Attachment 1 - Statement of Work _3.27.2026.pdf
PDF 162 KB Posted
- Solicitation number
- 1240LT26Q0053
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the Northern Hills Ranger District Parking Lot Reconstruction project issued by the U.S. Department of Agriculture Forest Service for the Black Hills National Forest.
The project involves complete reconstruction of the parking lot located at 2014 North Main Street, Spearfish, South Dakota, to address structural deficiencies, inadequate drainage, and safety concerns. The contractor must provide all labor, materials, equipment, testing, and documentation required for the work. Specific tasks include removal of existing asphalt and concrete pavement, fencing, and lighting; site grading; placement of aggregate base materials; installation of new concrete and asphalt paving; and installation of new fencing and lighting. The contractor must demonstrate experience in campground construction, general contracting, and road construction, with strong communication skills for coordinating with clients, subcontractors, and stakeholders. Detailed Contract Specifications and Construction Plans are provided separately with the solicitation.
Key deliverables include an Accident Prevention Plan (due 10 days prior to work), Action and Informational Submittals (before beginning work on individual items), a Construction Schedule (monthly updates via email to the Contracting Officer Representative), and an Operation and Maintenance Manual (within 30 days of receiving review comments). The contractor must provide an onsite superintendent and company executive contact information. All travel costs to the project site must be included in the contractor's quote with no separate reimbursement. All electronic deliverables must be Section 508 compliant, and all data, reports, and documentation generated become property of the U.S. Government. The contractor is responsible for installing and maintaining security barriers to protect the public, employees, facilities, and surrounding property.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
United States Department of Agriculture
Forest Service
Black Hills National Forest
Northern Hills Ranger District Parking Lot Reconstruction
Statement of Work
March 27, 2026
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards Attachment.......................................................................................................... Error! Bookmark not defined.
Project Northern Hills Ranger District Parking Lot Reconstruction
General Information
1.0 Scope of Work
The project covers the reconstruction of the Northern Hills Ranger District parking lot to fix structural, grade, and drainage problems. The contractor shall provide all labor, materials, equipment, testing, and documentation necessary to remove fence, lighting and existing surfacing. Provide new grade, surfacing fencing and lighting.
2.0 Background
Reconstruction of the Northern Hills Ranger District parking lot to fix structural, grade, and drainage problems.
To ensure public health and safety and increase public access, The parking lot is poorly constructed with inadequate sub-base and little base gravel. Soil under gravel is clay-rich and holds water, causing settling, cracking, water infiltration, freeze/thaw breakup and heaving. Over 65% of Parking Lot has alligator cracking.
Project will reconstruction parking lot with proper base materials, regrade site and add drainage, add sidewalks and designated walking areas, improve accessible parking, and improve site lighting for safety.
Location: Northern Hills Ranger District Parking Lot Reconstruction, 2014 North Main Street Spearfish, South Dakota, 57783
Contractor Requirements
3.0 Technical Requirements / Tasks
Contractors should demonstrate a thorough understanding of the project requirements and attention to detail is crucial for quality construction. Strong communication skills are essential for coordinating with clients, subcontractors and other stakeholders. Experience in campground construction, general contracting, and road construction is beneficial. Contractors should have the capacity to handle the specific project requirements and deliver within the specified timeline.
A full copy of the Contract Specifications can be found with this solicitation.
A full copy of the Contract Construction Plans can be found with this solicitation.
Work shall include but not limited to:
Removal of asphalt and concrete pavement Removal of fencing and lighting Grading Placement of aggregate base Concrete Paving Asphalt Paving Fencing Lighting
4.0 Government Furnished
There are no Government Furnished Materials associated with this project.
5.0 Deliverables / Schedule
Key Deliverables Item No.
Deliverable / Item Title Description Frequency Reference
Delivery Format Due By
Accident Prevention Plan
Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project
Once Specifications General Requirements 2.2.A-E
Via email to
COR
10 days prior to on-site work beginning
Action Submittals
Written and graphic information that requires Contracting Officer’s(CO's) responsive action.
Prepare and submit Action Submittals required by individual Specification Sections.
Specifications General Requirements 3.4
Submit four copies of each submittal, unless otherwise indicated.
Before beginning work on individual item
Informational Submittals
Prepare and submit Informational Submittals required by other Specification Sections.
Prepare and submit Action Submittals required by individual Specification Sections.
Specifications General Requirements 3.5
Submit two copies of each submittal, unless otherwise indicated.
Before beginning work on individual item
Contractor's Construction Schedule
Provide a construction schedule that incorporates the full contract period.
With each Progress Payment request
Specifications General Requirements 3.6
Via email to
COR
10 days prior to on-site work beginning.
Monthly interval
Operation and Maintenance Manual furnish two complete sets of operation and maintenance (O&M) data
Before scheduling a final inspection
Specifications General Requirements 6.2
Digital file Via email to
COR
Within 30 days following receipt of review comments
6.0 Travel
Travel to the Northern Hill Ranger district site is required for the reconstruction of the parking lot. All travel costs shall be included in the contractor’s quote. No separate reimbursement will be provided.
7.0 Contractor’s Key Personnel
The Contractor is to provide name, position title and contact information of company executive responsible for the project. Contractor is to always provide an onsite superintendent.
8.0 Security Requirements
The Contractor is to install and maintain suitable barriers to ensure the protection of the public, employees, and facilities. Protect persons, motor vehicles, surrounding buildings, plants, and surrounding surfaces or buildings from harm resulting from Contractor’s work.
9.0 Data Rights
All data, reports, test results, and documentation generated under this contract become the property of the U.S.
Government.
10.0 Section 508 – Electronic and Information Technology Standards All electronic deliverables shall be Section 508 compliant, including readable PDFs and accessible text formats.
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |