Attachment 2_SOW Replace Compressor.pdf

PDF 148 KB Posted

Attached to
Main Air Compressor Replacement, Wyndmoor, PA Federal contract opportunity
Solicitation number
1232SA25Q0654
Issued by
Department of Agriculture Agricultural Research Service

About this file

This Statement of Work (SOW) details a project for the USDA Eastern Regional Research Center (ERRC) in Wyndmoor, PA to upgrade and modernize its main high-pressure air compressor. The contractor is required to remove the existing antiquated air compressor and replace it with a specific Gardner Denver Electra Saver II G2 Oil-Flooded Rotary Air Compressor (Model # STG2-40) or equivalent, with detailed technical specifications including a 40HP motor, 192 CFM output at 125 PSIG, 460V power, and water-cooled heat exchanger. Additional tasks include providing installation materials, completing discharge and piping tie-ins, connecting to existing electrical systems, testing the unit, and providing onsite owner training. The contractor must notify the USDA ARS area office representative upon work completion and before invoicing.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

USDA, ERRC Main Air Compressor Replacement

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Deliverables / Schedule

Project USDA, Eastern Regional Research Center, Wyndmoor, PA Pathogen Lab Air Handling Unit Corrective Work

General Information

1.0 Scope of Work

ERRC Upgrade and modernize main HP Air Compressor.

2.0 Background

The Eastern Regional Research Center (ERRC) is one of four Regional Research Centers of the Agricultural Research Service, U.S. Department of Agriculture. The ERRC is home to the nation’s leading scientists and engineers who solve problems facing the U.S. today and tomorrow with fundamental, applied, and developmental research on agricultural commodities. Most of this research is conducted in the main building within two laboratory wings. The original building was constructed in 1940. Due to continuous upgrades and renovations, ERRC is very modern with respect to laboratory design and system condition.

Contractor Requirements

3.0 Technical Requirements / Tasks

1. Remove an antiquated air compressor and properly dispose.

2. Supply and install the new compressor in the same area. The new compressor must be one (1) Gardner

Denver Electra Saver II G2 Oil-Flooded Rotary Air Compressor, Model # STG2-40 (Fixed Speed) or an equal item with the following salient characteristics:

• at least 40HP (30kW)

• at least 192 CFM @ 125 PSIG

• 460V/3PH/ 60Hz (Less Enclosure)

• Water-Cooled Heat Exchanger

• Wye-Delta Reduced Volt Start

• With Starter

• ODP High Efficiency Motor

• Full Synthetic oil with at least 8000 Hours lifetime comparable to the AEON 9000SP 8000 Hour Lube STD

• 80°C (176°F) Mixing Valve Temp (with Water Temp Regulator, Water Shutoff Valve, and Moisture Separator)

3. Provide material needed for installation tie in / cut over.

4. Complete discharge, cooling water and condensate piping tie-in to new unit.

5. Tie new air compressor into existing electrical.

6. Verify all hook ups and test unit for proper operation.

7. Provide onsite owner training for the new equipment and warranty registration.

4.0 Deliverables / Schedule

1. The Contractor shall notify the USDA ARS area office representative when work is complete and before invoicing.

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Deliverables / Schedule
1. The Contractor shall notify the USDA ARS area office representative when work is complete and before invoicing.