Attachment_2_Performance_Specifications.pdf
PDF 880 KB Posted
- Attached to
- San Luis NWRC PV System Federal contract opportunity
- Solicitation number
- 140F0322R0003
About this file
This document outlines a request for proposal from the U.S. Fish and Wildlife Service for the design and construction of ground-mounted photovoltaic systems at two locations near Los Banos, California. The scope of work includes installing 213 kW and 130 kW solar PV arrays to power wells and reduce electricity consumption at the sites. A two-phase selection process will be used, with the first phase evaluating past experience and performance, and the second phase evaluating technical approaches. Phase I proposals are due April 6, 2022, and the performance period is expected to be 365 days. The contract value is estimated between $500,000 and $1,000,000. This acquisition is set aside for small businesses only. Interested parties must be registered in the System for Award Management to be considered for award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_1_Design_Build_Project_Scope.pdf | ||
| Attachment_3_DB_General_Engineering_Requirements.pdf | ||
| Attachment_7_Other_Solicitation_Documents.pdf | ||
| Attachment_6_Davis-Bacon_Wage_Determination.pdf | ||
| Attachment_4_Water_Pump_Specs.pdf | ||
| Sol_140F0322R0003.pdf | ||
| Attachment_5_Sno-Bird_Estimated_Energy_Usage_Deep_Well_Pumps.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SNO-BIRD PHOTOVOLTAIC SYSTEM
U.S. FISH & WILDLIFE SERVICE
SAN LUIS NATIONAL WILDLIFE REFUGE COMPLEX
LOS BANOS, CA
PERFORMANCE SPECIFICATIONS
Design and Construction, of Onsite Photovoltaic Systems
March 1, 2022
C.1 GENERAL DESCRIPTION OF THE WORK
C.1.1 The USFWS seeks to install two solar PV ballasted ground systems: one at the Sno-Bird location and the other at the Merced Shop Compound location. There are three electric utility meters located on the Sno-Bird site, one for each of the three deep well pumps, all located on the same parcel of land. The three pumps shall be served by the same ground mounted solar PV system located adjacent to the SNO DW 1 and connected to the Pacific Gas and Electric (PG&E) account #3699663240. The solar PV system will be physically connected to the PG&E electric meter serving SNO DW 1 and aggregated to the electric accounts serving SNO DW 3 (#3699663891) and SNO DW 5 (#3699663329) using PG&E’s Net Metering Aggregation (NEMA) program.
C.1.2 There is one electric utility meter located near the east boundary of the Refuge that serves both the P-17 and P-17B deep well pumps. The two deep well pumps shall be served by the same ground mounted solar PV system, and connected to (PG&E) account #8980941517. The solar PV system will be physically connected to the PG&E electric meter serving the Merced NWR Main Shop using PG&E’s NEMA program.
C.1.3 The Contractor shall design both PV systems to meet 100% of both site’s average annual electricity consumption. The Contractor shall reference Attachment 1 to assist in the design of the PV systems.
C.1.4 Under this Contract, the Contractor shall design, install, commission, warranty and interconnect, solar photovoltaic systems necessary to deliver a guaranteed minimum annual kWh. As described in Section 16, the Weather Corrected Performance Ratio shall be used to calculate system performance.
C.1.5 Due to concern with cultural resources below surface, the ground arrays shall be ballasted only with PV system power lines routed overhead to point of connection.
Contractor advised to bring in pre-cast ballast as water is generally unavailable on site for concrete work.
C.2 LOCATION OF THE WORK
The map below shows the proposed array location on the Merced Shop Compound site. The footprint area of the array is approximate and shown only for illustration.
C.3 INTERCONNECTION REQUIREMENTS
The Contractor is responsible for complying with all PG&E interconnection requirements, providing all necessary PV system details for the interconnection applications, and paying PG&E’s interconnection application deposit and any fees required by PG&E. If any further interconnection studies are required to be performed by or on behalf of PG&E, the Contractor shall notify the Contracting Officer. The Government will make arrangements to pay for such additional studies if required.
The Contractor is responsible for gaining approval from PG&E for interconnection and any PG&E-required upgrades. The Government will assist in facilitating communications with PG&E for this purpose. The PG&E interconnection agreements to connect the PV systems to the grid will be signed by the Government or Contractor as required by PG&E agreements. The Contractor shall provide interconnection agreements to the government at least 30 days in advance for legal review. Note that the Government is self-insured and requires that indemnity and termination clauses, among other things, are consistent with Government requirements and authority.
The Government has contacted PG&E, obtained a copy of the “Interconnection Agreement for Net Energy Metering (NEM2) of Solar or Wind Electric Generating Facilities of 1,000 Kilowatts or Less, Other than Facilities of 30 Kilowatts or Less”, and appended it in Attachment 3, which shall be used for this interconnection. Interconnection will be under PG&E GSA Areawide Contract # GS-00P-14-BSD-1137 in Attachment 4. The Contractor shall complete and submit PG&E’s Pre-Application Report Request in Attachment 5 to the utility. It is expected that the Contracting Officer will sign Exhibit D of the GSA Areawide Contract and submit it to PG&E with the approved interconnection agreement.
The Contractor shall submit an electric utility interconnection process plan to the Government within 14 days of contract award. The plan shall include key steps, timeline, interconnection details, and assumptions necessary to complete the interconnection process.
The Contractor shall be subject to and shall satisfy the interconnection requirements of PG&E. The Contractor shall provide any needed repair and upgrade to site electrical distribution equipment to meet interconnection requirements. The Contractor shall provide to PG&E if required: single line diagrams, engineering power flow studies, estimated energy production data estimates, catalog cuts, and other specifications and data with respect to the proposed new generating systems. Among other things, it is expected that PG&E will require a new production meter and disconnect.
Any local codes required by utility interconnection laws and regulations shall be followed, and the Contractor will be responsible for fees, permits, and inspections.
PG&E’s interconnection agreement language used for this project must be acceptable to the Government before the Contractor or the Government executes it. The draft interconnection agreement in Attachment 3 does not have final approval of the Government and is provided for information only.
The final interconnection agreement submitted to the utility must be accompanied by GSA Areawide Agreement Exhibit D in Attachment 5 signed by the Contracting Officer.
C.4 SITE CONDITIONS
Existing Feasibility Studies and Engineering Studies Done by Others Feasibility evaluations to determine the potential size of the solar PV systems have not been completed.
The proposed solar PV array locations shown in Section C.2 are for illustrative purposes only. The
Contractor is responsible for ascertaining relevant site conditions to determine project feasibility and to determine final system size according to the terms of this solicitation. If any drawings, specifications, existing engineering studies or facility conditions reports are provided through this solicitation by way of the site information package, the bidders and Contractor shall independently verify all information provided.
C.5 - ENGINEERING AND CONSTRUCTION
Coordination of Professional Services The Contractor shall be responsible for the professional quality, technical accuracy, and coordination of all investigations, evaluations, drawings, testing, cost estimating, submittals, written reports, construction, operations, and all deliverables, as required by this Scope of Work document or as required to complete the work of this contract.
Coordination of Sub-Contractors’ Credentials The Contractor shall ultimately be responsible for the completeness, accuracy, and coordination of all submittals but may delegate the preparation of submittals in whole or in part to sub-contractors or suppliers.
Modifications and Alterations of Government Property Modifications, alterations, and/or additions to existing facilities shall be designed and certified to satisfy applicable requirements of Section C.
Equipment Location
The Contractor shall use a minimum of a 100-year flood level as set by the United States Geological Services (USGS) when choosing the elevation of electrical equipment.
Components shall be located indoors whenever feasible, in ventilated (non-air conditioned) utility rooms and where space and codes allow. When inverters and major electrical components are located outdoors, they shall be protected from direct exposure to sunlight.
The Contractor shall coordinate with the Contracting Officer’s Representative (COR) regarding locations and appearance of all equipment, including PV modules, conduit, inverters, disconnect switches, wireways, and control and monitoring equipment. The COR must approve all locations prior to installation.
Site Management The Contractor shall procure a storm water permit and then install a storm water runoff collection system at the down gradient of the PV field to collect and safely channel collected rainwater to natural runoff channels to minimize erosion.
The Agency shall approve the gravel, fire control program, weed control program, and storm water runoff collection system.
Pollinator Friendly Ground Cover Plantings The Contractor shall coordinate with landscape company, retained separately by FWS to establish pollinator plantings in array fields. Coordination shall start during site assessments and early schematic planning.
Fixed Ground Arrays: Front and Back Piles - High Wind Zones The Contractor shall integrate high wind design guidance found in SEAOC PV-2 2017.
Wind Fencing The Contractor shall install wind-break fencing to manage high winds out of the North that could damage array. Contractor to install only purpose built wind-break fencing system at least 15’ from North edge of array and at least 5’ tall. Fence design shall be able to withstand 120 MPH wind gusts.
Contractor to submit during design phase, chosen wind fence product.
C.6 - PRODUCTS, MATERIAL, AND SERVICE REQUIREMENTS
Site Service Conditions Materials shall be designed to withstand the year-round temperatures and environmental conditions to which they are exposed to.
Same Manufacturer and Product Line Each major array component category (modules as one category, inverters as another, and electrical switchgear as a third) are to be new and of the same manufacturer and product line. For example, different brands of modules may not be mixed in one array, but it is acceptable to use a different brand of switchgear manufacturer from module and inverter manufacturers.
New Equipment The Government will not accept used, reconditioned, after-market, or grey-market products or equipment.
Corrosion Resistance All PV hardware and rack components shall be of corrosion-resistant material, such as stainless steel SAE grade 316. Aluminum and hot-dipped galvanized steel may be used for non-marine environments under ASTM A123 specifications. Fasteners shall be compliant with ASTM F2329.
Markings (Labeling) Strict conformance to system marking requirements of PV systems and their components are crucial for the safety of operators, service personnel, emergency responders, and others. The Contractor shall include general PV system labeling requirements, as per NEC 690 Ch. VI and specific requirements from Articles 690 and 705. The Contractor all required and desired labeling language in the design drawings for agency review.
Electrical equipment and components used in PV systems shall have markings that identify the manufacturer, size, type, ratings, hazard warnings, and other specifications. Equipment markings shall never be removed and shall be able to withstand the environmental conditions in which the equipment is installed (e.g., “UV rated” for outdoor labels). Markings must be visible or easily accessible during and after installation. The Contractor shall be responsible for all field-applied markings as required by local, state, and federal codes.
Minimum Transformer Efficiency Rating Any new transformer installed as part of the project shall be a “high-efficiency” transformer. Any such transformer shall comply with “NEMA Premium Efficiency” and be of amorphous steel core with bio-based oil.
Expected Service Life Unless noted otherwise, all materials furnished for the project shall have an expected service life of thirty (30) years or more, given the unique service conditions of each PV system site. Equipment warranties (modules, inverters, etc.) are shorter than the expected service life. With a 30-year system life, it is common and well understood by industry that inverters and a small percentage of failed modules would need to be replaced, though the system as a whole would provide at least 30 years of service. The Government shall seek the type of equipment and workmanship that can result in a 30-year system.
Locating Site Utilities The Contractor is responsible for locating all existing underground utilities prior to excavation and for utilizing the “Call Before You Dig” hotline to confirm with any potentially affected public utility company.
A notification of 72 hours in advance shall be given to the Government to locate the utilities belonging to the Government. If the Contractor fails to have these services performed, it will be the Contractor's responsibility to make temporary repairs to damaged underground utilities immediately, and permanent repair within 24 hours, at no expense to the Government. Any repairs made to the underground utilities by the Contractor shall be inspected by a Government representative before backfilling. Any damage done to existing underground utility systems are the sole responsibility of the Contractor.
Any site utility drawings provided by the Government, utility companies, municipal and county agencies, and prior Government contractors are for informational purposes only and are to be considered incomplete and inaccurate. The Contractor is responsible for confirming the exact location, depth, and type of underground utilities present.
Underground utilities that may be found traversing the proposed array areas might include but are not limited to: telecommunications trunks; cable TV lines; electrical distribution conductors; water mains;
oil, steam, propane, and natural gas lines; access and security camera systems; waste water and/or storm water drain pipes; traffic and/or street light power; and communications cabling.
C.7 – BATTERY STORAGE “READY” DESIGN
Under separate solicitation, FWS may install battery storage equipment to manage the costs of the new time-of-use tariffs. Contractor shall install a “battery ready” system by:
1. Identifying the point of electrical coupling for battery system. Service panels supplied shall have reserved battery breaker positions.
2. Electrical drawings shall show where future batteries are to be connected electrically.
3. Site plan drawings shall show location of future batteries. The Contractor shall also consider space-planning issues such as pad or wall space and spare conduit.
C.8 MODULE SAFETY, QUALITY & LONG-TERM PERFORMANCE
The Contractor shall select modules that are qualified based on:
Existing test lab results made public:
Some certified test labs share results publicly under pre-negotiated agreements with module manufacturers. These public lists of tested modules are not comprehensive but do provide a very convenient source of information on brands that have been tests.
One public source is the annual test results published by PV Evolution Labs (PVEL)1.
C.9 WIRE, CABLE AND CONDUIT MANAGEMENT
Direct Current (DC) Circuits: All interior and exterior DC conduits, raceways, enclosures, cable assemblies, and junction boxes associated with the PV system shall be marked to alert individuals that DC power is present. The marking shall be placed every ten (10) feet or fraction thereof, at turns and above and below penetrations, and on all DC combiner and junction boxes.
Wire Management: Under no circumstances shall plastic (non-metallic) cable-ties be used to secure and organize array wiring exterior to electrical enclosures. Wire cannot lie exposed directly on roof surface or ground. Long horizontal conduit runs shall have expansion unions every 30’ in order to reduce wire abrasion caused by fixed couplings. Couplings and expansion unions shall use anti-abrasion bushings. All wiring shall be attached to the system components by the use of strain reliefs or cable clamps, unless enclosed in conduit.
C.10 MINIMUM PERMANENT SIGNAGE AND LABELING
1. For ground mounted systems, signage shall contain the text “CAUTION PHOTOVOLTAIC SYSTEM”
2. Warning letters shall consist of letters having a principal stroke of not less than ¾ inch wide and be at least six (6) inches high on a contrasting background.
3. When serving utility, applicable codes and authorities having jurisdiction require additional or different signage – their requirements supersede above.
4. Print or engrave operating instructions and frame under glass or in approved laminated plastic.
Post instructions where directed. For operating instructions exposed to the weather, provide weather-resistant materials or weatherproof enclosures. Operating instructions shall not fade when exposed to sunlight and shall be secured to prevent easy removal or peeling.
C.11 PREVENTING VANDALISM AND THEFT
There is concern that the solar PV systems could be subjected to theft, vandalism, or intrusion by unauthorized personnel, the agency will establish criteria to the solicitation and final contract addressing these issues. In this event, the Contractor shall install the following security features at the site:
• Install standard 3-strand barbed wire fencing around both the Snobird array and the Shop Compound array. Fencing will be set back from the PV arrays by 15 to 20 feet to allow vehicle access between the fencing and the arrays.
1 https://www.pvel.com/pv-scorecard/ https://www.pvel.com/pv-scorecard/
• Note the North-side fence should be wind fencing, see section C.5 for specifications.
Motion activated alarms and lighting (commissioned to not react with animals)
• Security cameras
• Security padlocks on inverters, combiner boxes, and main electrical switches
• Anti-theft devices for copper cabling
C.12 STANDARDS FOR DRAWINGS
Drawing Submittal
Use
35% Schematic level 75% Full draft 95% Essentially complete drawings and specifications with only minor coordination and technical issues to be resolved.
100%- Construction Set
Complete drawing and specification packages suitable to issue for construction. Government to use to back-check to make sure all comments have been incorporated.
As-Built 100% set showing all changes that have occurred during construction.
Provide drawings for each discipline required (electrical, roofing, structural, etc.), with separate plans for new work and demolition as well as special types of drawings where necessary, such as enlarged plans, equipment curbing and flashing details, ground mounting and roof penetration details, etc. Detailed drawings shall be provided showing base and structural supports planned for supporting the PV arrays, i.e. footers, pylons, support, etc. Drawings shall clearly distinguish between new and existing work. Each drawing shall indicate project title, official FWS title block, project number, building name, building address, A/E firm, A/E's address and/or phone number, contract number, drawing title, drawing type, drawing number, and key plan. A cover sheet shall be provided and shall include a list of the drawings, legend, vicinity map, and location map in addition to all items required for each drawing.
Each A/E submission shall be clearly dated and labeled. Drawing sheet submitted shall include a graphic scale in the lower right-hand portion of the sheet. Restrictive markings must be affixed to all drawings in accordance with each agency’s document security policies. Drawings may not be copyrighted by the Contractor or Contractor’s designer. Provide drawings sent for comment in hard copy and pdf in quantities requested by the Contracting Officer. Final record drawings and as-builts shall be provided in hard copy, pdf and dwg format in quantities requested by the Contracting Officer. An FWS drawing title block will be provided by the Contracting Officer upon request.
C.13 SUBMITTALS AND SUBMITTAL REVIEW PROCESS – POST AWARD
After Contract award, during design development phases, the Government shall review and provide comments on drawing sets.
The Contractor shall respond to all Government review comments in writing, indicating one of the following:
1. Adoption and action taken,
2. Adoption with modifications and action taken,
3. Alternative resolution and action taken, or
4. Disagree.
In cases other than unqualified adoption, the Contractor shall provide a statement as to why the reviewer's comment is inappropriate. Disagreed items shall not go forward to the construction phase until adequate resolution to the disagreed item has been approved by the Contracting Officer. Design review comments shall not relieve the Contractor from compliance with all applicable codes and standards and the terms and conditions of this contract. Contractor's comment resolution shall be transmitted to Government within seven (7) calendar days of comment receipt and incorporate discussions from the scheduled design comment review meetings.
If the Contractor believes that any Government design comments or requested changes will result in a change in the contract cost, they shall notify the CO and COR within seven (7) calendar days of receiving the comment(s) and provide detail cost estimate of anticipated contract modifications.
Submittals shall be made to the COR and shall contain one (1) hard copy and one electronic copy saved to one (1) thumb drive containing copies of all submittals and materials. The Contractor shall combine all product data submission material into hard copy manuals for reference during all phases of construction. Shop drawings shall be bound with product data.
C.14 - SYSTEM STARTUP AND COMMISSIONING
After PG&E provides permission to operate (PTO) in parallel with the grid, the Contractor shall complete commissioning and acceptance testing, in accordance with agency safety plans, its own quality-control plan, manufacturer's recommendations, PG&E interconnection requirements, IEC 62446 Grid Connected Photovoltaic Systems Minimum Requirements for System Documentation, Commissioning Tests, and Inspection. The Contractor shall document all performance measurements.
The Contractor shall provide all work required for testing, start-up, and commissioning as prescribed by the following requirements.
1. Commissioning standard IEC 62446 shall be followed, and associated reports shall be included with the as-built submittal package. The as-built drawings shall also contain an AutoCAD dwg file for all drawings in addition to pdf files and hard copies.
2. Provide a North American Board of Certified Energy Practitioners (NABCEP) or International Test Association (NETA) certified engineer or technician to perform start-up and acceptance testing of the specified PV systems.
3. Complete a system commissioning per the Specification and equipment manufacturer’s written instructions.
4. Request and coordinate with the Utility and the Government representatives for acceptance and certification of the PV system and permission to operate.
5. Commissioning shall include the Contractor’s data acquisition system (DAS).
The Contractor shall notify the Government not less than ten (10) Business Days prior to the anticipated date of System Acceptance Testing. The Government shall have the right, but not the obligation, to be present at and observe the System Acceptance Testing, at the Government’s sole cost. The System Acceptance Testing shall be witnessed by the utility if required for interconnection approval, and the Contractor shall meet the utility’s test notification requirements. An FWS manager or representative may request to be present during any or all phases of the start-up and testing activities.
C.15 WARRANTIES
C.15.1 TOTAL ARRAY OUTPUT WARRANTY
The intent of this contract is to make both the Sno-Bird and Merced Shop Compound locations net zero electricity use (annual true-up) by the above-specified wells (SNO DW1, SNO DW3, and SNO DW5 at Sno-Bird; P17 and P17b at Merced Shop Compound). The PV system at the Sno-Bird location shall be approximately 213 KW and occupy an area of approximately 1.25 acres of ground space. We anticipate this will provide a minimum of 355,497 KWHs annually.
The PV system at the Merced Shop Compound location shall be approximately 130 KW and occupy an area of 0.75 acres of ground space. We anticipate this will provide a minimum of 216,970 KWHs annually.
The Contractor shall provide a system to achieve a Weather Corrected Performance Ratio of at least 0.9 over the warranty period of 5 years2. The ratio of actual to predicted performance is the “Performance Ratio” as described in IEC 61724 or ASTM E2848 – 13.
C.15.2 LINEAR MODULE WARRANTY
Modules used shall have a minimum of a 25-year performance warranty as measured using the linear module warranty methodology.
No module will be warranted to, or in actuality, generate less than 97% of its STC rated output in the first year of system operations. No module shall depreciate more than 0.9% for each year of the required minimum 25-year module warranty period.
The Contractor shall warrant both PV systems for a period of five years from Government acceptance.
C.16 PERSONNEL QUALIFICATIONS
C.16.1 NATIONAL ASSOCIATION OF BOARD-CERTIFIED CONTRACTORS (NABCEP) CERTIFIED
INSTALLERS
A NABCEP certified supervisory level site manager shall be onsite and managing all skilled or unskilled crews during the construction and startup and commissioning phases of system installation.
C.16.2 PROFESSIONAL ENGINEER AND LICENSED DESIGN PROFESSIONALS
2 http://www.nrel.gov/docs/fy13osti/57991.pdf http://www.nrel.gov/docs/fy13osti/57991.pdf
The Contractor shall comply with the requirements of the Utility if a Professional Engineer’s stamp is required. Engineers stamping designs for this project shall be licensed in the state of California.
C.16.3 PROJECT MANAGER
The Contractor shall assign a project manager with authority to represent the Contractor. The Contractor must have at least five years’ experience with project management of photovoltaic installations of similar scale and complexity.
C.16.4 REGISTRATION SEALS
Each submitted final design drawing, calculation document, and specification manual shall be signed and dated by, bear the seal of, and show the State Certificate Number of the Architect or Engineer who prepared the document and is responsible for its preparation.
C.17 PV SYSTEM MONITORING
A Government power meter, as specified by FWS, shall be furnished and installed by the Contractor in addition to any utility revenue or production meters. This meter shall be in addition to any metering capabilities provided by inverter or optimizer (if used) manufacturer.
This is a remote site power metering application. Remote network to be established under separate effort with specialized telecommunications firm. Contractor to work with telecommunications firm to establish meter connection to network. Telecommunications firm to commission network once meters have been connected by contractor. Contractor to commission meter.
Through a cyber secure cellular connection, the Contractor shall provide five (5) years of clouded 15-minute power and production data accessible to the government through a dashboard.
Government Meter Specification
a. Provide revenue grade meters capable of measuring interval data at 15-minute increments and storing data at least one year.
b. Provide power meter to record, at 15-minute intervals:
1. Power (kW)
2. Production (kWh)
3. Phase Voltage
4. Power Factor
c. Coordinate with and provide support to FWS IT personnel in order to establish cyber-secure communication with each solar PV system power meter.
d. Indicate Government meters on both review and as-built drawings sets.
e. Test and demonstrate complete power monitoring system operation to location facilities and IT personnel Identified by FWS.
The power meter shall be submitted to Government IT Security personnel to determine if that meter has been scanned and has an acceptable remediation plan with the manufacturer. If not, the Contractor must:
a. provide a meter temporarily for FWS to scan, with complete configuration information
b. If the meter is determined to have vulnerabilities, an alternative meter shall be proposed by the
Contractor
C.18 PROJECT MANAGEMENT REQUIREMENTS
C.18.1 MEETINGS
A kickoff meeting shall be held at the start of the design and construction phases after the contract has been awarded.
The Contractor shall meet with FWS managers on site or virtually as necessary to complete the work of this project. Meetings are anticipated to include, but are not limited to, an in-person overall kickoff meeting at the location, 100% on-site design review meeting and weekly virtual progress meetings during design and construction. Additional meetings may be required in response to particular problems or issues that arise. The Contractor and the Government should reasonably and efficiently synchronize meeting locations for both sites so that Contractor and Government personnel traveling to meetings may attend multiple meetings in one trip.
The DOE/FEMP representatives will create minutes for each meeting, circulate for comment within two working days of the meeting, and finalize within two working days of receipt of comments.
C.18.2 SCHEDULE MANAGEMENT
In addition to the overall project schedule which must be approved before notice to proceed is granted, the Contractor must submit for approval:
1. Any revisions to the overall schedule for each site.
2. A week-ahead schedule must be submitted by Thursday of each week for the next week, when construction activity is anticipated for the next week.
3. A request must be submitted two weeks in advance for any activity which requires an electrical or other service outage. Such outages must be scheduled off hours or at times selected by FWS management and must not disrupt agency activities.
C.19 PROTECTION OF EQUIPMENT TO PREVENT DAMAGE
Under no circumstances shall any Contractor personnel walk or lean on PV System equipment or in any other way impose additional loading on PV System Modules, Racking, or equipment. If it is determined that the Contractor damaged PV System equipment, the damaged equipment shall be replaced at the Contractor’s expense. The Contractor shall not be responsible for equipment that have been damaged previously by others, prior to the start of the Contract.
C.20 DESIGN AND CONSTRUCTION STANDARDS
C.20.1 GENERAL
The Contractor shall be responsible for the professional quality, technical accuracy, and coordination of all investigations, evaluations, drawings, testing, cost estimating, submittals, written reports, construction, operations, and all deliverables as required by this Scope of Services document or as required to complete the work of this contract. The Contractor is responsible for verifying all information provided by the Government.
Prevention of harm to person, research, plants, animals and property from fire, electrical hazards or structural deficiencies shall be a priority consideration in all design, construction, and system operation.
C.20.2 CODES AND STANDARDS
The PV systems at both sites shall comply with the most recent version of the following codes, standards, and regulations:
• The National Electrical Code (2017)
• SEAOC
o SEAOC PV-2-2017
• ASCE
o ASCE-7-16
• IEEE
o IEEE 1547 o IEEE 2030
• IEC
o 62109 (2020) o IEC 61215-1 or 61215-2 o IEC 61730 o IEC 62093 o IEC 62548 o IEC 62446-2 (2020)
• UL
o UL 1741 o UL 1703 o UL 2703 o UL 4703
• ANSI
o ANSI C.12.1 (electricity metering)
• DIN
o DIN 25201
C.20.3 GENERAL ENVIRONMENTAL REQUIREMENTS
As part of construction planning, Contractor shall provide, at the Contractor’s sole cost and expense, the following detail in the “required implementation plan”
1. Hazardous Materials/Due Diligence – The Contractor shall indicate if any hazardous materials will be disturbed, encountered, or used in the construction of the PV systems. The Contractor shall provide all appropriate mitigation measures, if required, to reduce impacts to insignificant levels.
2. Storm Water Runoff Management – The Contractor shall provide sufficient documentation to demonstrate that the requirements of Energy Independence and Security Act (EISA) section 438 are being met. The Contractor shall not change the pattern of storm water amounts or runoff. If the project involves digging/trenching in soil of an area more than 50 linear feet, the Contractor must provide an erosion and sediment control plan. The contractor shall restore predevelopment hydrology where more than 5,000 SF is disturbed.
The Contractor shall comply, at its sole cost and expense, with all Environmental Laws that are or may become applicable to the Premises or the Contractor's activities on the Premises, including but not limited to all applicable Federal, state, interstate, and local laws, regulations, and other requirements relating to occupational safety and health, the handling and storage of hazardous materials, and the proper generation, handling, accumulation, treatment, storage, disposal, and transportation of hazardous wastes. The Contractor shall at its own expense maintain in effect any permits, license or other Governmental approvals relating to Hazardous Substances, if any, required for the Contractor’s use of the Premises. The Contractor shall make all disclosures required of the Contractor by any such Environmental Laws, and shall comply with all orders, with respect to the Contractor's and its employees', agents', Contractors' and invitees' use of the Premises, issued by any Governmental authority having jurisdiction over the Premises and take all action required by such Governmental authorities to bring the Contractor 's and its employees', agents', Contractors' and invitees' activities on the Premises into compliance with all Environmental Laws affecting the Premises.
A. The disposal of any toxic or hazardous materials within the Premises is strictly prohibited.
B. If the Contractor discovers any hazardous materials or hazardous wastes at the Premises of any kind, in, on, under, about or migrating from or onto the FWS properties, the Contractor shall immediately stop work, take measures to reduce exposure to all Contractor site personnel, notify the Government of such condition and location and shall ensure access to the site of discovery is restricted until appropriate response activities have been completed, and any required notifications are made to State and/or Federal environmental regulatory agencies. Contractor will not further disturb the site of the discovered hazardous materials or hazardous wastes without the written permission of Government.
C. The Contractor shall immediately call 911, the COR, and the FWS Safety Environmental Officer
Sean Brophy at 209-587-0369, Sean_Brophy@fws.gov; on any state, local or Environmental Protection Agency (EPA) reportable spill of hazardous substances or materials, and oils or other petroleum pollutants. The Contractor shall then institute appropriate spill control measures/procedures as soon as possible. The Contractor is responsible for all spill mitigation/cleanup expenditures associated with the spill/release.
C.20.5 HISTORIC PRESERVATION
The Contractor shall not remove or disturb, or cause or permit to be removed or disturbed, any historical, archeological, architectural or other cultural artifacts, relics, remains or objects of antiquity. In the event such items are discovered on the Premises, the Contractor shall immediately notify the Government and protect the site and material from further disturbance until the Government gives clearance to proceed.
mailto:Sean_Brophy@fws.gov
C.20.6 ENVIRONMENTAL, SAFETY AND HEALTH MANGEMENT (ES&H)
A. The Contractor shall assure the Government that its designated environment, safety and health (ES&H) manager is knowledgeable in applicable Federal, state and local ES&H requirements. The Contractor shall assure Government that its Subcontractors and employees are trained in, familiar with, and comply with Contractor’s ES&H policies, procedures and standards.
B. The Contractor shall notify the Government's Authorized Representative within two hours of any employee injuries/illnesses at the Premises requiring medical attention in excess of first aid, or incidents at the Premises that result in damage to equipment or facilities, or threats or impacts to the environment.
C. The Contractor shall suspend operations at the Premises and immediately notify the
Government's Authorized Representative if unanticipated conditions are encountered that present a possible ES&H exposure (e.g., imminent danger, suspected hazardous materials, accidental release of hazardous material, possible archaeological sites). Contractor must inform all its workers and Contractors that they have stop-work authority when these conditions are encountered. A hazard assessment must be completed, and appropriate controls identified to mitigate the identified hazard(s) prior to beginning work.
D. The Contractor shall conduct activities on the Premises within the scope of any environmental assessments and determinations made by the Government pursuant to the National Environmental Policy Act (NEPA). The Contractor shall not initiate any construction or take any other irreversible actions until the Government issues a NEPA clearance. If changes are anticipated to the scope of activities as described in the applicable NEPA documents and determinations, or if the scope of activities is desired to be expanded, the Contractor has a continuing notification obligation, and shall notify Government of any proposed changes.
Requirements for additional NEPA documents or determinations shall be determined on a case-by-case basis. The Contractor shall provide information as requested to support any future NEPA determinations.
E. DUST CONTROL: During construction, dust is inevitable in certain remodeling operations;
therefore, the contractor shall make a concerted effort to control airborne dust particles as indicated by the contract and/or applicable Federal, State, and Local regulations.
F. ENVIRONMENTAL PROTECTION: The contractor shall provide and maintain environmental protection during the life of the contract as defined herein. Environmental protection shall be provided to correct conditions that might endanger the environment during construction operations.
G. EROSION AND SEDIMENT CONTROL MEASURES:
1. BURN-OFF: Burn-off of ground cover will not be permitted.
STORMWATER POLLUTION PREVENTION: The contractor shall take all steps necessary to prevent pollutants from coming in contact with stormwater discharge. The most significant high-risk areas for stormwater contamination must be identified by the DOI and the contractor prior to commencing work. Preventive measures and best management practices (BMPs) shall be developed and implemented in potential risk areas.
CONTROL AND DISPOSAL OF SOLID, CHEMICAL, AND SANITARY WASTES: Wastes shall be placed in closed metal containers, which are emptied on a regular schedule. Handling and disposal shall be conducted in a manner to prevent contamination of the site and other areas.
DISPOSAL OF RUBBISH AND DEBRIS: Materials defined in paragraph a. (3) and a. (4) above shall be disposed of OFF FWS PROPERTY.
(a) In the event the contractor or subcontractor should dump rubbish/debris at any area of FWS, the contractor shall be required to retrieve this rubbish/debris and dispose of OFF FWS PROPERTY to a certified landfill.
(b) The contractor shall provide proof of an approved, certified landfill prior to the removal of lead containment materials and asbestos material. All dump tickets from the approved landfill shall be provided to the COR.
(2) GARBAGE: The contractor shall dispose of all garbage OFF FWS PROPERTY. Garbage shall be kept in sealed metal containers and disposed of daily. The preparation, cooking, or disposal of food on the project site is strictly prohibited.
(3) SEWAGE, ODOR, AND PEST CONTROL: Chemical toilets or comparably effective units shall be utilized in accordance with Federal, State, and Local regulations. Wastes shall be periodically collected and removed from the site by a licensed sewage disposal contractor.
Measures shall be taken to control pests and to mask or eliminate undesirable odors. Chemical toilets shall be cleaned/serviced by a licensed company at least every 2 weeks.
(4) DISPOSAL OF HAZARDOUS WASTE: Materials defined in paragraph 2-20 a. (7) shall be disposed of utilizing the following guidelines:
a. Hazardous waste must be disposed of at an EPA approved Treatment, Storage, and Disposal Facility (TSDF) in accordance with applicable Federal, State, and Local regulations.
b. Prior to transporting waste off-site, the contractor must:
[2] If applicable, provide a copy of the TCLP results from analysis performed to identify the waste as hazardous (e.g., lead concentrations above 0.5 mg/l).
[3] Notify the FWS Environmental Compliance Officer twenty-four hours before hazardous waste is to be removed from the site to ensure someone will be available to check the shipment and sign the appropriate paperwork.
c. To transport the waste off-site, the contractor must: Provide a completed Hazardous Waste Manifest and its supporting documentation to the Environmental Manager’s Inspector during the loading of the transportation vehicle. If the shipment is approved, the Environmental Manager’s Inspector will sign the Manifest and supporting documents. All waste will be transported in accordance with Federal, State, and Local Department of Transportation regulations.
Provide appropriate copies of the Hazardous Waste Manifest and supporting documents to the Environmental Manager’s Inspector.
Note: If the shipment is not approved, the Manifest will not be signed, and the material may not be removed from the site. All cost incurred due to an unapproved shipment will be the responsibility of the contractor.
e. LEAD CONTAMINATED MATERIALS: Debris containing lead contamination at 0.5 mg/l or higher, determined by either analysis prior to or after demolition/renovation, must be handled as Hazardous Waste in accordance with paragraph 2-20 d (4) above. Transportation of this material off-site must be accomplished by an approved DOT method. In most cases, lead contaminated debris will be placed in a sift-proof, roll-off container or trailer, covered by a secured tarp. As stated above, if shipment is not approved due to improper methodology or inadequate transportation vehicle, the Manifest will not be signed, and the material may not be removed.
Costs incurred for the delay in shipment will be the responsibility of the contractor.
g. CLEAN AIR/CLEAN WATER: The contractor shall not utilize equipment that has emissions which exceed limitations under the Clean Air Act and the facility’s Title 5 Permit. Steps shall be taken to prevent the discharge of pollutants into or on any land or water.
TRUCK HAULING ON FWS property: The contractor shall be responsible for covering open-bodied vehicles that are transporting sand, gravel, fill materials, dirt, construction debris and any other material which may become airborne and/or possibly create air pollution while on FWS property.
[END OF SECTION]
C.21 CONTRACT PERFORMANCE DELIVERABLES
Submittal Items – This list is intended to be a guide but may not be all inclusive. A specific separate supporting RFP section is not required to establish these submittal requirements.
Description Submittal Timeframe Recipient of Deliverable
Insurance Certificate Upon Award COR / CO Responsible Supervisory Personnel List Within 3 business days
COR / CO
Copy of interconnection application (s) submitted
2 weeks after award COR / CO
Safety Plan 2 weeks after award COR / CO
Product Cutsheet – Module, Inverters, and racking
Submit with 35% Set COR / CO
System sizing factors Total array STC Rating Array Tilt Array Azimuth DC to AC conversion losses (%) Losses (%) from inverters to contracting billing meter.
Losses (%) from billing meter to point of connection to
Government electrical distribution system(s).
Submit with 35% Set COR/CO
Product Cutsheet – Switchgear and transformers Submit with 75% Set COR / CO
Photographs, material samples, renderings, and/or architectural elevations as necessary to understand aesthetic impact of proposed system.
With 95% Submittal COR / CO
All low voltage wiring; communications, metering, meteorological instruments and fault detection/alarming systems shall have separate diagrams/drawings
With 95% Design
COR / CO
Photographs, material samples, renderings, and/or architectural elevations as necessary to understand aesthetic impact of proposed system.
With 95% Design Submittal
COR / CO
Construction Drawings Stamped:
Electrical Structural Civil
With 100% Design Submittal
COR / CO
Detailed project schedule With 100% Design Submittal
COR / CO
Copy of permit applications (If local building official will review)
With 100% Design
COR / CO
Location of underground utilities after site verification using professional utility locating service and Call 811.
Prior to commencement of
SOLAR PV SYSTEMS
installation
COR/CO
Accident Reports As needed – During Construction and
Contract Term
COR / CO
Material Safety Data Sheets Before bringing product onsite
Vehicle Registration; plate number, make, model and year. Parking passes to be issued after registration if required by location
Prior to Commencement of work COR/CO
“As-Builts”, including:
String labeling on drawings keyed to match combiner or inverter box labels.
30 Days Post Construction Completion
Commissioning Report per IEC 62446
Post Construction Testing
COR / CO
Training Materials (including video recording of live training) for Site Operations Staff.
Completion
COR / CO
Operation and Maintenance Manuals for all PV equipment.
Completion
COR / CO
PG&E’s permission to interconnect correspondence (if sent to the Contractor rather than the agency) accepting the PV system and grid tie-in and granting permission to feed electrical power into the local utility electric power grid.
Prior to Government acceptance
Construction Completion
COR / CO
PV System component warranties with manufacturer’s contact for the remaining period.
Prior to Government Acceptance COR / CO
[END OF SECTION]
| C.1 General description of the work |
| C.2 Location of the work |
| c.3 INTERCONNECTION REQUIREMENTS |
| c.4 SITE CONDITIONS |
| C.5 - Engineering and Construction |
| C.6 - Products, Material, and Service Requirements |
| c.7 – Battery Storage “Ready” Design |
| c.8 Module Safety, Quality & Long-Term Performance |
| c.9 Wire, Cable And Conduit Management |
| c.10 Minimum Permanent Signage and Labeling |
| c.11 preventing vandalism and theft |
| c.12 Standards for Drawings |
| c.13 Submittals and submittal review process – post award |
| C.14 - System Startup and Commissioning |
| c.15 WARRANTIES |
| c.15.1 Total Array Output Warranty |
| c.15.2 Linear Module Warranty |
| c.16 Personnel Qualifications |
| c.16.1 National Association Of BOARD-CERTIFIED Contractors (NABCEP) Certified Installers |
| c.16.2 Professional Engineer and Licensed Design Professionals |
| c.16.3 Project Manager |
| C.16.4 Registration seals |
| c.17 PV SYSTEM MONITORING |
| c.18 PROJECT MANAGEMENT REQUIREMENTS |
| c.18.1 Meetings |
| c.18.2 Schedule Management |
| c.19 Protection of Equipment to Prevent Damage |
| c.20 DESIGN AND CONSTRUCTION STANDARDS |
| c.20.1 General |
| c.20.2 Codes and Standards |
| c.20.3 General Environmental Requirements |
| c.20.5 historic preservation |
| c.20.6 environmental, safety and health mangement (Es&H) |
c.21 Contract performance deliverables