This document contains answers to questions regarding solicitation number 70Z08523RIBCT0012 for repair and maintenance work items aboard USCGC BLUEBELL DD FY 24. Key details include clarification that table 1 fans data will be provided, intent verbiage added for work item W-032, confirmation that parts for work item W-034 will still be supplied by the contractor despite references to government property, specification of cosmetic polymeric epoxy resin for work item W-049, corrections to the CIR list, clarification that approximately 100 linear feet of piping will need replacement rather than the full 700 feet listed for work item WI 59, and confirmation that fuel tanks will not need to be cleaned and gas freed to complete work item WI 54 as the new berthing racks can be mounted to existing areas not requiring welding to the deck. The period of performance will remain January 16, 2024 to March 25, 2024 with no flexibility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers – CGC BLUEBELL DD FY 24
1. WI-027 - The spec references Table 1 Fans but no table is given. Additional vaneaxial fan data was not provided in the notes section. Please provide additional clarifications.
• Added table to WI, removed additional data verbiage from 4. NOTES, updated spec
2. W-032 - The intent section is missing verbiage, and the CIR section reference does not exist. Please provide additional information.
• Added verbiage to 1. SCOPE, updated spec
3. W-034 - Section 3.2 references Govt-issued property throughout tasks. Section 1.2 says
“None” for GFM. Please clarify.
• GFE was already purchased commercially. Parts still supplied by us.
4. W-049 - Does this work item require polymeric Epoxy or One step Terrazzo?
• Cosmetic Polymeric Epoxy Resin
• CIR requirement updated , updated spec
5. See the following screenshot. The CIR list contains several errors. Please provide clarification:
• Updated CIR list, updated spec
6. WI 59 – Piping lengths verification, The intent of the work item is for the contractor to renew miscellaneous heating and chilling water piping systems throughout the cutter. The referenced drawing in 3.3 lists nearly 700’ of piping. Are we to quote replacement of all the material listed in drawing number 180-TE-3802-4, Rev B? Or just miscellaneous parts of the system that have failed. Please provide an approximate amount of piping to be replaced if it is not the whole list.
We will not be replacing the whole piping system. I spoke with EPO and it would be approximately 100 liner feet.
7. WI 54, Fuel Tank Interference For Securing New Racks, The installation of new berthing racks will take place above the fuel tanks. In order to weld the racks to the floor the tanks will need to be cleaned and gas freed. Will the tanks be required to be cleaned and gas freed to complete this WI?
The KTR will not have to weld racks to the deck. There are existing mounting areas that the
KTR can use to mount the new racks.
8. Is there flexibility in the PoP?
No, the Period of Performance will now stand as the original PoP, 1/16/2024 - 3/25/2024.