Attachment 2 Statement of Work.pdf

PDF 1 MB Posted

Attached to
Cooling Tower Replacement, National Agricultural Library (Beltsville, MD)
Solicitation number
1232SA25R0038
Issued by

About this file

This Statement of Work details a cooling tower replacement project for the National Agricultural Library (NAL) in Beltsville, Maryland. The project involves completely replacing two existing cooling towers with a capacity of approximately 1000 tons, including demolition of existing infrastructure, installation of new cooling towers, structural support, pumps, piping, controls, and integration with the existing building automation system (BAS). The contractor will be responsible for providing all labor, equipment, materials, and services necessary to complete the work, with the facility remaining operational during construction and only experiencing limited outages.

Key project specifications include a 180-calendar day performance period, work hours limited to Monday-Friday 7:30am to 4:30pm, and a one-year warranty on workmanship and materials. The project will follow multiple building and engineering codes, including International Building Code, ASHRAE standards, and OSHA regulations. The contractor must submit a site-specific safety plan, comprehensive project schedule, and various technical submittals. The engineering project manager is Jim Glick from USDA, and the real property manager is Michael Hajjar, both located in Beltsville, MD. Contractors must be registered in the System for Award Management (SAM) and are encouraged to conduct a site visit to confirm project conditions before bidding.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture

Research, Education, and Economics

Agricultural Research Service

USDA-ARS Facilities Division

5601 Sunnyside Ave, Beltsville, MD 20705 USDA is an Equal Opportunity Provider and Employer

STATEMENT OF WORK

National Agricultural Library (NAL)

Cooling Tower Replacement

Beltsville, MD

Jim Glick

March 28, 2025

NAL Beltsville, MD – Cooling Tower Replacement

Table of Contents 1 Project Information

2 Scope Statement

2.1 Background Information

2.2 Base Bid

2.3 Bid Options

2.4 Site Visit

3 Codes and Standards

4 Project Requirements

5 Contractor Responsibilities

6 Documentation Requirements

6.1 Submittals

7 Special Requirements

7.1 Permits

7.2 Quality Control

8 Safety Requirements

8.1 Housekeeping

8.2 Clean-Up

9 Project Schedule

10 Period of Performance (POP)

10.1 Work Hours

11 Warranty

12 Project Contacts

13 Attachments

STATEMENT OF WORK

1 Project Information

Title: NAL Cooling Tower Replacement

Location: National Agricultural Library (NAL) 10301 Baltimore Ave, Beltsville, MD 20705

2 Scope Statement

The objective of this project is to REPLACE the two existing cooling towers entirely according to the 100% Design Package documents prepared by Summers Consultants Inc., including demolition of existing towers and associated components, replacement of the structural steel support, provide a new control system fully integrated into the existing BAS, equipment commissioning, and training onsite personnel. Contractor shall provide temporary means of cooling the building outlined in the 100% Design Package during the time the main tower system is not in service or not yet commissioned.

The contractor shall include all services and field labor, equipment (including cranes, rigging, and digging equipment), materials, testing and personal protective equipment necessary to perform the work.

No government equipment or services will be available for use by the contractor.

The facility will be occupied and must remain operational during construction activities. The NAL can only experience limited outages during construction.

2.1 Background Information

The National Agricultural Library was built in the mid to late 1960’s. The Library approximately 340,000 square feet of space and has a fifteen-story tower and a two-story annex.

The cooling tower has an approximate capacity of 1000 tons. The cooling tower was replaced in 1998 but is now at the end of its serviceable life. The 1998 replacement construction documents are not available.

2.2 Base Bid

The contractor shall provide a detailed technical proposal and cost estimate for the entire project as specified in this statement of work. Vendor proposal shall be structured and itemized with details for each item including roll-up costs for items listed below. The base of the proposal shall include:

1) Demolition of cooling towers and associated components

2) Replacement of Cooling Towers, structural support, pumps, piping, controls

3) Commissioning of cooling tower system

2.3 Bid Options

The contractor shall provide the bid options in their technical proposal and cost estimate to include the following tasks.

1) No bid options are anticipated for this project. Contractor may include options in their proposal that may be appropriate.

2.4 Site Visit

Contractors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing conditions relevant to the completion of this project.

No consideration will be given to claims based on lack of knowledge of existing conditions except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.

Contractor must be registered in System for Award Management (SAM) prior to submitting a bid. Registration can be completed at www.sam.gov.

3 Codes and Standards

The following codes and standards govern the design, construction, quality control, and safety of structural work performed on this project (but not limited to the following):

International building code (IBC-2021), international code council (ICC).

International existing building code (IEBC-2021), international code council (ICC).

Minimum design loads and associated criteria for building and other structures (ASCE 7-

16), American society of civil engineers.

Building code requirements for reinforced concrete (ACI 318-19), American concrete institute (ACI).

Specifications for structural concrete for buildings (ACI 301-16), American concrete institute (ACI).

Manual of standard practice, (CRSI msp-2018) concrete reinforcing steel institute (CRSI).

Specification for structural steel buildings (AISC 360-16), American institute of steel construction (aisc).

Structural welding code-steel (AWS D1.1/D1.1M:2015), American welding society

(AWS).

Other applicable Codes and Standards apply and are not limited to the following:

ADA - Americans with Disabilities Act AMCA – Air Movement and Control Association ANSI – American National Standards Institute ASHRAE – American Society of Heating Refrigeration and Air-Conditioning Engineers ASME – American Society of Mechanical Engineers EPA – Environmental Protection Agency NEC – National Electric Code NFPA – National Fire Protection Association OSHA – Occupational Safety and Health Administration RCRA – Resource Conservation and Recovery Act SMACNA - Sheet Metal & Air Conditioning Contractors’ National Association

4 Project Requirements

The scope of work for this project includes the following:

Demolishing cooling towers, support structure, pumps, piping, and controls Supply and install new cooling towers, support structure, pumps, VFD’s, piping, controls Integrate cooling tower controls into existing BAS system Providing temporary cooling (as specified in the 100% Design Package) and incidental related work.

Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

The contractor is responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work.

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a) Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b) Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer.

At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

Commissioning is required for this project. The Contractor shall provide all services necessary to ensure commissioning is accomplished in accordance with the requirements described in section 100% Design Package. Contractor shall submit a separate CPM schedule for pre-performance testing, TAB, start-up, commissioning, and substantial completion.

5 Contractor Responsibilities

The contractor shall provide a complete and functional installation, including all labor, supervision, tools, materials, equipment, apparatus, transportation, rigging and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.

The project work shall be performed per the following guidelines:

Contractor will verify all dimensions and site conditions prior to beginning work.

Contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees.

Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site weekly.

Contractor is required to manage the project and consult with the Government prior to beginning all work phases.

Contractor shall perform work in a manner that minimizes the impact of daily operations of the facility and its workers. The building will be occupied and must remain functional during construction work.

Contractor will provide daily reports of work performed to the COR and LM, and weekly status updates to the EPM and COR.

Contractor must have a superintendent on the jobsite when crews are performing the installation work.

Contractor will provide their own restroom facility.

All work is to be performed according with building codes, ordinances and laws of the Authority having jurisdiction on the project. When the requirements of the building codes, ordinances and laws conflict with any other part of the building codes, ordinances and laws, the most restrictive requirement shall prevail.

Contractor shall determine where debris will be disposed of and what containers and methods will be used for handling and separating demolition debris.

The contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the contractor’s expense, to pre-damaged condition to the satisfaction of the COR and LM.

The contractor shall provide continuous noise and dust abatement as required to prevent disturbance and nuisance to the public, workers, and occupants of adjacent premises and surrounding areas. Dampen or cover areas affected by demolition operations as necessary to prevent dust nuisance.

6 Documentation Requirements

Provide submittals to the Government well in advance of utilizing the material on the project to give enough time for review and approval. Do not purchase any material without Government approval of the submittal. Distribute product submittals to CO, COR and Location Monitor (LM) in pdf format via email attachment.

Comments and approval of the submittals by the Government shall not be construed as releasing the Contractor from compliance with the specified requirements herein or any applicable Codes.

6.1 Submittals

Submittal reviews and responses to RFI’s shall be accomplished in a maximum of 7 days for the contractor AND 14 days for the Government for a total of 21 days.

Electronic files of all required documents necessary to describe the complete design intent shall be transmitted directly to the EPM/COR, LM, and CO with electronic files in PDF format (unless otherwise specified by the Government).

Submittal requirements detailed in specification 01 33 00 and subsequent technical spec sections of the 100% Design Package and include:

SD-01 Preconstruction Submittals SD-02 Shop Drawings SD-03 Product Data SD-04 Samples SD-05 Design Data SD-06 Test Reports SD-07 Certificates SD-08 Manufacturer's Instructions SD-09 Manufacturer's Field Reports SD-10 Operation and Maintenance Data SD-11 Closeout Submittals

7 Special Requirements

7.1 Permits

Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the contractor shall obtain these items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the contractor. Submit copies of demolition, hauling, and debris disposal permits and notices for record purposes. Include a description of the proposed haul routes.

7.2 Quality Control

The work performed under this contract shall be subject to continuous audit by the COR and LM. Quality control is the exclusive responsibility of the contractor.

A final inspection shall be completed and documented prior to final payment and project close-out. The final inspection report must confirm the completion and successful installation of equipment, piping, electrical, and utilities according to the manufacturer’s recommended installation instructions. Final inspection report shall include a completed punch-List confirming each action item has been fully addressed to the satisfaction of the COR and LM.

8 Safety Requirements

The contractor is responsible for complying with all local, state, and federal safety codes and laws.

The contractor will submit a Site-Specific Safety Plan (SSSP) in industry recognizable format to the CO and COR within 14 days of the contract award. The Government shall review the (SSSP) prior to the start of any construction activities.

Safety and health matters, as they relate to the work, are the exclusive responsibility of the contractor. The contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities, and personnel.

8.1 Housekeeping

Effective housekeeping can help control or eliminate many workplace hazards. It also requires paying attention to important details such as the layout of the whole work site, work areas, walkways, storage areas, etc. Good housekeeping is also a basic part of incident and fire prevention.

Housekeeping is an ongoing task, not an ‘achievement’. Cleaning and organization must be done regularly, not just at the end of the shift. Constantly integrating housekeeping into jobsite activities can help ensure this is done properly. A good housekeeping program identifies and assigns responsibilities for the following:

Clean up during the shift Day-to-Day cleanup Waste disposal Removal of unused materials Inspecting to ensure cleanup is complete

8.2 Clean-Up

The contractor shall keep the construction site clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the contractor shall remove all unused material, trash, and debris resulting from the work to the satisfaction of the COR and LM.

9 Project Schedule

The Contractor shall provide a CPM project schedule within seven (14) calendar days after the date of receipt of award. The schedule shall show all work activities are successfully completed within the period of performance. At minimum, the schedule shall include major milestones and MEP disciplines, to include, but not be limited to:

• Notice to Proceed Date

• Permit Applications and Inspection dates

• Planned outages

• Government Review Time (2 weeks)

• Construction Start Date

• Construction End Date

• Substantial Completion

• Final Inspection/Acceptance

• Warranty Start

Contractor shall submit a separate CPM schedule for pre-performance testing, TAB, start-up, commissioning, and substantial completion.

10 Period of Performance (POP)

The period of performance shall be 180 Calendar Days after receiving the Notice to Proceed (NTP) from the Contracting Officer.

10.1 Work Hours

Generally, the contractor work hours shall be Monday - Friday, 7:30 am to 4:30 pm except on Government Holidays. Any changes to the work schedule shall be submitted to the CO and COR for written CO approval three days prior to implementing the change to the schedule.

11 Warranty

All work shall be guaranteed for workmanship and material failures for a period of one (1) year from the date of final acceptance of the work. The contractor shall submit all product warranty documents to the COR.

12 Project Contacts

Project Role: Name / Location / Phone / Email

Contracting Officer (CO) TBD

Engineering Project Mgr (EPM) Contracting Officer’s Rep (COR)

Jim Glick - USDA Beltsville, MD 443-310-0559 jamesglick@usda.gov

Administrative Officer (AO)

Location Monitor (LM)

Safety and Occupational Health Officer

Real Property Manager (RPM) Michael Hajjar Beltsville, MD michael.hajjar@usda.gov

13 Attachments

NAL CTW – Final Design Phase Commissioning Plan

NAL CTW – Final Drawings

NAL CTW – Final Specifications

End of doc