Attachment 2 - Schedule of Items - Lava Fire Fence Project.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
Lava Fire Rangeland Fence Reconstruction
Solicitation number
1240LT26Q0030
Issued by

About this file

This file is a Schedule of Items pricing template formatted as an Independent Government Estimate (IGE) for the Lava Fire Rangeland Fence Rebuild Project on the Council Ranger District of the Payette National Forest in Council, Idaho. The template provides instructions for completing an IGE, which must be an independent estimate used to determine procurement value, identify applicable thresholds, and evaluate contractor pricing reasonableness against government requirements.

The project scope involves the removal and reconstruction of 3.5 miles of segmented interior Forest Service fence and Forest Service/BLM boundary fences across seven distinct fence segments. The work includes removal of all old fence material, clearing of vegetation and large woody debris, and construction of permanent four-strand barbed wire livestock fence with let-down capability. The schedule of items identifies fence removal and reconstruction as line item 0001, measured in miles with a quantity of 3.5 miles, with pricing to be provided on a firm fixed-price basis. The template is formatted to accept unit price and total price entries, though specific pricing values are not filled in on this version of the document.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

INSTRUCTIONS: HOW TO USE THIS FORM

Independent Government Estimate (IGE)
No specific format is required for an IGE; however this must be an independent estimate and not a reiteration of a contractor quote. The selected format should generally be in the same level of detail and manner that the Schedule of Items pricing we request from contractors. The estimate should state any underlying assumptions or rationale used in formulating the estimate. Initially the CO will use the IGE to determine the estimated value of the procurement and to identify the appropriate procurement thresholds applicable to the solicitation. Later the IGE is compared to prices received to evaluate an offeror’s understanding of the government requirements and in supporting a price reasonableness determination.

EXPLANATION OF TABS

Stand Alone IGE:Use if the below do not apply to your requirement.
Stand Alone IGE w/options:Use if you have a requirement where you know you have an ongoing/recurring need year after year.
IDIQ:Use if you have a need that is reoccurring or multi-year requirement.
Task Order:Use if you want to issue a order against an existing contract or agreement.

CONTRACT (NO OPTIONS)

FILL OUT THE AREAS IN RED BELOW
SCHEDULE OF ITEMS

(NAME) DISTRICT/FOREST/STATION/ACTIVITY

PROJECT TITLE: (NAME) WORKPLAN ACQUISITION PLAN/REQUISITION NO: (NUMBER)

Period of Performance (Required for Services and A&E)Start Date - End date
Anticipated Delivery Date (Required for Supply and Construction)Delivery Date
SCHEDULE OF ITEMS
ITEM
NUMBERDESCRIPTIONPAY UNITEST QTY
0001
0002
0003
0004
0005
0006
EA - EACH

MO - MONTH Award anticipated to be a firm fixed price contract.

CONTRACT (WITH OPTION YRS)

SCHEDULE OF ITEMS

Council Ranger District/Payette National Forest/Council, Idaho PROJECT TITLE: Lava Fire Rangeland Fence Rebuild Project

SCHEDULE OF ITEMS
ITEM
NUMBERDESCRIPTIONUnit of MeasureQuantityUnit PriceTotal
0001Fence Removal/Reconstruction of permanent, 4-wire, let down, livestock fence.Miles3.5
Total Price =$