Attachment 2 - Schedule of Items 4.8.2026.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Northern Hills Ranger District Parking Lot Reconstruction, Spearfish, South Dakota
Solicitation number
1240LT26Q0053
Issued by

About this file

This is a Schedule of Items pricing template for the Northern Hills Ranger District Parking Lot Reconstruction project in Spearfish, South Dakota. The template is structured as a line-item bid sheet for CLIN 0001 (Base Items) and requires vendors to provide unit pricing for nine distinct work categories. The work items include mobilization (lump sum), earth moving (6,520 cubic yards), imported material (3,275 cubic yards), excess material removal (6,520 cubic yards), base preparation (47,315 square feet), asphalt paving (16,520 square feet), concrete paving (30,795 square feet), site improvements (lump sum), and demolition (lump sum). All pricing must be rounded to the nearest whole dollar with no cents included, and the total of individual line items must equal the CLIN total.

This pricing template is part of Request for Quotation (RFQ) 1240LT26Q0053 issued by the Department of Agriculture Forest Service for reconstruction of a parking lot with structural, grade, and drainage deficiencies. The project involves proper base material installation, site regrading, drainage improvements, sidewalk and walking area additions, accessible parking enhancements, and site lighting improvements. The solicitation uses commercial item procedures under FAR Part 12, with a mandatory site visit scheduled for May 6, 2026, at 1:00 PM MST. The project is classified under PSC Code YlLZ (Construction of Parking Facilities) and NAICS Code 237310 (Highway, Street, and Bridge Construction), with an estimated project magnitude between $1,000,000 and $5,000,000 and a small business size standard of $45 million.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOI

BLACK HILLS NATIONAL FOREST NORTHERN HILLS RANGER DISTRICT PARKING LOT REPLACEMENT Schedule of Items

Vendor Name:
UEI:
Item
No.DescriptionMethod of
MeasurementUnitsQuantityUnit
PriceTotal
CLIN 0001

BASE ITEMS

1MobilizationLump SumLump Sum1$0.00$0.00
2Earth MovingQuantityCubic Yards6520$0.00$0.00
3Imported MaterialQuantityCubic Yards3275$0.00$0.00
4Excess MaterialQuantityCubic Yards6520$0.00$0.00
5BaseQuantitySquare Feet47315$0.00$0.00
6Asphalt PavingQuantitySquare Feet16520$0.00$0.00
7Concrete PavingQuantitySquare Feet30795$0.00$0.00
8Site ImprovementsLump SumLump Sum1$0.00$0.00
9DemolitionLump SumLump Sum1$0.00$0.00
TOTAL CLIN 0001 BASE ITEMS$0.00
NOTES:
All individual line-item pricing provided shall be rounded up to the nearest whole dollar, do not include cents, the total pricing should equate to the individual line-item amounts.

File details come from the government source that posted it. Updated .