be used to prevent damage of the temporary service line. When available, temporary service lines may be run through the ship’s structural elements (i.e., cable ways, light stanchions, etc.). When the routing of temporary services overhead is not practicable, temporary services, rigging of hoses, welding leads, and temporary lights shall be clear of the decks on temporary “trees” or brackets and be arranged to minimize tripping and other hazards."

8 (Rev-0)

"3.2.3.5 Quick Disconnect Fittings. QDFs shall be located within 10 feet of designated vertical and horizontal fire zone boundaries. When practicable, QDFs shall be installed within 10 feet of hull penetrations used for personnel access, to facilitate the deployment of smoke control curtains. QDFs must be capable of being disconnected safely on pressurized or energized systems unless approved for use as described in paragraph 3.2.3.7. Pressurized and disconnected QDFs must prevent wetting of energized equipment. For hull openings used for services only, QDFs are not required, provided the opening is fitted with an air and smoke control “sock” that remains in place around the services. Air and smoke control curtains are not intended to provide an air tight seal of the hull opening. Rather, the curtains or socks, are to ensure that emergency responders can control the flow of air and smoke through the opening to allow for de-smoking of compartments, and minimize “chimney” effects. Curtains shall be made of fire resistant fabric meeting the requirements of NFPA 701."

"3.2.3.7 Service lines crossing fire zone boundaries. When service lines transit a fire zone boundary which cannot be safely disconnected locally (e.g., high voltage cables), the COR shall approve, in advance, the method to safely secure and remove the service."

3.7.4 SFLC Standard Specification 6310.

3.7.4.1 On page 2, replace REFERENCE “MIL-PRF-24667C, May 2008, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application” with “MIL-PRF-24667D, FEB 2021, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application”

3.7.4.2 On page 9, replace the NOTE under paragraph 3.1.8.5 as follows:

NOTE

De-ionized water may be used in cases where available fresh water has excessive chloride/chlorine content. Submit a CFR prior to using de-ionized water.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

9 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust…