Attachment 2 - Specifications.pdf

PDF 1 MB Posted

Attached to
Levee Repair at P. L. 84-99 Site 0561-31
Solicitation number
W91238-20-R-0056
Issued by

About this file

This is a solicitation for levee repair work at PL 84-99 Site 0561-31. The repair work includes constructing approximately 2,000 feet of new setback levee to tie into the existing levee at both ends of the site. The solicitation is issued by the Department of the Army Corps of Engineers Engineering District Sacramento. The repair work will be awarded on a competitive basis. Offerors should submit proposals by the response date specified to be considered for the award.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISTRIBUTION STATEMENT A

Approved for public release; distribution is unlimited

REQUEST FOR PROPOSAL (RFP)

SACRAMENTO RIVER RIGHT BANK

PL 84-99 EMERGENCY LEVEE REPAIRS

SITE 0561-31

YOLO COUNTY, CALIFORNIA

SOLICITATION NO. XXXXXX-XX-X-XXXX

SPECIFICATION NO. 2214

DESIGN FILE NO. 6-04-2266

ISSUE DATE: MARCH 2020

PL 84-99 Emergency Repairs, Site 0561-31 Spec No. 2214 Site 0561-31 Sacramento River

PROJECT TABLE OF CONTENTS

DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS

00 01 15 LIST OF DRAWINGS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 PRICE AND PAYMENT PROCEDURES

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 23 TEMPORARY STORMWATER POLLUTION CONTROL

01 71 10 MOBILIZATION AND DEMOBILIZATION

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 GEOTEXTILE

31 11 00 CLEARING, GRUBBING, AND STRIPPING

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 15 00 AGGREGATE SURFACING

32 92 19 SEEDING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/11

PART 1 GENERAL

1.1 SUMMARY

1.2 CONTRACT DRAWINGS

1.3 SUPPLEMENTARY DRAWINGS

1.3.1 Subsurface Data

-- End of Section Table of Contents --

DOCUMENT 00 01 15 Page 1

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/11

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

DRAWING

NO.

REVISION

NO.

TITLE

G-001 N/A Cover Sheet

G-002 N/A General Notes, Legend, Abbreviations and Sheet Index

G-003 N/A Project Location and Vicinity Map

G-004 N/A Staging Area and Haul Routes

G-005 N/A Key Map and Control Line Line and Curve Tables

G-006 N/A Construction Limits

V-001 N/A Project Survey Control

C-101 N/A Excavation Plan

C-111 N/A Plan and Profile, STA 30+20 TO 20+00

C-112 N/A Plan and Profile, STA 20+00 TO 10+00

C-201 N/A Waterside Ramp Plan and Profile

C-301 N/A Typical Cross Sections

C-311 N/A Cross Sections, Sta 10+50 TO 13+25

C-312 N/A Cross Sections, Sta 13+50 TO 16+00

C-313 N/A Cross Sections, Sta 17+00 TO 25+25

C-314 N/A Cross Sections, Sta 25+50 TO 28+00

C-315 N/A Cross Sections, Sta 29+00 to 30+20

DOCUMENT 00 01 15 Page 2

C-501 N/A Details

1.3 SUPPLEMENTARY DRAWINGS

These supplementary drawings may not be a part of the Contract but are included with the drawings for information.

1.3.1 Subsurface Data

Subsurface data, not specified or indicated, have been obtained by the Government at the Project site. The data are available for examination by prospective bidders in the office of the Contracting Officer.

-- End of Document --

DOCUMENT 00 01 15 Page 3

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

05/17

PART 1 GENERAL

1.1 PAYMENT

1.2 REFERENCES

1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

1.4 SUBMITTALS

1.5 PARTNERING

1.5.1 Informal Partnering

1.6 UTILITIES

1.7 PLANNED UTILITY OUTAGES AND STREET CLOSURES

1.8 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.9 BID ITEM OVERRUN

1.10 WARRANTY OF CONSTRUCTION

1.11 NON CONTRACT WORK

1.12 DAMAGE TO ROADS

1.12.1 Documentation Regarding Potential Damage to Access Routes

1.12.1.1 Preconstruction Quantity Survey Plan

1.12.1.2 Preconstruction Access Road Survey

1.12.1.3 Post-Construction Access Road Survey

1.13 LEVEE QUANTITY SURVEY

1.13.1 Preconstruction Levee Survey

1.13.2 Post-Construction Levee Survey

1.13.3 Borrow Site and Disposal Site

1.14 ENVIRONMENTAL LITIGATION

1.15 ADDITIONAL STAGING AREAS

1.16 LEVEE DEGRADE CONSTRUCTION WINDOW

PART 2 PRODUCTS

2.1 GOVERNMENT FURNISHED MATERIALS

PART 3 EXECUTION

3.1 AFTER AWARD DOCUMENTS

SECTION 01 00 00 Page 1

SECTION 01 00 00

GENERAL REQUIREMENTS

05/17

PART 1 GENERAL

1.1 PAYMENT

No separate payment will be made for the work covered under this Section and all costs in connection therewith will be considered a subsidiary obligation.

1.2 REFERENCES

The publications listed below form a part of this Section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 415-1-15 (1989) Construction Time Extensions for Weather

1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) Contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE Contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant Contract, USACE Contractors are encouraged to seek out highly qualified veterans to perform services under this Contract. The following resources are available to assist USACE Contractors in their outreach efforts:

Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx

Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/

Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/

Army Wounded Warrior Program -http://wtc.army.mil/modules/employers/index.html

U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/

Guide to Hiring Veterans - Reference Material http://www.whitehouse.gov/sites/default/files/docs/white_house _business_council_-_guide_to_hiring_veterans_0.pdf

SECTION 01 00 00 Page 2

1.4 SUBMITTALS

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Preconstruction Quantity Survey Plan; G

Preconstruction Access Road Survey

Preconstruction Levee Survey; G

After Award Documents

SD-11 Closeout Submittals

Post-construction Access Road Survey

Post-Construction Levee Survey; G

1.5 PARTNERING

To most effectively accomplish this Contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government Construction Team, the Contractor and their Subcontractors. Key personnel from the Government Construction team, Construction Subject Matter Experts, the Contractor and Subcontractors, will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule. Small projects should have an Issue Resolution Matrix at a minimum. As project increase in size/complexity, the partnering processes will expand accordingly.

1.5.1 Informal Partnering

The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel. The Initial Partnering session will be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor. The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than three to six month intervals.

Informal Partnering is led by Resident Engineer personnel at the Pre-Construction Conference.

1.6 UTILITIES

It is anticipated that pole lines, signs, pipelines and private improvements that would interfere with or are to be replaced by new construction will be removed to new locations by the owners (or by the State of California or its agents) in advance of construction operations.

Notify the Contracting Officer at least 30 calendar days in advance of the date on which work will be started requiring the removal of such utilities or private improvements. Care must be taken to preserve and protect any such improvements from injury or damage during construction operations.

SECTION 01 00 00 Page 3

Assume full responsibility for reimbursing the owners for any damage to their properties, utilities, or improvements, or interference with their services caused through construction operations. Should such damage be found to have been caused without the Contractor's fault or negligence an equitable adjustment in the amount due under the Contract will be made under the applicable CONTRACT CLAUSES. If unplanned utilities are discovered during construction the Contractor must notify the Contracting Officer.

The Contractor shall coordinate with utility owners and the Contracting Officer for utilities identified to be protected in place on the Plans.

Contact information for utility owners are shown on the Plans.

1.7 PLANNED UTILITY OUTAGES AND STREET CLOSURES

Power outages must be restricted to off-duty hours and weekends. Other utilities may be connected and streets closed during normal working hours with the outage duration and street closure as short as possible. All outages and street closures must be scheduled as far in advance as possible with the Contracting Officer and in no case less than 7 days before the outage or closure.

1.8 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

This provision specifies the procedure for the determination of time extensions for unusually severe weather. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the Contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather-dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

8 7 7 3 2 0 0 0 1 2 5 8

Upon execution of the Notice to Proceed (NTP) and continuing throughout the Contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

SECTION 01 00 00 Page 4

Refer to ER 415-1-15 .

1.9 BID ITEM OVERRUN

Throughout the Contract (at a minimum, every two weeks), monitor placement or installation of unit price items (if any) with respect to the original estimated quantities shown in the Contract. If placement or installation indicates a possible overrun with respect to the original estimated quantities shown in the Contract, immediately provide written notification to the Contracting Officer with revised total estimated quantities.

1.10 WARRANTY OF CONSTRUCTION

a. Performance Bond.

(1) It is understood that the Contractor's Performance Bond will remain effective throughout the life of all warranties and warranty extensions.

(2) In the event the Contractor or his designated representative fails to commence and diligently pursue any work required under the Warranty of Construction Section of the Technical Provisions within a reasonable time after receipt of written notification pursuant to the requirements thereof, the Contracting Officer must have a right to demand that said work be performed under the Performance Bond by making written notice on the surety. If the surety fails or refuses to perform the obligation it assumed under the Performance Bond, the Contracting Officer must have the work performed by others, and after completion of the work, must make demand for reimbursement of any or all expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

(3) Warranty repair work which arises to threaten the health or safety of personnel, the physical safety of property or equipment, or which impairs operations, habitability of living spaces, etc., will be handled by the Contractor on an immediate basis as directed verbally by the Contracting Officer or his authorized representative. Written verification will follow verbal instructions. Failure of the Contractor to respond as verbally directed will be cause for the Contracting Officer or his authorized representative to have the warranty repair work performed by others and to proceed against the Contractor as outlined in the paragraph b. above.

1.11 NON CONTRACT WORK

Do not perform any work or erect any structure for third parties, landowners or otherwise, within the limits of construction shown on the Plans without prior approval of the Contracting Officer.

1.12 DAMAGE TO ROADS

Preserve and protect all existing private or private project access or right-of-way roads. At the completion of work and prior to the Contractor leaving the project, he must restore to pre-project conditions all such roads. Repairs must include replacement of base rock and/or surface treatment as required. Refer also to paragraph PROTECTION OF TRAFFIC in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.

SECTION 01 00 00 Page 5

1.12.1 Documentation Regarding Potential Damage to Access Routes

1.12.1.1 Preconstruction Quantity Survey Plan

Complete and submit a Preconstruction Quantity Survey Plan stating the names of personnel and license number who will be performing the Before Construction (BC) survey, plus the procedures to be followed in conducting the BC Survey. Surveys must be performed by a licensed surveyor in the State of California. The plan must also include the Preconstruction Access Road Survey and the Post-Construction Access Road Survey.

1.12.1.2 Preconstruction Access Road Survey

Complete and submit a Preconstruction Access Road Survey including digital video and digital photographs of all public, private, and project access or right-of-way roads as noted on the Plans before construction begins.

Submit two copies of the survey, the digital video, and the digital photographs before the start of construction operations. Video must be digital format. Photographs must be digital prints.

1.12.1.3 Post-Construction Access Road Survey

After completion of construction of the project, submit a Post-Construction Access Road Survey including digital video and digital photographs of the same area where preconstruction digital video and digital photographs were taken. Submit two copies of the survey, the digital video, and digital photographs.

1.13 LEVEE QUANTITY SURVEY

1.13.1 Preconstruction Levee Survey

Survey cross sections before construction begins (see submittal "Preconstruction Levee Survey"), along the entire length of the construction site. These preconstruction survey cross sections will be used to reflect existing ground before any construction activities begin and will also be used as the original ground surveys when checking measurement for pay quantities as described in Section 01 22 00 PRICE AND PAYMENT PROCEDURES and Section 31 00 00 EARTHWORK. Cross sections must be surveyed perpendicular to the setback levee control line shown on the Plans. Points along the cross sections must be surveyed within 10 feet of each other. Where applicable, perform a profile survey of the top of the levee along the entire length where the road is used for access.

Cross sections along the Control Line shown on the Plans shall include the entire existing levee embankment where the existing levee will be excavated and reconstructed and continue out to a point at least 10 horizontal feet past the completed work on both the waterside and landside and 10 feet beyond the limits of excavation. Elevations must be taken at inflection points but at not more than 5 feet intervals to the nearest 0.1 feet. Horizontal locations must not deviate from the alignment of the cross section line by more than 1 foot. All cross sections must be plotted as viewed in the downstream direction. The survey data must be provided to the Contracting Officer on Compact Disk containing survey control and cross section points defined in the form of Northing and Easting coordinates and their elevations (i.e., X, Y and Z). Horizontal control must be referenced to the North American Datum (NAD) of 1983.

Vertical control must be the North American Vertical Datum (NAVD) of

SECTION 01 00 00 Page 6

1988. Survey data must be provided in English units in AutoCAD 2016 format (Name.DWG).

Provide the Contracting Officer the survey data files, one set of the cross section data, plotted as viewed in the downstream direction, with a 5 horizontal X 2 vertical grid, on a standard D size drawing sheet, at a scale of 1:10, horizontal and vertical. The Contractor is responsible for preparing any needed layout drawings. Standard cross section plotting paper with pre-printed red grid is not acceptable.

1.13.2 Post-Construction Levee Survey

Provide to the Contracting Officer surveyed cross sections taken after the placement of compacted fill. Take cross sections at the same locations as the Preconstruction Levee Survey cross section, referenced in this Section. All surveys must be performed by a licensed surveyor in the State of California.

1.13.3 Borrow Site and Disposal Site

The Contractor shall prioritize use of excavated soil for construction of the Project provided the soils meet the requirements of Section 31 00 00.

Additional fill materials shall be acquired from commercial borrow site at the Contractor's expense. The Contractor shall determine that borrow area is Federally approved and State of California approved. Excess excavated material shall be sent to a commercial disposal site at the Contractor's expense.

1.14 ENVIRONMENTAL LITIGATION

a. If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, must determine whether the order is due in any part to the acts or omissions of the Contractor or a subcontractor at any tier not required by the terms of this Contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a subcontractor at any tier other than as required by the terms of this Contract, such suspension, delay, or interruption must be considered as if ordered by the Contracting Officer in the administration of this Contract under the terms of the SUSPENSION OF WORK clause of this Contract. The period of such suspension, delay or interruption must be considered unreasonable, and an adjustment must be made for any increase in the cost of performance of this Contract (excluding profit) as provided in that clause, subject to all the provisions thereof.

b. The term "environmental litigations" as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

1.15 ADDITIONAL STAGING AREAS

The Contractor is required to use the proposed staging areas shown on the Plans for offices and staging. If alternative sites are determined to be necessary, they must be near the project and the Contractor must make all arrangements including but not limited to clearance of non-sensitive

SECTION 01 00 00 Page 7 archeological and environmental sites for their use at the Contractor's expense and must be approved by the Government prior to use..

1.16 LEVEE DEGRADE CONSTRUCTION WINDOW

Excavation of the existing levee at the setback levee tie-in locations shall not begin prior to June 1. Restoration of the existing levee and tie-in shall be completed by September 15.

PART 2 PRODUCTS

2.1 GOVERNMENT FURNISHED MATERIALS

The Government will provide an optical disc at the preconstruction conference that contains the materials specified in Section 01 78 00

CLOSEOUT SUBMITTALS.

PART 3 EXECUTION

3.1 AFTER AWARD DOCUMENTS

Provide five conformed hard copy sets reproduced from the PDF Contract plans and specification provided by the Contracting Officer at the time of award. The hard copy drawings must be two sets of ANSI D (22" x 34")and three sets of half size (11" x 17") 3-hole punched and bound with metal posts. The five sets of specifications must be standard letter (8-1/2" x 11") 3-hole punched and bound with metal posts. Submit these documents within 5 work days of the receipt of the AWARD documents from the Government .

-- End of Section --

SECTION 01 00 00 Page 8

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.2 TYPE OF CONTRACT

1.3 PROJECT LOCATION

1.4 PROJECT DESCRIPTION

1.4.1 Project Description

1.4.2 Borrow Area

1.4.3 Water Supply for Construction

1.4.4 Offices, Stockpile and Staging Areas

1.4.5 Site Access

1.5 EXISTING FACILITIES

1.6 LOCATION OF UNDERGROUND UTILITIES

1.7 CONTRACTOR'S USE OF THE PREMISES

1.8 WORK TO BE PERFORMED BY THE CONTRACTOR

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

This Section describes the Sacramento River Right Bank, PL 84-99 Emergency Levee Repairs, Site 0561-31 Project, including location and access, existing facilities, the Contractor's use of the premises, project occupancy, and the work to be performed by the Contractor. The description of the work to be performed that is provided herein is intended to be a general overview and does not include all the work actually required under the contract.

1.2 TYPE OF CONTRACT

This contract consists of Lump Sum and Unit Price Bid Schedule Items.

1.3 PROJECT LOCATION

The project is located on the right bank of the Sacramento River approximately 3.6 miles north of Knights Landing in Yolo County, California. The exact work is shown on the Plans.

1.4 PROJECT DESCRIPTION

1.4.1 Project Description

The work includes the construction of an approximately 1,800-foot-long setback levee along the right bank of the Sacramento River. The existing levee will be excavated at the tie-in locations and rebuilt to existing grade concurrent with the construction of the setback levee. A 50-foot-wide berm will be constructed along the landside toe of the setback levee and extended along the landside toe of the existing levee as shown on the Plans. The setback levee will be constructed with materials obtained from a Contractor-provided borrow source that meets the requirements of Section 31 00 00 EARTHWORK. Material excavated from the foundation and from the existing levee can be used for setback levee and berm construction provided it meets, or can be blended to meet, these requirements. Excess excavated material will be placed within stockpile areas shown on the Plans. An all-weather aggregate base access road will be constructed on the setback levee and the portion of the existing levee disturbed at the tie-in locations. A ramp will be constructed on the waterside slope of the setback levee to provide access to the setback area. An existing concrete ditch and existing irrigation piping within the footprint of the setback levee and berm will be removed and wasted.

1.4.2 Borrow Area

The Contractor shall identify a local borrow source with sufficient material to construct the proposed work. On site excavation shall be used as fill materials to the maximum extent possible provided the material meets, or can be blended to meet, the requirements of these Specifications. Testing showing the suitability of the borrow site for

SECTION 01 11 00 Page 2 the proposed work shall be submitted in accordance with Section 31 00 00

EARTHWORK.

1.4.3 Water Supply for Construction

Refer to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS for information regarding the water supply for construction and the responsibilities of the Contractor.

1.4.4 Offices, Stockpile and Staging Areas

Refer to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS for information regarding areas available for field offices and stockpile and staging areas.

1.4.5 Site Access

Refer to the Plans for information regarding site access points and haul routes.

1.5 EXISTING FACILITIES

Existing facilities are shown on the Plans to the extent known.

1.6 LOCATION OF UNDERGROUND UTILITIES

Overhead and underground utilities exist within the project area and along access/haul routes that will be protected in place. The Contractor shall coordinate with utility owners and the Contracting Officer for those utilities shown to be protected.

The Contractor shall be responsible for the locating of all underground utilities and for coordinating its work with the appropriate Utility Owner as needed. Notify the Contracting Officer and Underground Service Alert (USA) at least 48 hours prior to starting excavation work to locate and mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday.

An existing 10-inch gas line has been identified at the upstream end of the project. All work within 50 feet of the gas line shall be coordinated with the Contracting Officer and Calpine Gas as shown on the Plans.

Any damage to existing utilities by the Contractor shall be repaired at no cost to the Government. The Contractor shall be responsible for protecting any utilities near work or haul/access roads.

1.7 CONTRACTOR'S USE OF THE PREMISES

In addition to requirements presented elsewhere on the Plans and in the Specifications, the Contractor shall adhere to the following requirements:

a. The Contractor shall have charge and care of, and bear the risk of damage to the Project until its completion and final acceptance.

b. The Contractor shall not create or permit the continued existence of any nuisance in or about the work site.

c. The Contractor shall protect and not disturb existing facilities, or access thereto, which are not in the work area or are in the work

SECTION 01 11 00 Page 3 area and can be avoided.

d. Materials and equipment shall be stored and protected as recommended by the manufacturer or required by applicable codes and standards, to guarantee preservation of quality, appearance, and suitability for the Project. They shall be stored to facilitate inspection by the Contracting Officer.

e. The Government will provide the lands, easements, and rights-of-way, or other right-to-enter and work on lands shown on the Plans. Nothing herein contained and nothing marked on the Plans, shall be interpreted as giving the Contractor exclusive occupancy of the lands, easements, or rights-of-way provided by the Government.

f. The work areas and the areas for the Contractor's use are shown on the Plans.

g. The Contractor shall be responsible for restoring, at its own expense, all disturbed storage and work areas to a condition similar to those existing prior to construction, except where other surfacing or treatment is required by the Plans or Specifications.

1.8 WORK TO BE PERFORMED BY THE CONTRACTOR

Construction of the Project consists, in general, of the following activities:

a. Performing mobilization, demobilization, and Contract administration.

b. Performing erosion and sediment control and storm water pollution prevention, and complying with all environmental controls and requirements related to the Contractor's operations as specified in the Contract Documents, in Project licenses and permits obtained by the Government, and as specified elsewhere in the Specifications.

c. Performing construction surveying and construction quality control.

d. Providing all required equipment, personnel, and materials to construct the Project as required by the Plans and Specifications, and to complete the Project in accordance with the Contract schedule.

e. Providing all required temporary facilities, utilities, and offices required to complete the work.

f. Providing water for construction from available sources, including pumping, piping, hauling, and storage that may be required, and paying all fees and costs associated with developing the water supply, including pumping energy costs.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 00 Page 4

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

08/15

PART 1 GENERAL

1.1 SUBMITTALS

1.2 SINGLE JOB PAYMENT ITEMS

1.2.1 Mobilization and Demobilization

1.2.1.1 Payment

1.2.1.2 Unit of Measure

1.2.2 SWPPP Design and Implementation

1.2.2.1 Payment

1.2.2.2 Unit of Measure

1.2.3 Temporary Fencing, Signage, and Traffic Control

1.2.3.1 Payment

1.2.3.2 Unit of Measure

1.2.4 Demolition

1.2.4.1 Payment

1.3 UNIT PRICE PAYMENT ITEMS

1.3.1 Ditch Removal

1.3.1.1 Payment

1.3.1.2 Measurement

1.3.1.3 Unit of Measure

1.3.2 Clearing and Grubbing

1.3.2.1 Payment

1.3.2.2 Measurement

1.3.2.3 Unit of Measure

1.3.3 Stripping

1.3.3.1 Payment

1.3.3.2 Measurement

1.3.3.3 Unit of Measure

1.3.4 Excavation

1.3.4.1 Payment

1.3.4.2 Measurement

1.3.4.3 Unit of Measure

1.3.5 Levee Fill

1.3.5.1 Payment

1.3.5.2 Measurement

1.3.5.3 Unit of Measure

1.3.6 Hydroseeding

1.3.6.1 Payment

1.3.6.2 Measurement

1.3.6.3 Unit of Measure

1.3.7 Aggregate Surfacing

1.3.7.1 Payment

1.3.7.2 Measurement

1.3.7.3 Unit of Measure

PART 2 PRODUCTS

SECTION 01 22 00 Page 1

PART 3 EXECUTION

3.1 CONTRACT COST BREAKDOWN

3.2 INVOICE SUBMISSION PROCEDURES

3.2.1 Required Procedure

3.2.2 Required Documents

SECTION 01 22 00 Page 2

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Contract Cost Breakdown

1.2 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE included at the beginning of these Specifications and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.2.1 Mobilization and Demobilization

1.2.1.1 Payment

Measurement and payment for mobilization, demobilization, staging areas, temporary construction facilities, and for all other work covered by the Project Specifications, as defined in Section 01 71 10 MOBILIZATION AND DEMOBILIZATION, shall be made at the Contract job price for item "MOBILIZATION AND DEMOBILIZATION"; which payment shall constitute full compensation for all the Work involved in mobilization and demobilization as shown or specified in the Contract documents, and directed by the Contracting Officer, including preparation of staging areas, improvements to existing ramps for construction access, and restoration of access roads and staging areas. Mobilization and Demobilization shall be cost loaded 40 percent mobilization and 60 percent demobilization. Final As-Built Drawings shall be cost loaded one half of one percent of the awarded contract as a portion of the demobilization amount.

1.2.1.2 Unit of Measure

Unit of measure: job.

SECTION 01 22 00 Page 3

1.2.2 SWPPP Design and Implementation

1.2.2.1 Payment

Payment will be made for costs associated with SWPPP design and implementation as defined in Section 01 57 23 TEMPORARY STORMWATER POLLUTION CONTROL as shown on the Plans, and as directed by the Contracting Officer at the contract lump sum price for item "SWPPP DESIGN AND IMPLEMENTATION". Payment shall constitute full compensation for all work involved in storm water pollution control including installation and removal of best management practices for erosion control, spill control, monitoring, providing updates to the SWPPP, rain event action plan, and record keeping as required by law, as shown in the Contract documents.

Payment will not include permanent erosion control and seeding as specified under Section 32 92 33 GRASS SEEDING AND EROISION CONTROL, which is covered by bid item "Hydroseeding.”

1.2.2.2 Unit of Measure

Unit of measure: job.

1.2.3 Temporary Fencing, Signage, and Traffic Control

1.2.3.1 Payment

Payment will be made for costs associated with the preparation and implementation of the traffic control plan as defined in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS at the contract lump sum price for item "TEMPORARY FENCING, SIGNAGE, AND TRAFFIC CONTROL". Payment shall constitute full compensation for all work involved in the protection of traffic along haul routes and at access points as required by local, state and federal regulations, including all barriers, lights, signals, detours, and other ancillary requirements.

1.2.3.2 Unit of Measure

Unit of measure: job.

1.2.4 Demolition

1.2.4.1 Payment

Payment will be made for the costs associated with demolition of existing irrigation features. All costs associated therewith must be included in the bid item “DEMOLITION”; which payment must constitute full payment for all the Work involved in demolition, hauling, and disposal as shown or specified in the Contract documents.

Unit of Measure

Unit of Measure: job

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, SECTION 01 22 00 Page 4 environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.3.1 Ditch Removal

1.3.1.1 Payment

Payment will be made for ditch removal as shown on the Plans at the contract unit price for "DITCH REMOVAL", which will be payment in full for furnishing all supplies, labor, equipment, materials and for performing all operations necessary for removal of the existing concrete lining and over-excavation of the ditch as shown on the Plans, including excavation, haul, and disposal at an approved waste facility, including fees.

1.3.1.2 Measurement

Ditch removal and related work shall be measured by the linear foot removed as shown on the Plans and directed by the Contracting Officer as verified in the field.

1.3.1.3 Unit of Measure

Unit of measure: linear feet.

1.3.2 Clearing and Grubbing

1.3.2.1 Payment

Clearing and grubbing, and the disposal of the materials from this operation and for all other related work as defined in Section 31 11 00 CLEARING, GRUBBING, AND STRIPPING, shall be paid at the contract unit price for "CLEARING AND GRUBBING". This price shall constitute full compensation for furnishing all labor, materials, equipment and incidentals, and doing all work necessary to complete the clearing and grubbing including removal of rocks, debris, existing aggregate surfacing, and all other deleterious items as noted on or specified in the Contract documents and as directed by the Contracting Officer, including disposal or salvage of materials, and restoring all ground surfaces including filling of holes that result from grubbing operations.

1.3.2.2 Measurement

Clearing and grubbing shall be measured for payment to the nearest 0.1 acre based upon horizontal area surveys.

1.3.2.3 Unit of Measure

Unit of measure: acre.

1.3.3 Stripping

1.3.3.1 Payment

Payment for stripping of the setback levee and berm footprint as defined in Section 31 11 00 CLEARING, GRUBBING, AND STRIPPING will be made at the Contract bid price for "STRIPPING". This price shall constitute full compensation for all equipment, labor, materials and incidentals necessary to complete the work as shown or specified in the Contract documents, or as directed by the Contracting Officer. Payment shall constitute full

SECTION 01 22 00 Page 5 compensation for stripping, stockpiling, transportation, loading, unloading, and placement as described in the Contract Documents.

1.3.3.2 Measurement

Stripping shall be measured for payment to the nearest cubic yard. The basis for measurement will be surveys taken after clearing and grubbing operations and after stripping operations to the depths shown on the Plans or directed by the Contracting Officer. Survey cross sections shall be performed at significant breaks in grade except that the maximum distance between cross sections shall not exceed 100 feet.

1.3.3.3 Unit of Measure

Unit of measure: cubic yard.

1.3.4 Excavation

1.3.4.1 Payment

Payment for excavation as defined on the Plans and in Section 31 00 00 EARTHWORK will be paid at the Contract bid price for "EXCAVATION". This price shall constitute full compensation for all equipment, labor, materials, and all incidentals necessary to complete the work as shown or specified in the Contract documents, or as directed by the Contracting Officer, including excavation of the existing levee and setback levee foundation, excavation of the inspection trench, and hauling to staging or stockpile areas for reuse (provided the materials meet the requirements of the Specifications) or hauling placing, and compacting materials to the stockpile locations shown on the Plans. Excavation shall also include the placement of Geotextile beneath stockpiled materials in accordance with the Contract Documents.

1.3.4.2 Measurement

Excavation will be measured for payment by the cubic yard and quantities will be determined by the average end area method. The basis for measurement will be surveys taken after stripping, clearing and grubbing operations and after levee and foundation excavation to within the specified tolerance. Survey cross sections shall be performed at significant breaks in grade except that the maximum distance between cross sections shall not exceed 100 feet. Excavation in excess of the design grades as indicated on the Plans, including allowable tolerance, will not be accepted.

1.3.4.3 Unit of Measure

Unit of measure: cubic yard.

1.3.5 Levee Fill

1.3.5.1 Payment

Payment will be made for Levee Fill placed as defined on the Plans and in Section 31 00 00 EARTHWORK, or as directed by the Contracting Officer at the Contract bid price for "LEVEE FILL". Payment shall constitute full compensation for furnishing all plant, labor, equipment, materials, and performing all operations necessary for foundation preparation, hauling material from staging areas, borrow areas or stockpiles, blending, placing

SECTION 01 22 00 Page 6 and compacting the material, materials testing, surveying, and moisture control.

1.3.5.2 Measurement

Material specified for Levee Fill shall be measured for payment by the cubic yard, in place, and quantities will be determined by the average end area method to the nearest cubic yard. The basis for measurement will be surveys of the areas to be filled taken after foundation and levee excavation and after embankment construction to the specified tolerances and before placement of topsoil or aggregate surfacing. Cross sections shall be performed at significant breaks in grade except that the maximum distance between cross sections shall not exceed 100 feet. Embankments not constructed to design grade and sections constructed above the allowable tolerance will not be accepted.

1.3.5.3 Unit of Measure

Unit of measure: cubic yard.

1.3.6 Hydroseeding

1.3.6.1 Payment

Hydroseeding as defined in Section 32 92 19 SEEDING will be paid for at the contract unit price under Bid Item "HYDROSEEDING". Payment shall constitute full compensation for furnishing all plant, labor, equipment, materials, and performing all operations necessary for hydroseeding the completed levee and berm slopes as shown on the Contract Documents.

1.3.6.2 Measurement

Hydroseeding will be measured for payment to the nearest 0.1 acre by horizontal area survey.

1.3.6.3 Unit of Measure

Unit of measure: acre.

1.3.7 Aggregate Surfacing

1.3.7.1 Payment

Aggregate surfacing as defined in Section 32 15 00 AGGREGATE SURFACING will be paid for at the contract unit price under Bid Item "AGGREGATE SURFACING". Payment will constitute full compensation for the construction and completion of the work, including material, subgrade preparation, and furnishing all labor and incidentals necessary to complete the work as defined in the Contract Documents.

1.3.7.2 Measurement

Aggregate surfacing will be measured for payment to the nearest 0.1 ton.

Quantities for payment will be certified by individual truck weight tickets delivered to the Project Site at the time of delivery of each truckload of material. Moisture content not exceeding six percent by weight will be acceptable in determining payment quantities. Deductions will be made from the certified weight for moisture in excess of this amount and for materials in excess of the allowable thickness.

SECTION 01 22 00 Page 7

1.3.7.3 Unit of Measure

Unit of measure: ton.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 CONTRACT COST BREAKDOWN

The Contractor must furnish within 15 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This contract cost breakdown will then be utilized as the basis for progress payments to the Contract.

3.2 INVOICE SUBMISSION PROCEDURES

References include USACE QMS, FAR 52.232-5, Payments under Fixed-Price Construction Contracts, and FAR 52.232-27, Prompt Payment for Construction Contracts.

3.2.1 Required Procedure

a. The payment request process must begin with the scheduling meeting.

Section 01 32 01 PROJECT SCHEDULE states: "Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment." The QA Representative or Project Engineer will meet with the Contractor each month and mutually agree to the quantities and lump sum percentages to be invoiced prior to the Contractor's official invoice being submitted to the Administrating Office.

b. The Contractor shall print a copy of the Contractor's Pay Request Form from RMS to record the mutually agreed upon quantities and percentages. NOTE: Contractor earnings shall not be projected. This form shall be signed and dated by the QA Representative and the Contractor. Consideration will be given to safety, submittals, Contractor Quality Control (CQC), acceptable work, as well as overall progress. In the case of deficient work, withholding the cost of removal and reconstruction shall be considered.

c. Contractor must submit a preliminary payment request worksheet to the Quality Assurance (QA) Representative. This document is printed from RMS, which lists not only the pay activities for which payment is requested, but also lists any Contractor action items e.g. outstanding submittals, payrolls, quality control items, etc. Contractor must submit documentation, surveys, concrete calculations, and weight tickets for tonnage items.

d. QA Representative will meet with the Contractor to determine if the preliminary pay request and corresponding back-up is acceptable. The

SECTION 01 22 00 Page 8

QA Representative shall enter the approved percentages or quantities on the preliminary pay request worksheet, ensuring that consideration has been made to all Contractor action items that have not been completed or corrected. Both parties will sign and date the last page.

e. Contractor must submit the formal pay request package to the Administrating Office (original) and the QA Representative (copy), incorporating any changes made on the preliminary pay request on or before the 10th of the month. Contractor must also enter the pay request into RMS.

3.2.2 Required Documents

Pay request packages from Contractors must include the following documents:

a. Prompt Payment Certification and Requested Earnings printed from RMS and wet signed.

b. Preliminary payment request worksheet, signed and dated by both parties.

c. Required documentation includes surveys (PDF and CAD), cross-sections, QC test results, and weight tickets.

d. Updated approved schedule (progress chart or NAS with narrative report as specified).

e. Safety Exposure Report (hard copy not required, will be verified in

RMS).

f. Current Submittal Register (hard copy not required, will be verified in RMS).

g. Current QC Test Log (hard copy provided and all tests entered in RMS).

h. Certified Payrolls (prime and subs at all tiers) entered in RMS and submitted to the Administrating Office.

If the progress payment request is missing any of the above items or imports into RMS, the Administrating Office will notify the Contractor within 7 days and suspend the processing of the progress payment until the missing information has been received. The invoice will not be considered acceptable until a complete pay request package has been submitted and imports performed. Upon receipt of an acceptable invoice, the invoice is stamped 'RECEIVED'. In accordance with FAR 52.232-27 Prompt Payment for Construction Contracts, the due date for making payment is 14 days after the designated billing office receives a proper complete payment request.

SECTION 01 22 00 Page 9

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

2.1.2.1 Primavera

2.1.2.2 Other Than Primavera

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 BASIS FOR PAYMENT AND COST LOADING

3.2.1 Activity Cost Loading

3.2.2 Withholdings / Payment Rejection

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

3.3.2 Activity Durations

3.3.3 Procurement Activities

3.3.4 Mandatory Tasks

3.3.5 Government Activities

3.3.6 Standard Activity Coding Dictionary

3.3.6.1 Workers Per Day (WRKP)

3.3.6.2 Responsible Party Coding (RESP)

3.3.6.3 Area of Work Coding (AREA)

3.3.6.4 Modification Number (MODF)

3.3.6.5 Bid Item Coding (BIDI)

3.3.6.6 Phase of Work Coding (PHAS)

3.3.6.7 Category of Work Coding (CATW)

3.3.6.8 Feature of Work Coding (FOW)

3.3.7 Contract Milestones and Constraints

3.3.7.1 Project Start Date Milestone and Constraint

3.3.7.2 End Project Finish Milestone and Constraint

3.3.7.3 Interim Completion Dates and Constraints

3.3.7.3.1 Start Phase

3.3.7.3.2 End Phase

3.3.8 Calendars

3.3.9 Open Ended Logic

3.3.10 Default Progress Data Disallowed

3.3.11 Out-of-Sequence Progress

3.3.12 Added and Deleted Activities

SECTION 01 32 01 Page 1

3.3.13 Original Durations

3.3.14 Leads, Lags, and Start to Finish Relationships

3.3.15 Retained Logic

3.3.16 Percent Complete

3.3.17 Remaining Duration

3.3.18 Cost Loading of Closeout Activities

3.3.18.1 As-Built Drawings

3.3.19 Early Completion Schedule and the Right to Finish Early

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Preliminary Project Schedule Submission

3.4.2 Initial Project Schedule Submission

3.4.3 Periodic Schedule Updates

3.5 SUBMISSION REQUIREMENTS

3.5.1 Data CD/DVDs

3.5.2 Narrative Report

3.5.3 Schedule Reports

3.5.3.1 Activity Report

3.5.3.2 Logic Report

3.5.3.3 Total Float Report

3.5.3.4 Earnings Report by CLIN

3.5.3.5 Schedule Log

3.5.4 Network Diagram

3.5.4.1 Continuous Flow

3.5.4.2 Project Milestone Dates

3.5.4.3 Critical Path

3.5.4.4 Banding

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

3.6 PERIODIC SCHEDULE UPDATE

3.6.1 Periodic Schedule Update Meetings

3.6.2 Update Submission Following Progress Meeting

3.7 WEEKLY PROGRESS MEETINGS

3.8 REQUESTS FOR TIME EXTENSIONS

3.8.1 Justification of Delay

3.8.2 Time Impact Analysis (Prospective Analysis)

3.8.3 Forensic Schedule Analysis (Retrospective Analysis)

3.8.4 Fragmentary Network (Fragnet)

3.8.5 Time Extension

3.8.6 Impact to Early Completion Schedule

3.9 FAILURE TO ACHIEVE PROGRESS

3.9.1 Artificially Improving Progress

3.9.2 Failure to Perform

3.9.3 Recovery Schedule

3.10 OWNERSHIP OF FLOAT

3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS

SECTION 01 32 01 Page 2

SECTION 01 32 01

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this Specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Preliminary Project Schedule; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required…